| |
Subject:
Re:
Munster Wastewater File
… Futile attempts to obtain honest cost breakdowns from
city staff.
From:
Richard Bendall -
benrich@sympatico.ca
Sent:
February 4, 2004
- (Slightly
amended, February 20, 2004, for greater clarity.)
To:
Ryan.Matthews@ottawa.ca,
Rosemarie.Leclair@ottawa.ca,
Richard.Hewitt@ottawa.ca,
Tim.Marc@ottawa.ca,
Jerry.Bellomo@ottawa.ca,
Bob.Chiarelli@ottawa.ca, Janet.Stavinga@ottawa.ca CC:
Steve.Kanellakos@ottawa.ca
(See more accurate costing below - with
latest
updates)
Dear
Mr.Matthews:
Your January 14, 2004 response
to my (December 1, 2003) request for simple costing information
still lacks the required information to reconcile the numbers in
your Annex “E” chart. Why are you finding it so difficult to
fulfill this simple request? Could it be, because the numbers
in the Annex “E” are not founded entirely upon fact? It
seems that if the figures in Annex “E” were honestly
supportable, you would have long since sent the supporting data,
and we would not be still having this time-wasting conversation!
The Environmental Information Network (EIN), Inc. seems to have
characterized the city’s type of approach quite succinctly, when
it says, “Reports based on faulty foundations of
inconsistent, missing, or biased data are meaningless,
misleading, and worthless. To deliberately present bad data as
if it were meaningful is scientifically invalid and immoral.”
The city’s mishandling of this
affair begs the question: Is it not unlawful for city staff and
politicians to violate their fiduciary trust to taxpayers, by
misrepresenting the true costs of the available options?
Three significant conclusions
can be drawn from the city’s attempts to impose the forcemain
option:
1.)
While attempting to defend the forcemain option by
fabricating spuriously low costs ---compounded over an unrealistic
90 year period--- the city has only convinced the public that
its cost arguments are fraudulent;
2.)
There is no justifiable rationale for neglecting the
well-founded safety concerns of 7,000 citizens (who deserve
better from their municipality), when total safety and
peace-of-mind can be achieved by the use of either of the two
communal treatment options ---each with guaranteed, fixed-price
bids--- that have been presented at 20 to 30 cents on the dollar
(relative to the “cost-plus” forcemain option);
3.)
The only foreseeable outcome from the city’s current
deceitful course, (i.e.: that of pushing ahead with the pipeline
option on the basis of misrepresented facts), would be to lead
to an even greater squandering of tax dollars, further
litigation and possibly criminal charges against any persons found
responsible for acting in bad faith, breach of trust, guilty of fraud, corruption, abuse of office, misappropriation
of tax dollars, public endangerment, and more.
City officials are in the process of knowingly committing a
grave injustice against a populace. An unnecessary, added burden
of worry (at additional expense) is about to be imposed upon an
entire community of 7,000 law-abiding residents, with no
conceivable upside or benefit. There are only negatives: of
both, elevated health risk and 500% in added cost. Where's
the rationale?
It is said, “A fool cannot
reason, a lawbreaker will not reason, and a slave dare
not reason.” In the event you feel you fit the last
category, may we urge you to pass this upward through the city’s
bureaucratic and political hierarchy, until you find those
persons (in the “will not reason” category) who are
responsible for ordering and drafting the fraudulent Annex “E”
chart, and have them try to reconcile the true cost itemizations
against their bogus totals. It’s that simple, Sir.
In the meantime, take a good
look at your own conscience.
Yours truly,
Richard Bendall
Encl: (See below)
Below, is a “Revised Annex E”, adjusted to reflect the more complete
costing information supplied by Totten-Simms Hubicki - (RMOC-Commissioned
report of February 13, 1998), Brackenshiel Study
(Independent, 107-pg.-“Critical
Analysis of the Munster Treatment Project” – 2002),
(Sections 3.4 to 3.5.4), and other current (city and independent) engineering
documentation, reports, contract information, and
correspondence:
City appears to be applying the
"legal-bully approach", to suppress citizens'
cost inquiries and further block flow of
costing information to ratepayers:
Threats from city's solicitor, (in lieu of addressing
problem). --- Ratepayer's reply
The city's
pattern of stonewalling continues...service to the public
interest, is the casualty:
Obfuscation
supplants transparency and traceability
REVISED ANNEX “E”:
(Corrections shown in
RED)
|
REVISED ANNEX ‘E’:
COST COMPARISON
|
No. |
Cost Considerations |
Alternative |
|
|
|
Snowfluent® (Northern Watertek)
|
Pipeline |
CMS (Seprotech)
|
|
1. |
Capital |
$3.3 - $3.7 M |
$6.6 -$7.6 M $14 - $18.3 M |
$3.5 - $4.3 M |
|
2. |
20-year life cycle |
$5.0 - $5.4 M |
$7.6 - $8.6 M $16 - $20 M |
$5.7 - $6.4 M |
|
3. |
Capital |
$3.3 - $3.7 M |
$6.6 -$7.6 M $14 - $18.3 M |
$3.5 - $4.3 M |
|
4. |
20-year life cycle |
$5.0 - $5.4 M |
$7.6 - $8.6 M $16 - $20 M |
$5.7 - $6.4 M |
|
5. |
Other costs:
(a)
Technical requirements to
complete EA, obtain C of A, etc.
