Engineers’
Statement of Agreements and Disagreements
OMB
Order No. 1012 Issued July 12/2000
Ontario Municipal Board
Regional Official Plan
Amendment No. 5
Proposed Munster Hamlet
Wastewater Pipeline
The Regional Municipality
of Ottawa-Carleton
OMB File No. O 990089
In accordance
with the Board’s Order No. 0851 issued June 7/2000, the
engineers with CRA who are consultants with the Regional
Municipality of Ottawa-Carleton, and the engineer who is a
consultant for the CMS System have held a series of Meetings (4
Days) to explore the feasibility of coming to an agreement upon
the optimal means of mitigating the problem with the existing
five-cell lagoon system in the Community of Munster Hamlet. In
accordance with the Board’s subsequent Order No. 1012 issued
July 12/2000, this document constitutes the Engineers’ Statement
of Agreements and Disagreements.
POINTS OF AGREEMENT
1.1
Design Flows - based on the evidence that has been
adduced at the hearing, and additional data obtained by CRA from
the RMOC Engineering Staff, it was determined that peak sewage
flows, particularly during the Spring freshet, are higher (4 to
5 times ADF), and sustained for a longer period than originally
anticipated. Based on the available information, the Engineers
agreed on the following revised design sewage flows for Munster
Hamlet:
Annual Average Day Flow (AADF): 575 m3/Day
or 6.65 L/s (unchanged from 1998 RFP)
Sustained Peak Flow: 25
to 30 L/s (Based on 2-week condition - April 1999)
Unsustained Peak Flow:
45 L/s (Up to 3.0
Hours)
1.2
CMS Modified Design - Of the 2 alternatives proposed by
CMS, the addition of 3rd rotating biological
contactor (RBC) as the preferred approach for modification of
CMS Plant to accommodate revised peak sewage flow criteria (2
alternatives evaluated by Mr. Pellerin).
1.3 Wetland - improvement in the impact on aquatic and terrestrial
habitat provided the wetlands are properly operated.
1.4 Selection of ferric chloride for H2S control.
POINTS OF DISAGREEMENT
2.
DESIGN MODIFICATIONS - CMS TREATMENT PLANT WITH JOCK RIVER
DISCHARGE
Mr. Pellerin
proposes implementation of a 3rd rotating biological
contactor (RBC), operating in parallel with the two (2) RBC’s
proposed in the original design by CMS. This approach increases
the plant capacity by 50% to 10.0 L/s, from the current design
of 6.65 L/s (ADF). The primary/secondary clarifier and dual
stage filtration (DynaSand) would also be designed for 10.0
L/s. As originally proposed, flow equalization for unsustained
peak flows (45 L/s for 3.0 hours) is proposed to achieve a
constant flow rate to the filters.
The modified
CMS Plant allows for continuous discharge to the Jock River for
sustained peak flows up to 10.0 L/s. At sustained peak flows
exceeding 10.0 L/s (Spring melt period) the treated effluent is
diverted to the constructed wetland. In this instance, the
diverted flow receives full treatment in the plant. However,
the filters, which normally operate in series, would transfer to
parallel operation, providing a filtration capacity of 30 L/s.
The UV system would also have capacity to disinfect the
sustained peak flow of 30 L/s. With the proposed modification,
a highly treated effluent is discharged from the CMS Plant to
the wetland (Pellerin).
The operating
mode proposed provides the wetland with some limited nutrient
and water necessary to sustain the wetland plants through the
growing season. This water, together with contribution from
annual precipitation, dissipates through a combination of
evaporation, evapo-transpiration, sublimation and groundwater
recharge (Pellerin).
CRA notes that the level of
effluent quality to the wetlands is undetermined under wet
weather
conditions.
Mr. Pellerin
can advise CRA that treatment to tertiary levels, through
filtration, phosphorus removal, and UV disinfection, will be
attained throughout wet weather conditions.
2.1 Efficiency and reliability of mechanical treatment plant system
discharging to the Jock River under wet weather conditions (CRA).
Mr. Pellerin (CMS) advises that the plant as modified,
discharges treated effluent to the wetland (not the Jock River)
under wet weather conditions, and is designed to accommodate the
modified peak sewage flow criteria agreed upon by the Engineers.
CRA is
concerned with wet weather operations.
