| |
(Highlighting added)
Transcript of Munster portion of
Ottawa City Council Meeting June 11, 2003
00:00 –
Mayor Chiarelli:
The next held item is held by Councillor
Stavinga, page 16: Munster Hamlet Wastewater Treatment Facility
Re-Evaluation of Alternatives and Recommended solution.
00:20 –
Councillor Stavinga: Thank you very much Mayor Chiarelli. ...Just had a series of
questions that I wanted to ask of our staff, with regards to this
item. As my colleagues are aware, that this was passed at
Environmental Services Committee, at a vote of 7 to 0 in support
of the staff recommendation. But regardless of that strong support
by Committee there has been quite a bit of correspondence we have
each received from various proponents as well as from residents
within the community of Goulbourn, and I just have highlighted a
number of questions I would like staff to address, because
certainly they of concern to me, and I would like those answers,
too. The first one is with regards to the fact that both
proponents of the other
technologies, the on-site
treatment, in
their various
correspondence have
indicated that
they believe, ah,
the process
in terms
of the evaluative
process as seriously
flawed. And they
reference the issue with
regards to
information that they
have provided that hasn’t
been reflected. Costing is incorrect, and I
guess really to kind of pin-point maybe where…
I think at
one point they
were on
board, but now at this
point they
are not at
all. Is the RV Anderson
report that
was put
together, and we
had a
community meeting that was
advertised in the Goulbourn area, on December, in
December 2002.
01:42 - The recommendation from RV Anderson recommended the city
proceed with one of two communal (options), or on-site treatment
alternatives, that being the mechanical treatment plant, or Snowfluent technology. However the report also said that from an
environmental perspective, each of the three options had merit,
and presented acceptable methods for the treatment of Munster’s
wastewater. The report also identified distinct challenges
associated with each of the three options. So, with that coming
out of the RV Anderson Report, in December, and then the staff
recommendation coming forward to the Environmental Services
Committee, in May, one could say, "What happened?". So, if you
could clarify, I mean, certainly RV Anderson indicated there are
distinct challenges, that need to be further explored by staff,
but from Seprotech, as well as from Snowfluent specifically
they’re saying that evaluative process is seriously flawed. So if
you can please help us to understand how we went from that point,
to the point before us today.
02:46 –
Richard Hewitt:
Madame Chair, I think it’s important to recognize perhaps
stepping a little bit with regard to the initial work that RV
Anderson was hired to do. In fact, they were hired in accordance
with a direction that we received from the Ontario Municipal Board
in dealing with the Official Plan Amendment, to perfect the case
so to speak, or to reconsider the recommendations that had been made
in 19(9)8, 99 by Conestoga-Rovers Associates, a firm that had been
hired initially to do the Environmental Assessment Addendum to
previous work. So, what I’m trying to indicate, here, is, in fact
the initial work by RV Anderson, that culminated in their Report
in December of last year, was in fact related to very specific
guidelines given by the Ontario Municipal Board, and our intent to
try and satisfy that requirement. And that requirement was, in
fact, that (a) re-evaluation be done of the quantitative analysis
that had been undertaken by Conestoga-Rovers, and to undertake a
qualitative analysis of the options that had risen as potential
solutions. In so doing, in undertaking the quantitative analysis,
RV Anderson came to the conclusion that we had three viable
options: Two of them communal, one of them a pipeline.
04:04 –
Through evaluating Conestoga-Rover’s work, it came to
the conclusion that the work had been done fairly, and
appropriately, and that in fact we had three viable solutions.
However, in presenting that, they then moved on, and said "we also
have been tasked with undertaking a qualitative analysis, and from
the evaluation of the information that had been previously done
---and that was the scope of their review--- they came to the
conclusion that the pipeline was a more costly option. And
therefore, on that basis, they indicate in their recommendations,
in December, that the pipeline should be discounted as a potential
solution, and that the two communal solutions should be brought
forward. All three solutions, as I indicated, were considered to
be technically viable, all of them had certain issues related to
their application, but none-the-less, I’ll say promise in all
three. 05:03- Looking, then, at staff, at the situation with regard to
the fact that we were re-viewing with information that was in
essence was four years old, three to four years old, at that time, we
felt that it was important to make current information available
so that we could evaluate in the 2003 context, where we stood with
these options. 05:24 - And we have undertaken to do that since that time. And
that’s the work that we again hired RV Anderson to
undertake to assist us in evaluating the three options that were
before us. And in fact, in doing so, and in looking at what we
feel is the appropriate evaluation life-cycle, and that type of
thing, we came to the conclusion that really the cost issue was
not as indicated by RV Anderson through their evaluation of
old information, that our updating of information led us to
the conclusion that in fact the options we in the same ball park,
and that the pipeline actually came out certainly in the range,
and potentially slightly cheaper.
