| |
Comment
Sheet #2
Comments from Open House #2
(August 19,1998)
illustrate public frustration over time-delays, amidst
relentless Regional interference, scarce factual information and
copious amounts of official 'misinformation' (to put it politely).
Time Urgency was important to
residents, but appeared not to be for CRA or the Region:
| |
TIME URGENCY-
Residents' written comments:
-
“Hope
that the ensuing study won’t take too long.”
-
D&L W, 4 Caddy Crt.
-
“…as
soon as possible.”
– LF, 36 Butterfield Rd.
-
“I
believe the
treatment plant could be up and running sooner than the
pipe. As I see it there are fewer problems with obtaining
the necessary approvals. I have grave concerns that the
objections based on environmental concerns could delay or
ham-string the pipe. I also see the potential for legal
problems in that the RFP seems not to have provided for
proposals based on pipe. This I saw as an omission
back in June and it grieved me.”
– GS, 7861 Franktown Rd.
-
“Hopefully there won’t be any further delays.”
– LD, 45 Butterfield Rd.
-
“…proceed with minimal delays and give a timely solution
to this long awaited solution.”
SB, 7907 Copeland Rd.
-
“Get on
with the job!”
– LD, 87 Owlshead Rd.
-
“Lets
get on with it!
– SC, 25 Butterfield Rd
-
“Considering the
delays inherent with the pipeline to Richmond proposal and
costs requiring final resolution …I would see the
preferred method as Mechanical Plant with discharge to the
Jock River.”
– KL (P.Eng.),
44 Owlshead Rd.
-
“I
am concerned with the potential for delay with all the
bureauracy and red tape that lies ahead for this proposal
(the pipeline selection). Let’s hope that for the
betterment of all concerned that the issue moves forward
expeditiously.
– GW, 9
Owlshead Rd.
-
“Going
with the sewer pipe option would delay remedial
environmental measures by one to two (or more) years, than
if the mechanical treatment process were chosen.
...(The)
pipe was not included in the RFP. Therefore, favouring a
pipe option as part of this RFP has “terrible optics”. To
proceed down this slippery slope would ...invite
litigation from other bidders (who bid in good faith).
...(Also)
the whole issue would most certainly lead to an OMB
hearing and other untold number of delays.”
-
Richard Bendall, (Member of the Munster Lagoon
Watchdog Committee, and member of the Munster PLC).
-
“(Those
who have concerns with the pipeline selection) could lodge these
concerns to the Ontario Municipal Board, which just might
delay the application.”
- GG, 26
Butterfield Rd.
-
“One
concern which I have is that the time required for this
option (the pipeline) to be realized may be long.
This may result in the RMOC becoming impatient and
implementing the previous plan of spray irrigation which I
reject because of the space required. For the pipeline,
there will be a number of approval processes that have to
be completed and each of them may be very time consuming.
The main argument will be that we are merely displacing
our problem not solving it.”
– BW, 40
Owlshead Rd.
-
“A third
public meeting should be held to discuss final decisions
and timelines. The timelines are very important because it
appears that this (a pipeline) could take 3 years to
actually operate.”
– CK, 11
Lakewood Dr.
-
“I will
be very satisfied when the solution is implemented and I
never have to hear the words ‘lagoon issue’ again.”
– JK,
28 Stroughton Cresc.
-
“…as
soon as possible”
– JS
7930 Bleeks Rd.
-
“…let’s
get on with the project. …do not hold up this important
decision any longer. …we deserve action. Please speed up
the process”
– P&Y E,
16 Chelmsford Cres.
-
“Let’s
make it (the decision) soon and get started.”
– CS,
7702 Bleeks Rd.
-
“A
speedy solution is critical.”
– AW, 7
Cone Terrace.
-
“Although I agree with the first choice (a pipeline) on
the surface, I wonder if
a local treatment
plant right in Munster might make more sense in the long
run and also might take less time to get up and running.”