2.2
Impact of wetlands; following below are CRA’s concerns with
keeping the existing sludges in the lagoons.
2.2.1 potential for odours (CRA);
2.2.2
potential for sulphide generation and
toxicity to biota and fish, as occurred in Listowel, Ontario (CRA);
Mr.
Pellerin questions the source of sulphide generation referenced
by CRA. The constructed wetlands, as proposed by CMS for bottom
sludge remediation and treated effluent by-pass in wet weather
conditions, do not produce a toxicity problem. The Munster
wetlands will receive highly treated effluent from the CMS
plant, whereas the constructed wetlands in Listowel were
implemented as a wastewater treatment system.
CRA does not agree, the
characteristics of the treated effluent are undetermined at this
time.
2.2.3 potential for off-site leaching and off-site
migration of nutrients to further deteriorate groundwater and
Jock River water quality due to leaching of the majority of
nutrients particularly phosphorus from dying plant tissues (CRA);
Mr.
Pellerin disagrees on the basis that any phosphorus migrating to
the shallow groundwater from the CMS constructed wetland would
be adsorbed in the overburden clay soils. Migration of
phosphorus to the Jock River is remote in this instance. CRA’s
own hydrogeologist has indicated a 20 year time frame for
groundwater in the vicinity of the lagoons to reach the Jock
River.
CRA notes that the existing
lagoons have up to a 40% leakage rate.
2.2.4 wetlands are not managed i.e., not harvested or
monitored essentially resulting in recycling of phosphorus
between the soil and plants, as the plant detritus of one season
is recycled to the tissues next growing season resulting in no
net loss in phosphorus (CRA);
The
concern regarding complete recycling in un-managed wetlands
raises a point which is insignificant. As is the case with a
natural wetlands, the CMS proposed wetland does not require
harvesting in the manner in connection with its intended
function (Pellerin).
CRA does not believe this to be
insignificant.
2.2.5 approvability of wetlands by MOE may require
further investigation in light of the sensitivity of the
receiver and previous experience with hydrogen sulphide toxicity
(CRA);
When previous experiences (Listowel) are not utilized to improve
environmental management, we have little to show for progress.
If we do not learn we regress rather than progress. The MOE is
certainly aware of the learning experience (Pellerin).
The
wetland design presented by CMS in the original RFP process
draws on the world renowned constructed wetland expertise of
Boojum Research Limited, and is proposed as a natural means of
decommissioning the existing lagoons (to remediate bottom
sludges). In addition, based on the additional flow data
received from the RMOC (1999/2000), the wetlands will accept
treated effluent from the CMS plant during sustained peak
flow conditions, which occur primarily in the Spring melt period
(Pellerin).
2.3
Impact of dry-ditch discharge, CRA is concerned with the
following:
2.3.1 enrichment and conveyance of agricultural
contaminants to Jock River due to contact with nutrients in the
treated effluent (CRA);
Agricultural runoff to Copeland Road ditch will discharge to the
Jock River irrespective of dry-ditch discharge. Furthermore,
the high quality of treated effluent from the CMS plant will
significantly dilute any nutrient rich agricultural runoff to
the Copeland Road ditch, thus enhancing the quality of runoff
entering the Jock River at that point (Pellerin).
2.3.2 perceived and potential health and liability risks
from open conveyance of treated wastewater (CRA);
The
CMS plant provides a level of treatment that satisfies MOE
requirements for dry-ditch discharge, as confirmed by Mr.
Pellerin in direct consultation with MOE Eastern Regional
Office. Mr. Pellerin is not aware of any objections of local
residents, perceived or real.
2.3.3 ecological impact on ditch habitat (CRA);
The
proposed discharge results in a water quality improvement and
therefore a positive impact on ditch habitat. A ditch with a
continuous flow of clean water supports a habitat of far greater
diversity than one which is dry (Pellerin).
CRA does not necessarily agree.
2.4
Impact of dynamic operational conditions (CRA):
2.4.1 washout of attached biomass on RBC media during
spring melt as a result of the high shearing velocities
resulting from tripling the hydraulic loading (CRA);
The
CMS plant as modified is designed for the hydraulic loading
rates agreed upon by the engineers. The internal baffling and
serpentine flow pattern through the RBC prevents washout, and
shearing velocities are not attained in this instance. RBCs are
responsive to both hydraulic and organic load fluctuations, and
the CMS design provides for a high level of treatment when
discharging to either the wetland or the Jock River (Pellerin).