06:01 –
Councillor Stavinga:
OK, well just maybe to clar…, because it seems that in terms of
potentially cheaper, and I, again this is something that’s really
been, meets the proponents of the on-site technology have
highlighted, that , if you did it by the lifecycle cost of 20
years, the on-site treatment were the ones that emerge as seeming
the most preferable, recognizing that from a technical perspective
all three of them could have been there. But what staff ended up
doing in their own analysis with the additional work that was done
by RV Anderson, was to look, then, at a 60 to 90-year horizon. And
then the question that arises, is, have we ultimately, then, skewed the result in such a way that we get our, the desir--- an outcome that actually favours a pipeline. So, the question is,
is it truly reasonable to forecast to the 60 or 90 horizon for
life-cycle cost, as it relates to the pipeline, and then
extrapolate that to the other two?
06:57 –
Richard Hewitt:
Well, I would certainly suggest that in terms of trying to
provide fairness in evaluation, that we need to look at the
expected life-cycle of the options that are before us. And
certainly, a 20-year time frame is probably reasonable to
consider before major re-habilitation would be required of
mechanical plants, but that is by no means a reasonable time span
to consider a pipe option, which is obviously a somewhat more
simple approach. In fact, if one looks at the direction that
cities are moving, and are actually being required to move by
incoming legislation, such as Bill 175, where we are moving
towards life-cycle evaluation and life-cycle costing of our
infrastructure, in fact it is incumbent on us to look at longer
term life-spans to properly evaluate the overall cost, both
capital and operating, over the period of time that you expect
that infrastructure to be in service.
07:52 –
Councillor Stavinga:
Another, while taking the life-cycle cost of that, and saying
that, yes, it is reasonable to do the extrapolation to the 60,
90-year time horizon, well the next question is, that the,
particularly, I mean, you hear it from the representatives of
Snowfluent, but also, the latest is Seprotech, specifically saying
that they have over 400 on-site wastewater treatment plants in
communities across North America. What is the problem with the
fact that they can’t do it in Munster? I mean, if they have
the ability to do it in 400 communities across America, why is
Munster, why is the community of Ottawa, so different that it
would not be appropriate, in the sense of just a general
extrapolation of what they’ve done in other areas. Why is this a
different situation?
08:43 -
Richard Hewitt:
Well, I think it’s fair to say that most of the applications
are likely different in certain respects. I think what we
obviously have most familiarity with is the one that’s before us
with Munster. And, what we can say is that while we certainly
recognize that technology as being well accepted, it has not been
proven to meet the criteria that have been imposed on us by the
Ministry of Environment in the case of the Jock River which would
be the receiving water in this case, which is classified as a
class-2 water. And as a result, we have certain criteria that we
have gone back to the ministry with on a number of occasions to
ensure that they have no leeway in terms of their requirements,
and have been told categorically that in fact the requirement they
have imposed on us have to be met. And in fact, with regard to the
other applications, so far as we are aware, and certainly have
given the proponents of the various technologies every opportunity
to provide us with information as well: there is no demonstrated
case of that type of technology meeting the discharge criteria
that are imposed on us, in this case, in an operational
environment.
09:53 -
Councillor Stavinga:
So, if I’m understanding correctly, even though they’re
working, right now, in over --- Seprotech is working over, in over
400 on-site wastewater treatment plants in Canadian, and across in
North America: none of those have shown to be able, or have
demonstrated in consistent manner, to be able to meet the
requirements that are specific to discharging to a Policy 2 river,
that being the Jock River, of .03 mg/ Litre of Phosphorus,
correct?
Richard Hewitt: That is correct.
Councillor Stavinga:
OK. Now just, the fact is CMS is now taken over by Seprotech,
we, I mean we do have a facility that we’re trying to get, it’s my
understanding--- it’s not up and running yet, it’s not operational
in Manotick. So, if we’re already testing that sort of technology
in Manotick, why would we not do it in Munster?