– SI, 80
Otterburn Ave.
-
“I am in
agreement with the pipeline alternative. However, I fear the process
might get “bogged down” in appeals due to the Wetlands (Richmond Fen). …I would prefer to see a Mechanical
Plant with RBC as this would cost about the same
(according to your numbers). I like the idea of a
Mechanical Plant in Munster because of the increased sense
of self-sufficiency with that option.”
–
RW, 40 Owlshead Rd.
|
|
|
Unsettling
Observations:
| |
In the period between the first and second Munster Meetings,
several ‘troublesome
developments’ occurred during the Environmental
Assessment (EA) process.
-
“Time Urgency” was
left out of evaluation criteria
– and the subject of "time urgency" was evaded by the Consultants. The Project Leader
was asked at the second public meeting, by two members of the
public (affidavit available), why the “time urgency” issue
was left out of the Evaluation Criteria (Matrix). His response
was,
“What time urgency?”
– Yet the Original
Council Motion stressed the requirement to guarantee to meet
the (MOE) compliance schedule (of approximately 1 year), and
Munster Residents certainly felt the need for time urgency
(see box of comments on 'Time Urgency', at top of
this page).
-
The RMOC and Consultants, running the Public Liaison
Committee (PLC),
barred the
Public
from quietly auditing their meetings. (So much for the meaning
of ‘public’!) Even one Environmental Student, doing his
thesis (on the EA process), was barred from the meetings.
It gave the
appearance that the Consultants may have had something to hide.
-
The
RMOC and
its Consultants on the PLC, placed gag orders on its
members, during the second public meeting ---on threat of
expulsion. (For those members trying to keep informed for the
public's sake, and attempt to communicate internally with the
already-seriously-compromised committee, it left little choice, but to temporarily keep silent.)
-
Many
individuals close to the process observed with increasing
concern, what appeared to be unsubstantiated
‘technology bashing’. When asked to provide any evidence
to support their defamatory allegations, the
Consultants could not provide it.
For example:
The Consultants created the impression that the Phosphorus
output of the RBC Sewage Treatment Plant would be detrimental
to the Jock River. They failed to correct one Councillor who
said (in their presence) that
“tonnes
of Phosphorus” would be dumped into the River
by the RBC-mechanical treatment plant.
In fact,
only
one level tablespoon of
Phosphorus would be discharged, in a 24-hour period
…significantly
lower that than the River’s ambient
Phosphorus level (thus creating a beneficial ‘diluting
effect’).
The Consultants,
(as well as those municipal politicians and staff members),
who made the numerous distorted and defamatory
assertions
are likely to be challenged in court when the pending
litigation transpires.
-
Important
questions not answered: (The more
probing the questions, the more the PLC-member questioners
were ostracized, for not being team-players.)
-
The Consultant’s made unsupportable allegations that:
-
Dry ditch
discharge was not safe ...when, in fact, the effluent
quality would be that of Ontario’s
swimable water
quality. (All-the-while ---as we wait for a
solution--- raw sewage leaks from the lagoon cells,
into the Copeland Road ditch, and groundwater (Reference TSH
– ESR, 1996)).
-
That bidders could not meet Policy 2 effluent criteria.
At the very same
time of that allegation, one of the bidders, (CMS), was
receiving an MOE Certificate of Approval (C of A) for a
treatment plant to go into a Manotick project ---to
discharge into a Policy 2 watercourse.
(At the OMB Hearing, Conestoga-Rovers and Associates denied
any knowledge of the Manotick C of A. One can only surmise
that the Region’s failure to inform CRA of the impending C
of A, is
indicative of their commitment to another
pre-determined selection.)
-
That
Mechanical Plants were at high risk of break-downs. CRA
singled out the RBC System as posing a risk of impending
disaster, due to a high potential of shaft breakage. Of the
L-1500 shaft type proposed for Munster, there has
not been a single known shaft breakage, after literally
millions of hours use.