2.4.2 prolonged recovery times to re-establish biomass
due to slow sludge yields inherent in attached growth system
such as RBCs (CRA);
The
modification of the CMS plant together with the inherent
resiliency of RBCs to hydraulic fluctuation, serves to maintain
biomass throughout the range of flow conditions agreed upon by
the engineers. Recovery time to re-establish biomass is
irrelevant (Pellerin).
3. ECONOMIC ANALYSIS
3.1
In CRA’s opinion, an economic analysis between CMS’s mechanical
treatment plant and the pipeline to Richmond was not conducted
due to the different delivery approach being proposed for each
option.
Mr. Pellerin believes economics to be an important planning
issue irrespective of the mode of delivery, and has assessed
capital cost for (i) the CMS Plant as a design-build, based on
detailed design information, facilitating assessment of a fixed
price design-build cost; and (ii) pipeline costs (estimate)
which cannot achieve the same level of accuracy, due to
uncertainty with regard to such fundamental design factors such
as final route selection through Richmond, geotechnical (rock)
conditions, pipe size and material, and by-pass cell
requirements in Munster.
CRA notes that
the CMS proposal is based on CMS’s understanding of the
delivered product. It is inevitable that there will be cost
changes as well since not all of the design basis was presented
in the 1998 RFP. There may be operational, control, and
material changes that could affect the CMS price. Furthermore,
there may be approval agency issues that could affect price as
well. Therefore, there is uncertainty with the CMS price as
well.
Mr. Pellerin finds this statement of CRA peculiar, as it implies
that CRA did not disclose the full design information in its own
1998 RFP, which document was prepared in association with RMOC
staff. Further, Mr. Pellerin advises that CMS has already
received approval from MOE and the RMOC for a plant designed to
meet the same effluent criteria, as required for discharge to
the Jock River. Therefore, CMS is well aware of the
operational, control and material requirements of the RMOC, and
the approval agency (MOE) issues as well.
3.2 Capital costs for the modified CMS Plant have been assessed by
Mr. Pellerin at a detailed level, on the basis of design-build
implementation as contemplated in the 1998 RFP (CRA). These
costs are all inclusive of design, approvals (including Addendum
to ESR), construction, contingencies and taxes (PST). The costs
reflect the 50% increase in plant capacity to 10.0 L/s
facilitating continuous discharge to the Jock River, and the
provision to by-pass treated effluent to the wetland at a
sustained peak flow up to 30 L/s (Pellerin).
The capital
cost for design-build implementation of the CMS Plant is
$3,331,594. An additional 5% allowance $166,580. has
been added to cover RMOC Engineering and Administrative Costs
for a Total Capital Cost of $3,498,174. A breakdown of
the Total Capital Cost of the Modified CMS Plant is attached (Pellerin).
3.3 Mr. Pellerin has completed detailed rock quantity calculations
based on OMM/Trow information, resulting in an estimated
quantity of 5892 m3 (refer to attachment). Based on
the information available on the proposed pipeline alternative,
Mr. Pellerin has estimated the cost of the pipeline at
$6,883,296., excluding Taxes and RMOC Engineering and
Administrative Costs (Pellerin).
CRA adds - Mr. Pellerin’s capital costs for the pipeline is
$4.855,040. To this is added $1,2000,000 for design and
construction management (Doran Contract), $100,000 for Richmond
Route selection and $728,258 Contingency (15%).
Based on additional information now available, CRA has adjusted the pipeline costs as follows:
• Based on a conventional
design/tender/construction approach and taking into account the
new 1999 and 2000 flow data and the 1999 geotechnical
information completed by OMM/TROW, CRA have estimated the
pipeline capital costs to be $5,500,000.00 (includes 15%
Contingency and 15% Engineering).
• Although CRA believes a 200 mm
pipe is adequate, the above costs, as an upset scenario, is
based on a 250mm HDPE, DR11 pipe material, which has a similar
ID to a 200 mm CLDI pipe, with a burial depth of 2.0m. This
line is capable of transferring approximately 45 L/sec.
• If a design-build approach were
used, as proposed by TPL in 1999 and making the necessary
adjustments to reflect the more accurate geotechnical
information available today, the capital cost was estimated by
CRA tp be $4,865,000.00.