(b)
Additional hauling
costs based on timing of implementation.
|
$0.8 M (< ?)
$1.5 M $1.0 M
|
(included in above capital
costs) $0.08 - $0.1 M
(±?)
$1.0 M (>?) |
$0.08 - $0.1 M (<
?)
$1.5 M $1.0 M |
|
6. |
Total
anticipated Capital cost (incl. other
costs)
|
$5.6 - $6.0 M < $4.5 M |
$7.1 - $8.1 M $14 - $18.3 M |
$5.1 - $5.9 M
< $4.5 M |
|
7. |
Total life cycle costing (including
other costs):
(a) 20-year life cycle
(b)
75-year life cycle
(c) 90-year
life cycle
(not valid)
|
< $7.3- $7.7 M
< $9.4 - $9.8 M
< $9.5 - $9.9 M |
$8.1-$9.1 M
$16- $20 M
$9.2-$10 M
$18 - $23. M
$8.9-$9.7 $20 - $30 M
(?) |
< $7.3 - $8.0
M
< $9.4 - $10.2
M
< $9.5 - $10.3
M |
|
Pipeline and Additional Capital Costs - (Forcemain Option)
Pipeline cost
(quoted by city)
$4,000,000
(Includes $1,200,000 for design &
construction oversight costs,
Pipeline materials of
$2,000,000, plus other materials and installation costs) Pipeline
material upgrade
$100,000
Upgrade cost to high density polyethylene (HDPE)
pipe Pump Station
at Munster
$625,000
(See Fig
1) Lagoon
Decommissioning
$300,000
($100,000 /cell
X3)
- at Munster Spray Field
decommissioning $100,000
(at Munster) New Lagoon
construction $200,000
(at Munster) Trucking of
sewage $650,000
(Counting on winter ’04/05 –
multiply figure by each added year) Traffic
Control
$570,000 (During
construction) (See Fig
2) Perth St. and
Cockburn work $4,000,000
(Excavation around existing
services, storm/leak drainage and road repair.
(Ref: Project #900700 -Dft. Budget)
Cost revised upward to reflect actual cost of Fortune St., at half
the distance.) Extra rock excavation $600,000 (?)
(One of the biggest unknowns as per
RV Anderson Report: Could easily become
$1,600,000) Trenching &
wall support costs $1,500,000
(?)
(See Fig
3)
H2S control vents,
valves & fittings
$100,000
(Required every kilometer –as
stated at Dec 9, 2003 Open House) Franktown
Road repair $2,000,000
(?) (See Fig
4) (Asphalt, granulars,
TCPL-gas utility crossing, etc.) Richmond Fen
crossing
$1,700,000
(See Fig 5) Booster
station $2,500,000 (?)
(In 2003-2004 Budget, but left out of costing.) Bio-scrubber
(in Richmond)
$600,000 (?) (To handle
Munster’s septic sewage) (See Fig
6) Jock
River Crossing (at Cockburn) $100,000
===========
Total:
$19,645,000
Additional Operation and Maintenance Costs – (Forcemain
Option)
Sewage
Treatment Costs: $132,000 / year*
(@
.60/m3 X 220,000m3 of sewage) – Munster
sewage only.
This cost was omitted from the
city’s O&M estimates.)
* (Does not
include calculation of the transportation costs of Munster's sewage, through
approximately seventy kilometers of pipe, and through seven
(or more) pump/lift stations, to ROPEC, for
treatment. When one considers that the lifetime of the Glen
Cairn Trunk was shortened to 26-years because of the corrosive
effects of "septic sewage", from Stittsville and Richmond,
then it can be clearly determined that there are significant
"downstream transportation cost". Project engineers for the city
prefer to ignore these costs. )
*
(Does
not include adjustments for the city's hydro cost estimates,
which were far too low for the forcemain option, and artificially
inflated for the mechanical treatment option.)