10:38 - Richard Hewitt:
Well, I think the key word there is, in fact, "testing", or
what one might term a "pilot". First of all the scale of the
facility in Manotick is much smaller. So, we’re dealing with a
system that if remediation is required, and certainly the criteria
are the same, I believe, the potential solution would be far
simpler to implement in terms of an add-on type of approach to
resolve the issues of non-compliance, and that system is in fact,
considered to be a pilot system. And it is very small in nature,
and it does not fit into the situation that exists in Munster. And
here we’re dealing with a community with an existing ---an
existing community obviously with a sewage treatment problem that
has been in existence for many years: one that the Ministry is
very keenly aware of, as are we, and we are under voluntary
compliance with the Ministry now, where we feel we need to move
forward with a
robust, and capable technology that we feel
is suitable to resolve the issues and get the community back
getting the level of service that the rest of the city gets.
11:44 -
Councillor Stavinga:
Again, just a couple more questions, Mayor Chiarelli: One, that
again, that’s continuously coming up, and it really truly concerns
me, although we talked about it at Environmental Services, again,
it came on the emails from last 48 hours, that all of the
Councillors received from again Seprotech as well as Snowfluent,
the continuous statement that, that they have sent information,
they have provided documentation to RV Anderson, under, when they
were preparing their report, as well as in preparation for the
Technical Memorandum: but none of that , none of that
information is actually reflected in what’s being provided to
staff and then through to our committee. And that’s a concern.
So, is that the case? Is there new information that has not been
reflected in here that would actually change our decision?
12:32 -
Richard Hewitt: Well, certainly, none of the information that has been provided
of late is any different than information we had received. The
proponents were all invited to submit information to us, and some
of them took advantage of that, and provided us with as recent
information as they could. In some cases we received nothing
new from information that had been obtained previously by
Conestoga-Rovers, back in the late 90s, and we did our evaluation,
based on that. We feel that we were consultative and
collaborative with them. We obtained the information that they
could give us, and we have utilized that information. I think the
conclusion we have reached is perhaps different than they would
prefer, and therefore there seems to be some concern about …about
that aspect, but I have seen all of the information that has come
in, as recently as yesterday and today. And, I feel comfortable
that we have addressed that information in our evaluation.
13:19 –
Councillor Stavinga:
There’s ongoing concern with respect to the fact that, what
will be happening with the pipeline, is the transferring of water.
That (the) Jock River already has a problem in the summer months
with regards to maintaining its base flow, and that what we’ll be
doing is actually transferring water out of that particular
sub-watershed, into another watershed. I appreciate your comment
upon that, as it relates to this environmental impact on the Jock
River.
13:46 -
Richard Hewitt:
Well, I think there are two issues that have to be kept in mind
here. One is that we’ve certainly confirmed that the aquifer that
is providing well water to, or water to Munster, is in fact coming
from another watershed, so in fact is
not local surface water.
And, in fact that other aspect that we need to remember, is the
order of magnitude here is negligible in relation to the overall flow of the Jock River.
14:10 -
Councillor Stavinga:
Another, with regard to cost of the pipeline: There’s reference
to the Totten-Simms and Hubicki Report, which was the first
Environmental Assessment that was conducted by the Region. This is
back actually under the leadership (at) that time, Regional Peter
Clark. It goes back quite some time. But it had a range of the
capital cost for the pipeline being anywhere from 11 to
12-million, 13-million dollars. How can technology possibly
advance so much, where we’re actually now seeing, a total
anticipated capital cost of 7.1 to 8.1? Is it a technological
change, or where there certain assumptions that Totten-Simms
Hubicki made, in their 11, to 12 or 13 million, that we haven’t
factored in. In other words have we underestimated the capital
cost of the pipeline? Why the disparity in numbers?
14:54 -
Richard Hewitt: No, I don’t believe we have underestimated the cost, and I
would certainly suggest that with regard to the Totten-Simms
Hubicki, information, which one must remember is coming close to
a decade ago, that that work was undertaken. There was
assumptions made with regard to the system, overall. And one of
the major assumptions that was made is that there would have to
be major upgrades made to the Richmond Pumping Station in order to
handle the Munster flow. That in fact is not the case, and that
was many millions of dollars that was included in the estimate, I
believe around 7-million, ah, included in the estimate at that
time, to ah, …which was attributed, of course, to the pipeline
option.
15:33 -
Councillor Stavinga:
And that’s not needed? Why would that not be needed now, then,
if it was needed back with Totten-Simms Hubicki?
15:35 –
Richard Hewitt:
Well, I think that was based on an assumption on their part, at
the time, which later investigation has proven is not required,
and that in fact the Richmond pumping station has been found to
be of sufficient capacity to handle the flows that would be
coming from the Munster pipeline.