• CRA has estimated 20-year present
worth O&M costs to be $937,000. The 1998 ESR pipeline O&M costs
were increased to include:
• annual pipeline
pigging;
•
5-year cleaning of the holding cell; and
•
sewage collection O&M costs of $4,000/year.
4.
PIPELINE ISSUES
In order to
further evaluate the proposed pipeline from Munster Hamlet to
the Richmond Pump Station with respect to the (i) natural
environment, (ii) social environment, (iii) land use, (iv)
economic and (v) technical criteria, Mr. Pellerin identified the
following issues requiring clarification. These are presented
below together with CRA’s disagreement in
italics.
4.1.1 Munster No. 1 Pump Station may be retained as part of the
lagoon by-pass system, and this must be considered for the
purposes of the evaluation (Pellerin);
Munster 1 Pump Station would not be retained based on CRA’s
evaluations completed in 1998 and early 1999 (CRA).
4.1.2 Terracing of Cell No. 1 is proposed to create a “fairly deep”
sump to allow by-passed sewage to be drawn back to the Munster
No. 1 Pump Station. As the lagoon bottom is located at rock
surface, an allowance for rock excavation is required (Pellerin).
Lagoon/Holding Cell; CRA does not agree with Mr. Pellerin’s
position on holding cell construction. Terracing is an option
that may be selected during detailed design. Should terracing
of the holding cell be selected during detailed design, the cell
elevations could be constructed in a manner whereby fill would
be used to minimize or eliminate rock excavation. Terracing
provides the advantage of only having to disturb a small portion
of the cell when used for a small volume of storage.
4.1.3 The proposed gravity sewer from the lagoon by-pass sump back to
the Munster No. 1 Pump Station will require substantial rock
excavation. An allowance for the capital and O&M costs for this
sewer and its associated rock excavation is required (Pellerin).
Lagoon/Holding Cell; CRA does not agree with Mr. Pellerin’s
position on construction of a separate gravity sewer. Other
options to a new gravity sewer include using the existing
forcemain to drain the lagoon/holding cell or a small pump
station at the holding cell (i.e., no new sewer required). The
most appropriate option will be selected during detailed
design. CRA’s cost estimate includes actuated valves at the new
pump station and using a portion of the existing 200 mm dia
forcemain to fill and drain the holding cell.
4.1.4 The new Munster Pump Station will also require substantial rock
excavation in close proximity to residential properties along
Dogwood Crescent, Munster Hamlet. Pre and post structural
audits of these homes together with vibration monitoring during
blasting should be included (Pellerin).
Rock excavation for the new Munster 1 Pump Station has been
included based on a borehole located near Munster 1 Pump
Station. A pre- and post-rock excavation structural audit of
homes along Dogwood Crescent is a low cost item and good
practice when excavation of rock is encountered (CRA).
4.1.5
Pump Station Building - as a much larger generator is
required together with fuel storage, and chemical addition
(ferrous chloride) for H2S control, a new building
meeting the current RMOC specifications for a generator room and
chemical storage should be included, such that the same standard
as that proposed for the mechanical plant is met (Pellerin).
CRA does not agree with Mr. Pellerin’s statement. Sufficient
floor space area exists within the Munster 1 Station metal clad
enclosure for the generator set and chemical storage and feed
system. There is an existing unused storage room in Munster
Station that is available for use for the chemical system.
Therefore, no new building is required.
4.1.6
Forcemain Depth - based on RMOC engineering standards, the
forcemain requires a minimum depth of cover of 2.40 metres. The
forcemain diameter (OD) and bedding depth for rigid or flexible
pipe (depending on the material selected) must then be added to
determine the full depth of excavation. Further, if the
forcemain is to be located in the travelled portion of the
roadway or its zone of influence, a greater depth of bury may be
necessary, as indicated by Mr. Jeff White, P.Eng. of Delta
Engineering who has expertise in this area (Pellerin).
CRA does not agree with a 2.4 m depth of cover. The depth of
frost should govern. Based on MOE Guidelines for the design of
Sanitary Sewage Works the frost penetration depth for the Ottawa
area is calculated as 1.6 to 1.9 m depending on the type of soil
material. Frost penetration is greater than 2 metres for poorly
graded gravel and rock, however these materials will not be used
for backfill above the pipeline.