Additional Hidden Costs – (Forcemain Option)
Not listed
above – additional costs (possible millions of
dollars) – Note: Not a fixed-price bid, as communal bids
were. Litigation
(re: RFP, etc): (possible millions of dollars) Post-installation mitigation work (possibly
millions of dollars) – Note: Glen Cairn collector lasted only ~26
years. Pipeline
Ruptures: Repair & Cleanups
(certain millions of dollars)
Litigation re: ruptures (certain millions of dollars) (High potential for high health
costs, and loss of human life, exist from riskier forcemain
option. The Richmond Village Association
asked for a
comparative Risk Assessment to be done, but city deliberately
omitted it from the RV Anderson
Work Plan. Potential litigation against those responsible, five
years from now, will not replace a lost life.)
Addenda
.
Other
cost-related issues:
1.) The (Feb 11/04) Draft
Budget …an exercise in political trickery:
The Draft Budget “hides” costs of anywhere from $15,000,000 to
more than $30,000,000 on the proposed Munster-Richmond
pipeline project. Councilors and the public have no way of tracing
the true project-cost, unless city staff reveals the breakdown
costs on all the relevant project codes (in the left-hand column
of the budget review). (See example list in red below.) Until
budgets list specific projects in a manner that includes their
complete component costs, city budgets will remain out of control.
For example:
Munster-to-Richmond pipeline cost is spread over multiple known
and unknown Project Numbers
PROJECT CODE
|
DESCRIPTION
|
BUDGET
|
EXPENDITURES & COMMITTMENTS
|
UNSPENT & UNCOMMITTED
|
#900221
|
Mnstr. Lagn. Rehab.
|
$12,642,000
|
$7,650,078
|
$4,991,922
|
#900235
|
Rchmd PmpStn.Upgr
|
$1,500,000
|
$1,243,309
|
$286,691
|
#902566
|
Rchmd Sewer rehab
|
$275,000
|
-
|
$275,000
|
#902964
|
Rchmd Sewer rehab
|
$275,000
|
-
|
$275,000
|
#902964
|
Perth St. monitoring.
|
$675,000
|
-
|
$675,000
|
(Ref: #900700) x2
|
Perth/Cockburn Wk
|
$4,000,000
|
-
|
$4,000,000
|
|
|
==========
|
|
==========
|
|
TOTAL:
|
$19,367,000
|
|
$10,473,613*
|
*Note:
Difference between
$10,473,613
(immediately above) and the more accurate list of
$19,645,000
(shown further up this page), is either missing entirely from the
Draft Budget, or is buried in any number of other
related-sounding projects
---worth over $140,000,000---such as those shown below:
900004 Environmental Management $771,000
900138 Environmental Resources Area Acquisition $13,601,000
902560 Environmental Management $250,000
900140 Water and Wastewater Strategic Planning $700,000
900256 Infrastructure Master Planning
$2,240,000
900813 Sanitary Sewer - Neighbourhood 3
$1,411,000
900895 Integrated Road, Sewer & Water Program $21,694,621
901296 Trenchless Rehabilitation & Spot Repairs $2,421,000
902550 Pre-Post Engineering Services $1,600,000
900679 Road Reconstruction Program $1,999,286
900700 Fortune Street. (Perth St to Jock River) $2,000,000
902344 Infrastructure Management - Roads
$335,000
901069 Resurfacing Program
$15,880,000
902160 Resurfacing Program
$13,750,000
900708 Structure Rehab./Replacement Program $4,165,000
901078 Rehabilitation/Replacement Misc. $5,495,000
902551 Rehab/Replacement Misc Structures $3,140,000
990002 2000 Sewer Upgrade Program
$2,014,388
900218 West Growth Area Sewer System Upgrade $11,192,500
900221 Munster Lagoons Rehabilitation
$12,642,000
900232 Pumping Station Equipment Replacement $1,008,000
900234 Trunk Sewer Operational Requirements $8,062,000
900235 Richmond Pumping Station Upgrade $1,530,000
900241 Hazeldean Pumping Station & Forcemain $10,068,000
900265 Corrosion Investigations
$985,000
902355 Wastewater Pumping Station Reliability $1,500,000
902568 Infrastructure Mgmt Prog - Wastewater $850,000
900252 Wastewater Facilities Upgrades $3,472,000
(Additional
costs of
$9,000,000 or $19,000,000 could easily be hidden in the above
projects, and both the public and the Councillors would have
no way to trace the real cost of the forcemain, without
project-specific listing of total costs.)
Repeated request to city staff for breakdowns of the above-listed
budget items have
been ignored.
Explanation of a few of the
Project Codes:
#900221:
Munster Lagoons Rehabilitation - $12,642,000:
More than half of this budget has already been wasted on repeat
studies, sewage hauling, and patch work, without a solution even
being started.
