CITY MISREPRESENTATIONS
MISREPRESENTATION #1:
It’s OK to
pollute …just use a bigger river to dump it into.
Councillor
Clive Doucet:
“I’m not
sure I understand it. We want to take Munster sewage 60 km. to
ROPEC, to treat it only to secondary level, then discharge into
the Ottawa River; when we have the alternative of an on-site
treatment plant that would treat Munster’s wastewater to tertiary
level, for local discharge into the Jock River. What am I
missing, here?”
Dave
McCartney, P.Eng., Operator of ROPEC:
“You have
to understand that the Ottawa River is a very large
receiver. It can easily handle the excess nutrient.”
Educated
Public Response:
Daah! The
City of Ottawa should be moving briskly in the direction of
tertiary treatment of its sewage. Edmonton and Calgary are
shining examples of enlightened cities that have already done
that. Ottawa, which is not heavily industrialized, is going in a
retrograde direction ---further and further away from the goal of
tertiary treatment. Now, the City is even planning to pipe Trail Road leachate to ROPEC for pass-though to the Ottawa River with minimal
treatment, instead of using modern on-site treatment technology,
at Trail Road.
Dilution
should not be used as the solution to pollution.
Everyone
is downstream!
It has been a
huge mystery to environmentally conscious citizens why the
Ministry of the Environment (MOE) idly sits by while all this is
happening.
_____________________________________________________________________________
MISREPRESENTATION #2:
“Diversion
of the Munster effluent is not significant to the Jock River,
because it only represents 0.2% of the average annual flow of the
river.”
Educated
Public Response:
The bulk of the River’s flow
obviously occurs during the spring “run-off”. From the peak flows
in the spring it plunges to a small-sized stream for the remainder
of the summer. In the last four years, in the Munster area, the
Jock River has ceased flowing ---entirely--- in
the period between late June and early September.
The fish kill
has been atrocious during such times as the isolated puddles dry up.
Clearly, any steady flow from a treatment plant in Munster, (even
if it reaches a low of 250 M3/day) would still
represent 100% of the flow of the Jock River ---at that
time--- and would be sufficient to maintain a healthy aquatic
habitat in the river.
The relative
proportion of river flow is not the measure used by professionals to evaluate the
effect upon river systems. The 7Q20 is a measure of the lowest
flow over a period over 20 consecutive years. Anything over the
observed 0-flow in the Munster segment of the river would
therefore be regarded as a benefit. Any competent engineer, versed
in such matters, will more correctly refer to the “7Q20”, rather
than the figure of “0.2%, or 1/500th of average flow”,
and, in looking over the data would very quickly verify the
pivotal benefits of Munster's highly-treated effluent to the Jock
River eco-system.
Similarly, anybody who supports
the negative environmental impacts of the pipeline option over the
environmentally protective
features of the
mechanical treatment option, in terms of significance to the
health of the Jock River ...cannot honestly claim to be all that
interested in environmental concerns. (Sadly, the Goulbourn-Ward 6 Councillor
appears to be including herself in that group.)
_____________________________________________________________________________
MISREPRESENTATION #3:
“The pipeline only requires use of a lagoon in Munster for one
week per year.”
Educated
Public Response: Several experts
have declared that the forcemain could not possibly operate
without use of a full-time retention lagoon. There is just too
little flow in the summertime to send raw sewage by an 11 km. forcemain
to Richmond. It would become blocked, in very little time, if
solids are not retained in lagoons and only the supernatant liquid
sent through. Knowing that Munster residents desperately
wanted to be rid of the offensive and problematic open sewage
ponds on their doorstep, the City has consistently lied about its
full-time lagoon
requirement
for a pipeline.
_____________________________________________________________________________
MISREPRESENTATION #4:
“The pipeline can be completed in the shortest time. The communal
options will take 12 to 18 months longer to complete.”
Educated
Public Response: Some of the
members of the Public Liaison Committee requested (in 1998) that
a
"time to
implement"
component be included as one of the unit values, in the evaluation of the options.
It
fell on deaf ears. Since it was admitted by the City (RMOC), at
that time, that
a pipeline
would take longer to construct,
they apparently omitted the time consideration, entirely, so as
not to put their
pre-determined pipeline at a disadvantage.
The City has
argued that a full Environmental Assessment would be necessitated
by the selection of either of the communal options. This has no
basis in fact. Any of the options (including the pipeline) ---with modifications (such as
a switch from forcemain to gravity sewer through Richmond) would
require an Addendum to the
EA, which is roughly a 2-month process. (Ref:
Class EA Planning Process, Part A.4.2.2, Change in Project or
Environment).
Another of the
City’s arguments, is that the communal options would be challenged
…causing further delay. This seems an absurd argument since both communal
options were received as qualified,
conforming RFP bids, (while
the pipeline "proposal" was illegitimately inserted into the RFP,
even though it did NOT conform in any way with the RFP's clearly
stated requirements). Also, there is nothing in EA convention that
would give cause to entertain a Bump-up Request on an
environmentally beneficial system.
What the City has not been
forthright enough to disclose, is that ---short of paying hefty
reparations to both communal bidders, making the pipeline costs
even more extravagant--- the only proper way to remove the
serious, pending, litigation over its RFP “irregularities”
(relating to the pipeline), is to proceed with
one of the two communal options,
as recommended in the $179,000, RV Anderson Report
(December 16, 2002).
Therefore, a pipeline selection would result in far greater delays
(perhaps several more years), if the City keeps trying to
short-circuit due process, let alone its legal responsibility to
work in the
public interest. For City officials to assert that the
pipeline would not create the greatest interruption and delay
---by far--- is quite plainly: dishonest.
(More to follow from
transcripts of Committee Meeting tape.) |