15:48 - Councillor Stavinga: OK. And Mayor Chiarelli, just with your patience, there’s just
three other questions that I have. The next question, third from
the last one, with regards to construction and the operation of
the pipeline, there’s a real concern by residents within the
neighbouring communities, those residents who are along the
pipeline route: a pipeline route that was decided through a public
process back in 1999, and went through Public Liaison Committees,
and community meetings, and such. But there’s still this
underlying concern that there is a potential for, and I quote from
one documentation, "a potential for a catastrophic contamination".
This is a real concern for those residents who are along the
route, who do have shallow wells. I mean, they’re not hooked up to
the water system like other areas, so they do have shallow wells.
My question to you is with regards to that potential happening,
both with respect to construction of the pipeline, and the second,
in fact, the long-term operation of the pipeline?
16:45 -
Richard Hewitt:
And we certainly appreciate the concern. We recognize that any
new infrastructure application put through existing communities
carries with it the concern of residents of disruption. There are
a couple of aspects, though, that I think we must consider in
doing so. First of all, while there are many wells in Richmond,
certainly Richmond already has sewer systems, and there are pipe
systems under, under the …in the rights of way already in
Richmond. And, quite frankly, with older systems, I would think,
you know, that is always a concern as well. But we are looking at
a modern construction of a properly constructed polyethelyne
fused-connection pipe, potentially going through the Village,
if we stay with a forcemain situation. We’re going through
rights of way. We will certainly as part of our final routing
review, and our selection, take into consideration the proximity
of wells and look at the existing situation in Richmond Village.
I’d also point out that in fact, our final design may allow for
gravity sewer, which is non-pressurized, of course, going through
the Village. We haven’t yet determined whether that is fully
possible, but it appears to be at a preliminary design point.
17:54 -
CouncillorStavinga: And again, just to clarify, gravity sewer is already there
within the Village of Richmond, right now.
Richard Hewitt:
Exactly, Very similar.
17:59-
CouncillorStavinga: And there’s two final questions: one is for you, Mr. Hewitt,
and then the final one is for legal department. I mean, I have
been charged with this too, and I just… It’s interesting, so I
asked of this. Because, interesting enough, I have been throughout
this process, although not from the very beginning of time,
because I was a Stittsville Councillor at that point, and not the
representative for either Richmond or Munster. I got on board
actually when I was the Mayor of the Township of Goulbourn. But I
was certainly part of the deliberation under the former Mayor,
Paul Bradley, when the Totten-Simms Hubicki Report came forth. But
there is this, again, perception that the process has been set up
for the pipeline to come out. That there is this momentum that was
created, that: that would be the outcome. And, I would ask the
staff, ah, I mean, there’s again this underline concern that the
staff has been predisposed to valuate this in such a way that the
pipeline would be the winner. And, so, I guess the question to
both of you gentlemen, and interesting enough, I’m thinking of
Rosemary LeClaire, who, none of you have been involved in this
process. This is something that was dealt to you as your
appointment under the new city. But, why, why, why are you so
adamant that it be …a pipeline?
19:21 -
Richard Hewitt: Well, quite frankly, I think "adamant" is probably the wrong
word. I think it is our job as staff to come forward with
professional recommendations as objectively put together as we
possibly can, to recommend to Council the approach we feel is the
most appropriate for any given situation. We certainly
acknowledge the viability of all the technologies that are on the
table. But in this case, we certainly, by looking at
environmental issues, risk issues, potential cost issues, we
feel that on balance, the pipeline is the preferred alternative,
and that is why our recommendation, is in fact before you. 20:00 I would also note that there are a number of agencies and
entities that are involved in this process that I think, that
while maybe given the weight that perhaps they should be, I think
is worthy of note. And I refer to the Rideau Valley Conservation Authority which has accepted the recommendation
of the pipeline, the initial recommendation by Conestoga-Rovers,
the work that RV Anderson has done with us, in terms of the final
recommendations we’re making now. The acceptance of the
Environmental Assessment by the Ministry of Environment, where
the pipeline remains the only environmentally approved solution at
this point, to deal with sewage from Munster. So I would
suggest that, ah, in fact there are a number of indicators that,
ah, I feel that are indicative of the fact that we have undertaken
as objective an evaluation as we can, and come to a conclusion
that we feel is most appropriate for this situation.
20:76 –
Councillor Stavinga: OK, my final question is to legal, to Mr. Marc. Again, there
was the concern that raised at Committee, and also again has come
forward at numerous times in the last week-and-a-half before this
matter (rised) into council. And with respect to the OMB direction
that was given to the city with regards to this particular matter.
And, the concern is that we have not fulfilled the obligation, we
have not been responsible to the direction that was given by the
OMB. So my question to you Mr. Marc, is, have we fulfilled that
direction. Have we not, or we perhaps not tended to something that
we should have?