For evaluation CRA has used a 2.0 meter depth of bury to top of
pipe.
The RMOC guideline of a 2.4 meter cover is for Regional
watermains and not sewer forcemains. Forcemain depth is
determined on a case by case basis. It is CRA’s understanding
that the current OMM design was based on a 2.0 m bury to top of
pipe. Note that sewer forcemains operate at different
temperature than a watermain (CRA).
It
should be noted that the RMOC guideline of a 2.4 meter cover is
based on road centerline elevation. Therefore when a pipeline
is placed along the shoulder of the road (as proposed for the
sewer forcemain) the actual depth of cover would be in the range
of 2.2 to 2.3 meters (CRA).
Instead of increased bury depth, other options for frost
protection on pipelines include rigid insulation placed in
backfill (CRA).
In Mr. Godin’s
own testimony he indicated a 2.4 m depth of bury to be the
criteria required for the proposed pipeline (Pellerin).
4.1.7
Trench Depth - as the actual forcemain material currently
proposed is unknown, a minimum depth of excavation of 2.85
metres should utilized for quantity calculation. This allows
for up to a 250mm diameter pipe (HDPE) plus depth of granular
bedding material (Pellerin).
CRA does not agree with Mr. Pellerin’s line of thinking here as
the exact pipe material will be determined during final design
and will have a minimal impact on depth of excavation.
4.1.8
Rock Quantity Contingency - the geotechnical investigation
undertaken to date (OMM/Trow) consists of boreholes at spacings
up to 100 metres, with no rock probing between borehole
locations. Given the limitations of this information with
regard to the spacing of boreholes, a sizable contingency should
be carried in the rock quantity take-off calculation for the
known portion of the pipeline route (Pellerin).
CRA does not agree with Mr. Pellerin that additional contingency
should be carried on rock quantities. It should be noted that a
substantial overall contingency was carried in the cost
estimate. The borehole rock profile looked consistent and did
not indicate a highly variable profile. It is just as
conceivable that the borehole information that the borehole
information overestimated rock excavation quantities as Mr.
Pellerin’s claim that it underestimated rock excavation
quantities.
Mr. Pellerin
adds that it is normal practice to apply an overall estimating
contingency (15%) at the preliminary design stage, particularly
when fundamental design issues are still undecided. In
addition, it is also normal practice to apply contingencies to
specific rock and earth quantities, particularly where quantity
calculation is based on preliminary geotechnical information (Pellerin).
4.1.9
Jock River crossing - crossing of the Jock River at
Richmond, and connection to the Richmond Pump Station is to be
undertaken by open trench excavation. As rock is located close
to the surface at this location, rock excavation (blasting) will
be required. Potential impacts to the existing forcemain and
any other utilities must be mitigated. Again, pre and post
structural audits of adjacent buildings together with vibration
monitoring during construction will be required (Pellerin).
CRA does not agree with Mr. Pellerin’s statement that the
crossing of the Jock River will be undertaken by open trench
excavation. CRA’s review of the Richmond Pump Station drawings
indicate that the existing line crossing the Jock River has a
variable depth of cover in the range of 1.5 to 2.8 m. This
should be sufficient to allow for several options for the method
of pipe crossing for the Jock River. Again, the exact method
will be determined during final design. Furthermore, it is
speculative to assume large quantities of rock excavation at the
Richmond Pump Station and Jock River Crossing.
Mr. Pellerin
adds that it is irresponsible to dismiss this factor in the
absence of definitive information.
4.1.10
Rock Excavation in Richmond Village - rock may be
encountered on the pipeline route through portions of the
Village of Richmond (other than Jock River crossing). As this
is currently an unknown, a suitable contingency for additional
rock excavation and mitigation measures must be added (Pellerin).
CRA does not agree with Mr. Pellerin’s statement. CRA noted
that during their pipeline route study they reviewed well logs
in Richmond which indicated an overburden of 3 to 5 m cover over
rock. The rock profile drops off at Richmond. CRA did not feel
that an added rock contingency should be added for the pipeline
through Richmond.
4.1.11
Rock Quantity Calculation - Mr. Pellerin has now completed
detailed rock quantity calculations based on OMM/Trow
information, resulting in an estimated quantity of 5892 m3
- refer to attachment (Pellerin).
CRA’s estimated rock quantity is 3,500 m3 based on
OMM/Trow information, and a 900 mm wide by 2.5 m deep trench.