Furthermore, with the three RBCs --- as proposed for
Munster--- there would be triplicate
redundancy.
(Appearance of the practice of
fear-mongering
is not a fitting or ethical way to disqualify a front-running
wastewater treatment system, in order to promote an inferior
pre-determined selection.)
-
That the proposed pipeline did not
require lagoons. The
Consultants told the public ---who were
bent on getting rid
of the lagoons (see Comment Sheet #1)--- that
"temporary holding cell"
use would be 1-2
days, once or twice a year. At the OMB, two Engineering
Experts testified that, with the small-bore forcemain
running such long distance, dealing with such variable
flows,
a lagoon system
would have to be in
operation ALL-YEAR-ROUND!
(Some recent developments with
regard to the Richmond
'temporary-use'
Lagoons verify this –See LINK to “RICHMOND”)
-
That
pipeline capital cost was less than that, for a Mechanical
Treatment Plant. Evidence at the OMB Hearing
demonstrated this to be
false.
-
That the pipeline/lagoon system O & M costs where the
lowest. Evidence at the OMB Hearing demonstrated this to
be false.
-
That Pipeline does not pose an
unwarranted risk to the Richmond Fen. How can such
claims be made, when
an on-site
Treatment Plant poses ZERO risk to the Fen,
and
especially when
the
Richmond-Kanata
forcemain has broken five times in the previous 19 years).
-
Requested
rationales not given,
as promised, in time for second public meeting. Grossly
inadequate, superficial, rationales were given,
about a month
after
the Public Meeting of August 19, 1998. The Consultant’s
criteria and rationales came under scrutiny at the OMB. The
OMB Ruled that the City’s case was
not “perfected”,
and that it did not have the evidence to support a pipeline.)
-
Stories of the occurrence of
several
RFP irregularities
became prevalent:
(One story was, that the
non-compliant
pipeline bids had been solicited. (The public had been told all-along, that the pipeline
bids were
"un-solicited".) Finally a letter surfaced, in
which
Taggart admitted,
in writing, that they had been solicited to put in a pipeline
bid. Another
instance, was when the deadline for the “unsolicited” pipeline
bid-deadline was delayed for two weeks to allow for their
non-compliant
inclusion.
Also, it appeared 'irregular' for the Region’s Engineer to be
receiving the incoming bids ---right in the Consultant’s
office. These are just three quick examples...
-
Bidder's costing was
publicized at the Public Meeting (August 19th),
at
near double the amount (in some cases), the
guaranteed
amounts submitted under the RFP
..without the agreement (or proper opportunity for
refutation), by the bidders).
-
The
published costing on the pipeline selection, was absurdly
low,
with
final pricing to be determined “at the design stage”.
(In other words, the non-compliant pipeline bidders were given
‘carte blanche’, to cost whatever they wanted, during the
design stage, or build the pipeline on a cost-plus basis).
All bidders had been ordered to put in guaranteed pricing.
All-the-while,
the
city had, in its possession, far more accurate costing figures
from Totten-Simmes Hubicki, (prior to the RFP), quoting in
the $12 Million to $15 Million range. (The City has since
broken the various items of this costing into individual
project segments---i.e.: Richmond Pumping Station
upgrading, twinning of the pipeline across the Jock River,
upgrading the Richmond Lagoons, etc., and has been proceeding
with work orders in these areas ---ON THE
ASSUMPTION IT WILL BE PROCEEDING WITH THE MUNSTER
PIPELINE/LAGOON SELECTION.
This is in
direct defiance and contempt
of the OMB Order. See the “RICHMOND”
LINK (at the top of the Home Page, for more details)
-
Unsatisfactory answers regarding lagoon
decommissioning and reconstruction:
Neither the Region nor the Region's Consultant could be pinned
down on how
SAFE
decommissioning of the lagoons
would be carried out, without disrupting the
sludge, in the event that an option was selected that required NEW lagoon(s).
