Munster Hamlet is a pocket
of development in the far reaches of Goulbourn noted for
only two things: First, its odd name and, more
important, its sewage.
City councillors, and their
predecessors at the regional government, have been
trying since 1996 to find an acceptable way to replace
Munster's leaky sewage lagoons.
Up until this week, the
short version of the story was $6.2 million spent and no
solution.
In its quest, city staff
has racked up consultants' bills for $1.6 million,
producing a mound of reports more than a foot high. The
city favoured a sewage pipeline as the solution, but
that plan was taken to the Ontario Municipal Board,
where the city was told to re-evaluate alternatives. The
city appealed the OMB decision in court and lost.
While all this was going
on, the city has been hauling sewage out of Munster at a
cost of $500,000 a year, under threat of being charged
by the Ministry of the Environment for problems with the
defective sewage treatment system.
So after all that, it was
a bit of a surprise Tuesday to see the city's
environmental services committee approve a pipeline to
solve the sewage problem, all without a minute of
debate. All it took was an impassioned speech by
Councillor Janet Stavinga, who represents Goulbourn.
The pipeline solution
ought to have led to some probing discussion, because
it's almost certainly the most expensive of three
alternatives. Last December, an independent consultant
the city was compelled to hire as a result of the OMB
hearing determined the pipeline and two types of on-site
treatment plants would all do the job, but the on-site
plants were preferable because of the pipeline's cost.
That seemed to be the
wrong answer, from the city's perspective. The same
consultants were asked to look at the matter further,
and come up with some new numbers.
The massaging the
consultants and city staff have produced to show the
merits of the pipeline solution is magical to behold.
Capital costs were added to both the other alternatives,
although the companies that were actually going to
provide the treatment plants say their offers include
all costs.
The pipeline originally
was shown as costing between $6.1 million and $7.1
million, approximately twice as much as the two
alternatives. Adding new capital components to two of
the solutions brought the costs closer together, but
there was still a gap of $1 million to $2 million. City
staff closed that further by adding its opinion on
expected operating costs. Over a 20-year term, the
pipeline was still most expensive. Over 60 years, the
three options are neck-and-neck, but over 90 years, the
pipeline is the cheapest.
Over the years, the city
and its consultants have offered pipeline costs ranging
from $5.8 million to $14.6 million. The figure cited now
is still a guess since the project hasn't been tendered.
Staff thinks it can figure out how much the three
systems will cost to operate over 90 years? That's a
stretch.
This looks like more than
yet another chapter in an old story at the city. The
private sector is invited to bid on public work, but in
the end, government decides to do the job itself because
the table is tilted against the private companies, or
the city simply refuses to accept anyone else is
competent.
Seprotech, one of the
companies offering on-site treatment, involves
technology already in use in 400 locations. The city has
agreed to a small pilot project in Manotick using the
same system. The other company, Northern Watertek, was
ranked first by the consultants.
In the end, staff says
there is just too much risk with the private sector
solutions. Even if the companies guarantee cost and
results and back it up with a letter of credit, it still
isn't good enough. The city already has sewage
pipelines, and is more confident in that answer. The
other factor is the province's environmental assessment
regulations. It appears that either of the on-site
treatment plants might trigger another assessment
process, although one would think that could have been
negotiated with the Ministry of the Environment, which
is eager for a solution.
The decision-making in
this matter is exceptionally complex, because it
involves conflicting consultants' reports, city staff,
popular opinion and political decision making. Staff
says its pipeline recommendation is simply its best,
disinterested professional advice. That may be true, but
the fact the city has been fighting to get the pipeline,
and Munster residents apparently favour it, would tend
to colour the outcome. Stavinga has been pushing this
matter hard, and doesn't want more delays. It's a pity
even after numerous studies and reports, the city still
can't make a convincing case for the pipeline. The
numbers it has shown to support that choice are pretty
creative. The weakness of the city's argument has
encouraged the proponents of the other two technologies
to seek further action, either in court or at the OMB.
The meter's ticking, and this one isn't over yet.
Contact Randall Denley at
596-3756 or by e-mail,
rdenley@thecitizen.canwest.com
© Copyright 2003 The Ottawa
Citizen