For rock
quantity calculation, Mr. Pellerin recommends a standard trench
width of 1050mm (OD + 800mm) for a forcemain < 400mm in
diameter, together with the 2.85 m depth noted under item 4.2
above.
4.1.12
Impact to Private Wells - contingency measures and funding
must be in place for both temporary and permanent impact to
shallow private wells along the proposed pipeline route
(Franktown Road and Richmond Village), due to the potential for
draw down of the shallow aquifer through the pipeline bedding
material, both in areas of permeable soils and/or as a result of
rock excavation (blasting) activities (Pellerin).
CRA did not concur with Mr. Pellerin that contingency measures
should be carried for both temporary and permanent shallow wells
along the pipeline route since construction contingency measures
would address this impact.
4.1.13
Private Well Monitoring - monitoring of private wells pre,
during and post construction will be required to establish
background conditions, as well as short and/or long term impacts
of the pipeline construction.
CRA does not agree that monitoring of the shallow wells during
construction is required. However, CRA noted that detailed
design should investigate this further as the costs to maintain
would be minimal.
Mr. Pellerin notes that it is
impossible to establish the success of a construction
mitigation measure and
associated costs, unless background
conditions are first established.
4.1.14
Trench De-watering - open trench excavation is proposed
through the Richmond Fen. Provision for trench de-watering in
areas of permeable soils should be considered as well as
mitigation of groundwater movement both during construction, and
long term through the pipeline bedding material (Pellerin).
CRA does not agree with Mr. Pellerin’s statement. There are
several options for the construction methodology for the
pipeline that travels adjacent to the Fen. It is inaccurate to
assume the type of methodology at this time as it will be a
detailed design issue and will also be impacted as to the time
of year construction takes place. Depending on the time of
season for the construction, the degree of dewatering may be
minimal. Competitive bidding will result in low cost pipeline
installation in the area as demonstrated by TPL’s 1998 proposal
to the RMOC. Furthermore, use of HDPE one pass trench
installation is not affected by water depth.
As stated in
evidence, Mr. Pellerin notes that TPL’s 1998 proposal costs were
incomplete as confirmed by Regional Engineering Staff before
Corporate Services Committee of Regional Council in January
1999.
Mr. Pellerin’s
stresses that trench de-watering requirements are an unknown,
and given the permeable soils identified by OMM/Trow, reasonably
conservative assumptions must be made until such time as further
details are available.
4.1.15
Sedimentation in Pipeline - the precipitant formed by the
reaction of ferrous chloride with generated sulphide will form a
relatively dense floc (ferrous sulphide) which will settle in
the forcemain, particularly in Summer conditions when both
sulphide generation and anaerobic activity within the pipeline
are at an annual maximum, and flows at an annual minimum - 300 m3/Day
(Pellerin).
CRA does not agree with Mr. Pellerin’s Statement. The floc
formed by ferrous chloride addition is not dense. Sufficient
scour velocity has been designed in the pipeline alternative to
prevent the build-up of chemical sediment from the odour control
strategy. Operating strategies to benefit sediment build-up
through use of high-flow pumping and pigging has been included.
These strategies have been used successfully throughout North
America, and in particular by the RMOC at the Richmond forcemain
which has a higher HRT than Munster and at the RMOC Carp 10.5 km
forcemain. CRA notes that the H2S control method on
the pipeline has been agreed upon by the engineers.
Mr. Pellerin
notes that the concern expressed is not H2S control,
but rather sedimentation of an 11.5 km small diameter forcemain,
and the potential operational problems and O&M costs.
4.1.16
Forcemain Operation and Maintenance - in these conditions it
may be necessary to operate the forcemain at an increased
velocity (and pump rate) to sufficiently scour the line. In
addition, an operational allowance for annual pigging of the
forcemain should be considered in conjunction with the annual
O&M costs (Pellerin).
An
annual allowance for pigging the forcemain will be has
been added to the pipeline O&M costs. Typically, this cost is
minimal (i.e., 2 man crew for 10 hours). This could be
completed during the Spring wet weather periods where water for
pigging from the holding cell may be used (CRA).
4.1.17
Pipeline Route Through Richmond - a further public
consultation process is required to evaluate and select the
pipeline route through the Village of Richmond. The time frame
and cost of this undertaking should be considered in the
pipeline evaluation (Pellerin).