It would pose a huge risk of groundwater contamination,
in the event that the City scraped away the sludges in the old lagoons, to rebuild new
ones in the same location (which
is what they appeared to be planning to do). If an
alternative is used that requires lagoons, then the full cost
of constructing new lagoons at a new location should be
calculated, and proper retiring and decommissioning of the old
lagoons should be done as a separate task,
without disturbing the sludge seal that rests on top of
its fractured rock base.
-
Even at this early
stage of the process" it was becoming more apparent,
day-by-day ---that "THE PIPELINE/LAGOON-FIX WAS IN".
|
|
Non-Statistical
Numerical
Results:
| |
Public Open House #2 – August 19, 1998
SUMMARY of the Comment Sheet Responses
...with
---Non-Statistical---
total of
38
Respondents
* Pipeline
without a lagoon was offered, but was not a valid
option. It
is important to note that Munster residents wanted rid of
the lagoons, and they were
wrongly informed that the only way to get rid of the
lagoons, was to select the pipeline option. However, at
the OMB Hearing, highly qualified pipeline experts for the
Appelants gave evidence that a forcemain of the size
and length intended for Munster, would require full-time
use of a lagoon. For this
reason, the pipeline support numbers are completely skewed
by the misinformation.
Actual count of
30
persons whose 1st choice was a pipeline (believing that lagoons
were excluded), dropped to a mere
2
persons (who thought that a lagoon may still be part of the pipeline
option process).
Comment Sheet: FIRST-CHOICE OPTION
(where ONE OR MORE options may have
been mentioned as acceptable):
Pipeline
(First) -
Falsely described
as NOT
requiring a lagoon*
.........…[Number
of persons = (30)] …78.95%
Mechanical Treatment
(First),
Falsely described by
consultants as requiring lagoons........... (7) ….18.42%
Snowfluent
(First) ……………..........................................................................................….… (1)
......2.63% ============ Total = 100%
____________________________________________________________________________
Listed frequency
of Acceptability
(Stand-alone preference or
combined with other option preferences):
1.) Pipeline Acceptability –FALSELY EXCLUDING
Lagoon(s)
–
All combinations ...........................(35)…92.11%
a., b.
2.) Mechanical Treatment
Acceptability With
Lagoons FALSELY INCLUDED–
All combinations .…(12)…31.58%
c.
3.) Pipeline Acceptability –CORRECTLY INCLUDING Lagoon(s)
–
All combinations..…............................(2) ….5.26%
d.
4.) Snowfluent Acceptability
–
All combinations …………………….............................................……(1) ….2.63%
5.) Lagoon & Spray Field
Acceptability
–
All combinations ………............................................….…(1) …2.63%
__________________________________________________________________________________________________
Time Urgency Concerns……………………………..………….......................................……………(21)
.….55%
______________________________________________________________________________
Summary:
Twenty-five percent of the
‘pipeline acceptable’ respondents had
contradictory or
confused comments
(For example: They supported a pipeline as their first or
second choice, because:
● "The various other proposals
seem expensive
and from what I
have been informed
are only a band-aid
solution";
or,
●"The idea of having ever-larger
sewage treatment plants, at huge cost, is not feasible",
or,
●" I was very pleasantly surprise(d) to learn that a pipeline
to Richmond was
the least expensive method of treatment").
Twenty-five percent represents a very high confusion rate.
That does not include the percentage of residents who
believed that the Consultants were providing full
disclosure when they stated that there would be no lagoons
with a pipeline
---merely an "emergency holding cell", to be used one to
two days, perhaps one to two times a year, then emptied
and flushed right away. (a.)OMB
evidence definitively proved that the proposed
pipeline, requires full-time use of lagoon(s).