21:29 – Tim Marc:
Mr. Mayor, the Ontario Municipal Board Decision, in its key
paragraph, reads, ah, that, the city was to add a symbol for a
city communal wastewater facility located in Munster
Hamlet, as shown in the schedule attached, which may be one of the
following: a pipeline, the mechanical treatment plant discharging
to the Jock River (CMS), or the Snowfluent, provided the
following of the evaluation of these alternatives to the
satisfaction of Council. And then the Board set out five criteria
for the evaluation, which he advised the City to follow, but
did not require the city to do so. In my opinion, the
evaluation done by RVA, once confirmed by Council, fulfills the
requirement of the Ontario Municipal Board’s Decision.
22:14 –
Councillor Stavinga:
OK. Thank you, Mayor Chiarelli. I would like an opportunity for
wrap-up but I know since some of my colleagues do have some
questions or comments, if I may hold my wrap-up for then? Thank
you.
22:22 –
Mayor Chiarelli: Thank you. Is the item carried, or do all you speakers still
want to speak to it? Ah, Councillor Bloess.
22:30 -
Councillor Bloess: Thank you Mr. Mayor. I don’t think the item’s carried because
some of us, I don’t think, will be supporting this item. I guess
when you go through the reports, and you’re looking at the
process, and the OMB, and certainly it’s a convoluted and a costly
process that we’re in here, and there seems to have been a mantra
about pipelines here. And, I guess, since I’m hearing this great
belief how pipelines are the answer, maybe we can look at a couple
of pipeline examples the city has, that I think some of you
members of staff have been involved in. The main SW collector that
runs around the SW then runs just on the east side of 417, to the
SE. Maybe you can tell us about some of the issues and problems
you had within the first year ---when consultants told us how well
it was going to work--- and what the legal outcome was on that
one.
23:25 -
Richard Hewitt: Frankly, Mr. Mayor, I’m not really in a position to do that. I
think this was a situation that is a number of years old, and was
certainly well before the time of the new City.
23:34 - Councillor Bloess: Well, maybe I just add in there that, that pipeline within the
first year of operation, had significant issues in it, including
having 24-hour security in Greens Creek valley where land was
eroding, and the pipeline was exposed, and all kinds of issues,
and if we’re not in court still, we certainly were in court for a
long period of time on that one. That was a brand new
pipeline. Perhaps somebody on staff can tell us how long the (Bellcourt)
pipeline, which we’re rebuilding right now …how long that one
lasted? ….It’s in the budget right now, last year and this year.
(5 second pause, no answer.)
…It’s a pipeline you could drive a small truck through. It
apparently fell apart within half, …half of its normal life span.
24:22 –
Richard Hewitt: I’m sorry, Mr. Mayor, I’m not able to address those issues. I
can certainly provide information subsequent to Council, but I’m not in a position to talk on it now.
24:30 –
Councillor Bloess: Well, Mr. Mayor, I guess, what it comes down to is that there
could be a great belief that the integrity of pipelines is
unquestionable, and may have a 90-year lifespan. But we know from
experience ---we have a number of very recent examples where that
is not the case. And this is a process, by the way:
Something
smells about this process, and it’s not just the sewage!
There’s something really wrong about what happened here when we go
from one recommendation to another, to another, and we end up
finding with the Technical Memorandum, which I think came out on
April 30th, which seems to contradict ---again--- what
had gone before. And, I guess what this shows me …and I for
one, even though there may have a unanimous support at Environment
Committee: that does not mean to me that that was the right
decision. This shows me, the right decision is to look at what
really happened here, and to use one of the alternatives. And
the
alternatives are very clearly less expensive. The fact is,
I guess what this really shows us is, if you don’t like the answer
the first time, hire either another consultant, or go back to a
consultant until you get the answer you want. And if I hire a
consultant and tell them what answer I want, I’ll probably get
that answer, even if it means water is going to flow up-hill
or up-stream.
Well, if you look at we have before you, there’s no way; …I’m
going to be calling for yeas and nays: because there’s no way I
will be supporting what’s being recommended here.
26:00:
Mayor Chiarelli: Thank you, Councillor Bloess. I was momentarily distracted. Did
you, ah, recommend a preferred option from your point of view?
Councillor Bloess: Yes, I did.
Mayor Chiarelli: Ah, which one was it?
Councillor Bloess: I said the on-site treatment.
Other Councillors: Which one?