The
remaining $4,991,922 would more than cover the total cost
of a communal treatment system, (that three out of the four
consulting engineers recommended),
but would not begin to pay the cost $18,000,000-PLUS cost of a
sewage forcemain system.
#900235:
Richmond Pumping Station Upgrade - $1,5030,000:
This is the work that the city said it never did.
#902566 & 902964: Rehabilitation of
existing sewer pipes in Richmond: $275,000 + $275,000.
Would not be done if not to help increase performance in dealing
with Munster inflow.
#902964: Performance monitoring
- $675,000. Perth St. wastewater collection and conveyance
monitoring along forcemain route area of Perth Street, extended to
Shea Rd.
#900700: Fortune St. (Perth St to Jock
River) - $2,000,000: Fortune Street was excavated to pipeline
depth, and reconstructed to handle gravity conveyance of Munster’s
sewage, if that considered option had been chosen. It was not.
The main point of interest, in this case,
is that the same detail of work would have to be done on the
selected route of Perth Street and Cockburn St, and at twice
the distance, the cost would be in the neighbourhood of
$4,000,000. (Is this item buried somewhere in
the “red list”, above?)
#??????: Where is the Booster Station -
$2,500,000 buried? - (proclaimed by the city to be in the
2003-2004 Budgets?)
#??????: Where is the Bio-Scrubber -
$600,000-plus buried? - (proclaimed by the city to be in the 2004
Budget?)
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Final Comment on the 2004 Draft Budget is
best expressed by Mark Sutcliffe: Ottawa entrepreneur, business
journalist and broadcaster (heard weekdays on CFRA), states in his Ottawa Citizen article of February 14, 2004:
“Ultimately, if the city were run
like a good business, providing good value for money, it would
be worth investing in it through a modest annual tax increase.
But the city has none of the elements of a good company: a
long-term strategic plan to focus on core operations and
investments, a comprehensive multi-year solution to its
escalating costs, or honest leadership that thinks ahead and
doesn’t shield the facts and then engineers a crisis that pits
different parts of the community against each other. Until it
does, the city will offer neither value nor a good price.”
Link to Mark
Sutcliffe’s full article:
“MEMO
TO A COST-CUTTING CITY…”
2.)
Remember? - RVAnderson
rejected the pipeline on the basis of its higher cost.
The RV Anderson report (December 16, 2000)
rejected the pipeline alternative ---in favour of either of the
communal alternatives--- on the basis of the pipeline’s higher
known and additional unknown costs:
"Of the three alternatives the pipeline
has the highest cost and the highest risk for cost escalation (due
to unknown issues like rock quantities)."
The public is still confused by the city’s,
“added cost for added risk”-approach.
3.) Need for Independent Auditor of city’s
activities
There have
been numerous high-level calls for an independent city
auditor to publicly address the numerous hidden abuses of the
public purse. Had this been in place prior to the $50,000,000
Ottawa South Collector boondoggle/fiasco/scandal, it would have
prevented some of the same city-players (including the current
Mayor/former Regional
Chair), from repeating the scandal at Munster.
An annual increase in
taxes, matched to the cost of living index would make sense ---ONLY---
after the city of Ottawa has put an Independent Auditor in
place. So far, the
requests have gone unfulfilled ---giving the impression that the
city has a lot to hide.
4.) Where is the city’s Internal Auditor’s
Report? The city's auditor, Tracy McTaggart,
was commissioned to do an internal audit of the Munster wastewater
project in the Spring of 2003, for release in September of 2003.
This report has been delayed, presumably because of what it may
contain. The city will be seen to be acting directly counter to the public interest, if goes ahead
with construction of the pipeline, before this report is
publicly tabled and considered in the cost analysis. (The city is
already seen as acting against the public interest on the health
risk issue.)
The Environmental Assessment Process, (see
excerpts of the EA Act), requires that documentation,
---including clear costing information--- in support a particular rationale, must be
easily
traceable, and be seen to be traceable in an open
and
transparently way. Since the city has already applied for a C of A
for the pipeline alternative, it would indicate that the city is
already trying to renege on it fiduciary responsibility to
taxpayers ---given the bleak cost figures for that option.
This is made all the worse by the
current budget shortfalls.
5.) Placing Richmond's shallow aquifer at
risk ---with a pressurized sewage forcemain--- may cost far more
than a squandered $12,000,000 to $15,000,000:
"The costs of
the Walkerton tragedy are estimated at $155 million - the
equivalent of 10 years of public health spending by the City
of Ottawa."
The
Ottawa Coalition for Public Health in the 21st Century - Ontario
Public Health Association
|
|