CRA does not agree with Mr. Pellerin’s statement. The public
and government consultation process for the pipeline route
evaluation through Richmond was not included in the pipeline
capital cost. CRA believes it should not be included as it is a
follow up effort of the EA effort and the project EA costs were
not assigned to any of the wastewater alternatives.
Furthermore, it is reasonable to expect that other alternatives
may require additional EA costs as well.
Mr. Pellerin
disagrees noting that he has carried a cost for an Addendum to
ESR (EA approval) in re-evaluating the cost of the mechanical
plant alternative.
4.1.18
Impacts to Richmond Village - the construction of the
pipeline through the Village of Richmond incurs natural
environment, social environment, and economic impacts to the
Richmond Residents that are not incurred with the on-site
treatment alternatives. These impacts, such as potential loss
of business activity from construction, disruption effects (i.e.
reduced road traffic), and impacts on the Jock River should be
reflected in the evaluation (Pellerin).
CRA does not agree with Richard Pellerin that loss of business
activity from construction of the pipeline through Richmond
should be included in the evaluation. It is not determined that
any business loss would occur and that common construction
practices would be maintained to not disrupt business activity.
It is Mr.
Pellerin’s experience that assessment of social or economic
impacts on the community and/or downstream community(s) for any
given alternative is common in an EA evaluation, and entirely
appropriate in this instance.
4.1.19
Richmond Pump Station - the capital costs of the interim and
ultimate upgrading of the Richmond Pump Station, which is
clearly influenced by the addition of Munster’s sewage flows,
should be reflected, on a proportionate basis, in the evaluation
of the pipeline alternative (Pellerin).
CRA does not agree with Mr. Pellerin’s position that the capital
costs for the interim and ultimate upgrades for the Richmond
Pump Station be included, on a proportionate basis. The
philosophy of the pipeline alternative was to take advantage of
capacity that is available under typical dry weather flow
conditions. The whole concept was to be able to use the
Richmond Station’s capacity that was sized for peak events and
that was not used the majority of the time. Adrien Comeau’s
memo of August 12, 1998 firmly confirms this concept and it
further confirmed by detailed instantaneous 1999 flow data. A
further objective was not to jeopardize infrastructure capacity
assigned for future growth. This is also addressed in Mr.
Comeau’s memo whereby in 20 years and under full build out in
Richmond, transfer of Munster’s sewage flows to Richmond will
not affect Richmond’s infrastructure capacity.
Mr. Pellerin
advises that the 1999/2000 data from RMOC confirms that the
capacity of the Richmond Pump Station was exceeded in
consecutive years, contrary to the previous findings of Mr.
Comeau. In addition, the unsustained (up to 3 hours)
instantaneous flow of 45 L/s as agreed upon by the engineers is
greater than the capacity of the Munster Pump Station as
currently proposed by CRA (30 L/s). These conditions together
with annual pump station and forcemain maintenance will require
more frequent by-pass of raw sewage to the Munster lagoon than
previously indicated.
CRA does not agree with Mr. Pellerin’s statement. Pumping
capacity to the holding cell addresses the 45 L/s. Furthermore,
detailed design may elect to implement a 45 L/s transfer system
to Richmond. CRA’s cost estimate has included pumps and piping
to transfer 45 L/s to Richmond. It is reasonable , that under
competition, pipelines of High Density Polyethylene (HDPE),
Polyvinyl Chloride (PVC) and Cement Lined Ductile Iron (CLDI)
could be similar in overall system capital costs. CRA stresses
again that the 1998 TPL proposal to the RMOC was for a CLDI pipe
utilizing open trench technology.
Again, CRA stresses this was a very attractive price, based on a
design-build approach under competition.
CRA does not concur with Mr. Pellerin’s statement that
“1999-2000 data from RMOC confirms that the capacity of the
Richmond Pump Station was exceeded in consecutive years”. CRA’s
review of the data shows the Richmond pump station capacity was
exceeded for the period of 3 days in 1999 (April 8, 9 1999) and
not at all in the Spring of 2000.
(CRA)
Note that in the data received from the Region for the Richmond
Pumping Station spring 2000 flows, which is the max reading per
10 minute interval, there was one extraneous data point on April
8, 2000. The raw data is listed below:
OMB FILE No. O 990089