Councillor Bloess: The one I’ve got flagged here, hang on. Well, I’ll give you the
one. I’m definitely not going to snow you, I know. Not going to
spray you either. I’m looking for the name of the company.
Seprotech, there you go.
26:30 – Mayor Chiarelli:
That’s the Snowfluent?
Other Councillors:
No, Seprotech
Mayor Chiarelli: Thank you. (Councillor Legendre):
26:44 -
Councillor Legendre: Thank you Mr. Mayor. I congratulate my colleague, Councillor
Stavinga. After all of her questions it’s amazing that I still
have two, that I want to ask. She’s covered the territory very
well. One that arises out an article, that I read in one of the
local papers today, written by the executive vice president, if
memory serves, of Seprotech. Would our staff have seen that
article today? You have it there? And, one of the allegations in
that article, troubles me. I guess it’s referring to the Technical
Memorandum. This is the, I think elsewhere in this report it might
have been called an Addendum to the original RVA Report. And it’s
saying that there’s no engineer can be found, that will put his
name to that … I would like to hear what staff’s response is to
that.
27:57 –
Richard Hewitt:
Well I would totally disagree with the statement.
Councillor Legendre: Allright.
28:00 -
Richard Hewitt: Quite frankly, the firm of record is a well-acknowledged
consulting firm by the name of RV Anderson Associates. We have the
vice president of RV Anderson here today, who is also the Project
Manager of this, ah, …registered consulting engineers in the
province of Ontario. The sub-consultants are similarly
well-qualified and well-respected firms. Ah, I don’t think there
is any doubt that we have information and recommendations provided
by that firm that are fully supported by that firm, and by the
professional engineers that are employed by that firm.
28:33 -
Councillor Legendre: Mr. Hewitt, you're our
Director of Infrastructure Services Branch?
Correct?
Richard Hewitt: Yes
28:39 -
Councillor Legendre: You are an engineer?
Richard Hewitt: Yes, I am.
Councillor Legendre: This Report carries your signature?
Richard Hewitt: ….Ah, the staff report carries …
Councillor Legendre: Ya, the staff Report
...sure, which included all of the other
staff?
Richard Hewitt: Yes...
Councillor Legendre: Allright.
Richard Hewitt:
...We certainly rely on their expertise.
28:56 –
Councillor Legendre: OK. Now, I’m now going over to page 40 of the report. And this
has to do with the Environmental Assessment approvals, should we
choose one of the other technologies. And that disturbs me a lot,
what I read in the middle of page 40, there. That, for instance,
it says there, if either of the communal treatment alternatives
---CMS or Snowfluent--- be implemented, an Addendum to the ESR is
required. The MOE has advised that any selection of an alternative
solution other that the pipeline, I guess; The pipeline is
automatically approved, right?
Richard Hewitt:
That’s correct.
29:47 –
Councillor Legendre: Right. And then it goes on to say, and this is what really
floors me, as a minimum, this would entail re-evaluation of
ALL SIX alternatives! Because, I was a member of Regional
Council when we went through this, and if somebody said a while
ago, that something smells here, you know, what we’ve done
as elected officials, making these decisions, and I guess the OMB,
is that we’ve bent over backwards ---to the point of breaking---
in order to really, you know ---with a microscope--- examine all
of the alternatives. And now I read, that if we choose something
other that a pipeline, we would have to go back, and re-examine
six alternatives. This is incredible to me. Can you put some
context around that? Are our laws in this province so written,
that this would actually have to happen?
30:46 -
Tim Marc: Mr. Mayor, if I can answer this one. The letter from the
Ministry, itself is found on page 72 of the Report. I wrote to the
Ministry back in 2001, after the decision came out, ah, in order
---before we reported to Environmental Services Committee--- in
order to find out what possible course of action could follow
under the Environmental Assessment Act, should Council wish to
pursue an option other than the pipeline. The pipeline is not
automatically approved. It has gone through the Class
Environment, an Addendum under the Class Environment Addendum
process, and it came out as the preferred option. If Council wants
to pursue an option other than the pipeline, then a similar
analysis must be followed, and the Ministry said that if you’re
going to pursue that Addendum process, then you are going to have
to look, at least, at the six options that were originally
evaluated. In fairness, three of them could, perhaps, receive a
summary analysis: the lagoons, ah, there was a biological
treatment process, and the do nothing alternative: could probably
be dealt with in a summary fashion. But the three other options:
Snowfluent, Seprotech, and the pipeline --- as well as the possibility of other options that might come forward at this time---
would have to receive a full analysis.
32:12 –
Councill Legendre: It sounds very much to me, like we would be back to square-one.
