Richmond ups ante in pipeline
fight
Seeks help of
environment commissioner
Jason Fekete
The Ottawa
Citizen
Thursday, October 02, 2003
Already
ensnared in a multi-million-dollar lawsuit over a proposed sewage
pipeline from Munster Hamlet to Richmond, the City of Ottawa now
faces growing opposition from the community.
Richmond
residents, who've fiercely protested the pipeline, will meet next
week with Ontario Environmental Commissioner Gord Miller to object
to what they say is a raw deal for their community.
In the middle
of the battle is ward Councillor Janet Stavinga, who initially
favoured the on-site option, only to flip-flop when a second round
of consultants' reports recommended the pipeline.
The Richmond
Village Association has pleaded with the city to halt the pipeline
for fear it will break and contaminate the area aquifer. But the
association says its concerns have fallen on deaf ears, so it's
now going to the environmental commissioner to ensure the city
isn't breaching the Environmental Bill of Rights.
"I would hate
like hell to see the Munster people put off their sewage solution,
but an on-site option is better for both of us," said association
president Ted Brown. "If we ever get a pipeline, it'll eventually
break and we'll be in big trouble.
"We feel the
commissioner may be one of the only people who can stop this
thing," he said.
The
11-kilometre pipeline would bring raw sewage from Munster Hamlet
-- where leaky sewage lagoons have raised the ire of the Ministry
of Environment -- alongside a shallow aquifer that doubles as
Richmond's well water supply.
The city has
already approved the sewage line's path to Richmond, but is still
reviewing six routing options through the community to the pumping
station along the Jock River.
The
municipality's decision to go with the pipeline option has led to
a lawsuit filed against it by what is now Seprotech Systems Inc.
-- one of the companies that offered one of two on-site options.
In the suit,
the former Regional Municipality of Ottawa-Carleton is a
co-defendant, along with Conestoga-Rovers & Associates Ltd., the
engineering firm contracted by the region.
Seprotech
alleges in the suit that the city put out a request for proposals
to deal with Munster's sewage, but then changed the tender
requirements to favour the pipeline.
Court
documents detail how the company is suing the city for punitive
damages for "arrogant and cavalier conduct."
"This is not
a matter of mere rejection of proposals; this is a matter of
inducing proposers to submit bids under false pretenses in order
to satisfy the defendant's own hidden agendas," the documents say.
"By
submitting a compliant proposal in response to the (request for
proposals), a contract was formed between the parties. As a
consequence, the defendant had a duty to treat the plaintiff
fairly, and to conduct the (request for proposals) process in good
faith."
In a
statement of defence, the city denied the allegations.
Conestoga-Rovers has counter-sued Seprotech for roughly $4.2
million, claiming libel and slander. The city has filed a
cross-claim against its co-defendant, arguing Conestoga-Rovers
should be responsible for any judgments associated with the
original suit.
City
solicitor Jerry Bellomo could not be reached for comment.
Martin
Hauschild, executive vice president of Seprotech Systems Inc.,
said he's dumbfounded as to why the city rejected the on-site
options.
"Clearly
there's a very major effort at very high levels to get this
pipeline put in," he said. "They're going to squander millions of
dollars at the end of the day with the pipeline.
"If they
accept the bid or reject the bid, that's one thing, but they can't
just turn around and under the same solicitation buy something
completely different."
The second
company overlooked in the proposal process, Northern Watertek
Corp., is reviewing whether to file a similar lawsuit against the
city for defamation of its product and for wasting its money on
the tendering process.
The
municipality has already taken a financial hit on the project,
spending $500,000 a year to haul Munster's sewage to Ottawa's R.O.
Pickard Environmental Centre for treatment and disposal.
The city has
also racked up roughly $1.6 million in consultants' fees and spent
more than $6 million on the project, with another $7 million
earmarked for construction, which has yet to begin.
Mr. Hauschild
and Northern Watertek owner Jeff White, however, say the pipeline
alone will run closer to $15 million.
The city has
largely favoured a pipeline option as the solution, but its plan
was taken to the Ontario Municipal Board. There, it was told to
re-evaluate the alternatives, two on-site treatment options that
would cost less and alienate far fewer residents.
Last
December, an independent consultant hired by the city -- in light
of the OMB ruling -- said the pipeline and on-site treatment plans
were all sufficient, but the on-site options were preferable
because of the pipeline's added cost.
City
officials have argued that an on-site option would require changes
to the environmental assessment process, which could slow the
plan's implementation by one year or more.
"Over the
years, as we've spent more than $5 million on studies and stop-gap
measures, it's become readily apparent that the on-site treatment
methods were not ready to provide the basic public service to the
people of Munster Hamlet," Ms. Stavinga said yesterday. "They
couldn't meet the performance requirements for on-site treatment.
Period."
But Mr.
White, a lifelong engineer, said any amendments to the
environmental assessment process would take only a few weeks.
The city
endorsed the pipeline option based partially on a 90-year cost
analysis. Mr. White said the norm is a 10-to-15-year analysis.
Editorial: Costly pipe to Munster
© Copyright 2003 The Ottawa Citizen
|