Of the 92.11% who indicated pipeline
acceptability, only
two respondents, (5.26%), acknowledged that
a lagoon presence ---with the pipeline was acceptable. It
is assumed that the other 86.85% were indicating
acceptability of a pipeline
(b.)---in
order to get rid of the lagoons--- (see: "GettingRid of the Lagoons":
Comment Sheet #1).
(d.)Therefore,
it is expected that the fall-off rate of acceptability of
the pipeline would be rather dramatic,
once residents
become aware that the Munster pipeline design includes
continuous lagoon usage.
Those selecting
the pipeline option (in general) provided comments that
were more terse, demonstrating ---perhaps—a rather
superficial examination of the issues. Mechanical
treatment comments were of greater length, providing
detailed rationales, and demonstrating a more studied awareness of all issues (i.e.: environmental, land use
planning, socio-economic, efficiency, etc.) involved in
this complex problem.
____________________________________________________________________________
It is important to
note that, in spite of the profound
‘lack of clarity’
(see: "Lack
of Clarity of Comment Sheets":
Comment Sheet#1),
put before the public on August 19, 1998, a full 31%
of respondents still indicated a knowledgeable acceptance
of the mechanical treatment system.
(c.)
Proper presentation of the facts, (including the
pipeline requirement for a sewage lagoon), may
well have put that support level over the 90% range.
Irrespective of CRA’s one-sided
presentation …based on missing, incomplete and erroneous information,
(as detailed in the OMB Decision)e.,
it is no surprise that the pipeline option drew a majority
of votes. Had the evaluation matrix (confusing as it is)
been presented, and walked through ---with the
Consultant's rationales for each rating--- the audience could
have been able to identify
the many errors in its logic,
and form 'their own' opinions. The result
would likely have been much different.
| |
(e.)
(OMB Decision, pgs. 14 &
15 - Chair, N.M. Katary:
"Here, the
evidence by the wastewater engineers who appeared in
opposition is helpful. Both Mr. Pellerin and Mr. White
pointed to a number of
specific instances where data used by the evaluation
team in assigning utility values were
either incomplete or simply
missing. ..."An aspect of evidence by Dr.
Nakhla is worthy of note. It appeared from the breadth
and depth of his opinions that he was the principal
engineer in developing and implementing the
methodology of CRA.
...None of
this would be unusual except that his approach to
defending his methodology used in this instance was
more in the
nature of advocacy than forthright professional
opinion.")
To see more on the OMB Decision:
CLICK HERE |
|
|
|
|
|
Conclusion:
| |
Given
the above sampling of highly irregular occurrences,
throughout the EA
process, it is easy to understand public confusion over
which wastewater system was best for Munster, and which system
would still require lagoons, and which would not. Of the
non-statistical sampling of 38 residents, 5.26% ---only
2 individuals--- acknowledged their acceptance of the
pipeline option together with a lagoon.
The other 95% (35 individuals)
were
of the firm belief (having been told so by the Consultants),
that there would be no lagoon presence ---just a pipeline,
with a very temporary “Emergency Holding ‘Cell’”, used 2-4
days a year, which would be flushed clean, and would remain
empty all the rest of the time. THIS INFORMATION WAS PATENTLY
FALSE.
Furthermore, in the
case of the mechanical treatment option ---which is the only
option which truly does not require use of a lagoon---
residents were told by the consultants that this option would
require a lagoon, and that the pipeline would not.
This is the complete opposite of the
truth.
| |
Postscript:
In the year
2004, one
has to consider that public suspicions have been
confirmed, in that: Had
the truth been told with regard to
the pipeline's requirement for year-round sewage retention
ponds, (given the first Comment
Sheet expressions of Munster resident's desire to eliminate
the lagoons), Munster's problem could easily have been solved
by an on-site treatment plant that would have been operational --BY
SEPTEMBER OF 1999-- and
Richmond's shallow aquifer would not have been put into the
distressing position of being subjected to constant
threat of contamination ...caused by the city?
|
|
|
|
|
|
|