32:16 –
Tim Marc: Mr. Mayor, we would be back to where we were in March of 1997,
yes.
32:22 -
Councillor Legendre: It’s not even earlier than that: March of ’97? It sounds recent
when you say it that way. It seems much longer to me. Well, I
think those are my questions, Mr. Chair.
Mayor Chiarelli: Thank you Councillor Legendre. Counciller Cullen.
32:42 -
Councillor Cullen: Thank you Mr. Mayor. Mr. Mayor, my questions were answered by
the very excellent presentation made be my colleague, Councillor
Stavinga. This is an issue that has been around for some time. It
has become controversial over the process by which different
responsible authorities have looked at the options for this
particular sewage problem in the Village of Munster, in the Hamlet
of Munster. You know, we’ve heard the history of the 1995 Study,
which talked about upgrading the facilities of lagoon and current
spray technology. We had the 1999 Study that recommended a
pipeline. We have the OMB Decision, which caused the re-evaluation
of all the three alternatives. We had the RVA recommendation last
year, which was for local wastewater treatment, yet today
we are facing a recommendation to extend the pipeline. I know
there are concerns out in the community and I think staff have
addressed these concerns of what would be the impact of this
pipeline on neighbouring wells. We’ve had concerns expressed about
the method of evaluation. We’ve had concerns expressed about the
costing of these projects. Through both the extensive Committee
consultation, and today at Council, I have yet to hear any reason
…I have yet to hear any reason, other than to choose what we have
before us. It’s certainly exhausting. There’s certainly competing
viewpoints on this. But ultimately we have to decide. And, I think
the report that’s been brought to us, fairly represent the choices
before this Council, and makes a recommendation that allows us to
deal with this long outstand problem in Hamster …in Munster
Hamlet. So, Mr. Chairman, I’m prepared to accept what’s before us,
here. I think it is appropriate to raise the questions that have
been raised, but ultimately, based on the information that we
have, of the recommendation coming from our staff, I think we have
done our due diligence, and now can move forward. Thank you, Mr.
Chairman.
Mayor Chiarelli: Thank you Councillor Cullen. Councillor Stewart.
34:55 -
Councillor Stewart: Thank you, Mayor. Just a bit of a follow-up. The question that
Councillor Legendre asked about the author of the latest agenda,
and you mentioned that it was RVA, but is there any individual who
actually signed that Report?
35:13 –
Richard Hewitt: The report, I believe, was signed by the project
manager, Mr. Reg Andres.
Councillor Stewart: Is he and engineer?
Richard Hewitt: Yes he is.
Councillor Stewart: And, so he conducted that… ah…
Richard Hewitt: Yes he … that’s correct.
Councillor
Stewart: So, it isn’t authorless. There is somebody that can be held
accountable if there are questions.
Richard Hewitt: That’s correct.
35:33 -
Councillor Stewart: OK, that’s good to know. I too, have a copy of the guest column on the environment that
was in today’s Citizen, by the vice president of Seprotech. And
he’s calling, in the end, for an independent financial audit of
this process: an investigation. I think, on the good side, we’ve
already begun that. Environmental Services Committee has
instructed the independent city auditor to take a look at this
entire process. Because, I agree with Councillor Bloess on this
one. I’ve been around since ’94, when this first came to the
Region, and we sort of derailed the spray irrigation, and opened
it up again. And, I am very disappointed in the way this has been
carried out, to the point where I really don’t have any faith or
confidence that we are on the right track. Personally, I would
like to see other solutions, other more creative, innovative
solutions than pipelines. I think that either of the other
technologies of Snowfluent or the
CMS system would give us a
little bit more ground-breaking ------ . To turn up our noses at
cheaper tertiary treatment, to transport this sewage all the way
to a secondary treatment facility, when it’s more expensive to do
so, just doesn’t make any sense. So, I will also be dissenting on
the recommended solution.
37:32 -
Mayor Chiarelli: Thank you Councillor Stewart. Councillor Stavinga.
37:36 –
Councillor Stavinga: Thank you very much Mayor Chiarelli. I appreciate all of
Council’s time with regards to this particular matter, because it
is one that has an incredibly long history. What I can tell you
is, that when I came to Regional Council as Mayor of Goulbourn
Township and I remember actually having a meeting at that time
with the newly elected Chair, that being Bob Chiarelli,
interesting enough, that was probably one day before the ice storm
became a state of emergency. I remember that day very well. But I
had approached him on behalf of the community of Goulbourn,
because the Township of Goulbourn was not satisfied with the study
that was done by Totten Simms and Hubicki, which identified the
recommended solution to be the expansion of the lagoons and spray
irrigation. We were not pleased with that. And as the Township of
Goulbourn, we unanimously requested a Bump-up by the Minister of
the Environment. That was denied. When the election came, and I
was elected as the Mayor of the community, I had actually a
discussion with a member of our community who was very involved
with the study beforehand, and also in a subsequent study, too,
with regards to a technology, that being CMS, a sole proprietary
technology that would actually provide on-site treatment. And I
can tell you as mayor of the community ---not just as mayor--- but
actually from the background which is mine in Masters of Science
degree in physical geography, dealing with water chemistry,
dealing with the long range transport of plumes up to the arctic,
I was very intrigued with the ability, wouldn’t it be great if we
could, in a very sustainable way, treat waste on site.
39:04 - So, with that
information I went to Regional Chair, and then asked Regional Council
to open this up. So, indeed, you did have a solution. And you
actually began acquiring ---as the former
Regional Council--- acquiring land to implement that solution. You
started that work. But because of the request from Goulbourn
Council, because of the request from the community, you opened it up again. So we asked from Goulbourn Council that it be an
open and independent process, and
you brought on Consestoga-Rovers.
Thank you for doing that. I can tell you at the beginning I was
very suspicious of them. I thought, once again, "Who has the
Region indoctrinated to bring ...to come in ...to come up with a solution.
But interesting
enough Conestoga-Rover proved themselves to the community. And
proved themselves to the Township of Goulbourn, by the integrity
in which they held out their process. And interesting enough,
that’s what RV Anderson says too, the level of detail in the
Munster Hamlet 1999 EA Addendum is considerably greater than
typical level of detail, based on typical EA documents, were
viewed as part of this investigation. So, another engineer
evaluating yet another engineer’s reports said they have gone
above and beyond. Interesting enough though, it was challenged by
the Ontario Municipal Board: not for environmental reasons, but
because it needed an Official Plan Amendment, and that enabled an
opening to the Ontario Municipal Board. We got the Ruling from the
OMB, we did what they told us to do, and interesting enough, the
on-site treatment is not the solution. 40:32-
I have a petition here before me with 690 names within
the community of Goulbourn, and I take this very seriously. And
I’ll read this to you. It says "We the undersigned, reject the
proposal of a pressurized sewage forcemain from Munster putting
private shallow wells, the environment and human health at risk,
when the safer alternative of on-site treatment at Munster would
protect health, benefit the environment and cost much less." You
know, I would sign this. I would sign this in a flash …if it was
true. But, it’s not … it’s not true. And what I would ask you,
today, to do, is support the staff recommendation. Support the
work that has been done by RV Anderson. Support the addition work
that was done through the technical memo, and let us bring this
story to a conclusion. This is a basic service for the residents
of Munster, and they deserve no less. There is also commitment
through staff and through this city council by the adoption of
this recommendation to engage the residents in the final design,
to the village of Richmond, and to ensure that we mitigate against
any potential (impasse), and as staff have said, that pipelines
are safe, reliable and reasonable. This is not the SE trunk. This
is …. is a pipeline. This is not something that you drive a truck
down. The comparisons are ludicrous, and unfortunately, it’s that
…that fear mongering which has fostered 690 people signing this
petition. 42:00 - I ask you, today, based on the evidence, and I have 1.4
million of the evidence right here: a box here, of a few other
boxes. Lots of evidence, and it is fair.
It’s very clear. Please,
support the recommendation from Committee, today. It is about,
indeed, a pipeline from Munster. Thank you.
42:20 -
Mayor Chiarelli: Thank you, Councillor Stavinga. Yeas and Nays:
Councillor Arnold: Yes
Councillor Cullen: Yes
Councillor Stavinga: Yes
Councillor Munter: Yes
CouncillorLittle: –
Councillor Deans: Yes
Councillor McNealy: Yes
Councillor Chiralli: Yes
Councillor Brooks:
**Yes**
Councillor Lagendre: Oui
Councillor Kreling: Yes
Councillor Bellemare: -
Councillor Harder: Yes
Councillor Hume: Yes
Councillor Mallier: Oui
Councillor Bloess: No
Councillor Doucette: ( - )
Councillor Hunter: Oui
Councillor Stewart: No
Councillor Thompson: Yes
Councillor Eastman: ( -?- inaudible)
Mayor Chiarelli: Yes
16 yeas and 2 Nays
43:27 -
Mayor Chiarelli: Carried.
Related Links and Follow-up pages:
|
|
|