|
 |
|
Jul. 9, 2004. |
Big pipe hits new snag
Environmental
groups launch Fisheries Act prosecution
Opponents
say it will 'subsidize 35 years of urban sprawl'
|
PETER
GORRIE
FEATURE WRITER
Just as the next phase of York Region's massive sewer pipe
appears likely to win approval, environmentalists are trying
to stuff a legal plug into the project.
This week, environmental groups launched
a private prosecution against the region, claiming
construction of the pipe which would require pumping up to
66 billion litres of underground water out of the ground near
the sensitive Oak Ridges Moraine violates the federal
Fisheries Act. |
|
|
 |
|
TONY
BOCK/TORONTO STAR |
|
Environmental activist Jim Robb, right, and lawyer David
Donnelly examine slime from runoff into Robinson Creek
from draining of an aquifer, part of Yorks sewer project. |
| |
|
The legal action is a technical
challenge based on the project's impact on Robinson Creek, a trout
stream and tributary of the Rouge River which, in turn, flows
along Toronto's eastern border and into Lake Ontario through North
America's biggest urban wildlands park.
"This is one of the largest dewaterings in
Canadian history, into one of Canada's most sensitive watersheds,"
says David Donnelly, a Toronto-based lawyer representing the lobby
group Environmental Defence.
It "makes a mockery" of
the provincial government's recent commitment to get tough on
permits to remove underground water for bottling and other
purposes, says Jim Robb, general manager of Friends of the Rouge
Watershed.
Opponents hope if they derail work on this
phase, they could impede plans for the entire $800 million
project, intended to flush about 740 million litres of sewage a
day from rapidly expanding communities north and east of Toronto
to a treatment plant at Pickering, on Lake Ontario.
The overall project, "is a plan to subsidize
35 years of urban sprawl all the way to Lake Simcoe," Robb says.
"Governments are handing developers money to destroy the
environment ... in breach of the law."
A York Region justice of the peace is to hear
submissions Wednesday on whether the case is solid enough to
proceed.
Today, however, the Toronto and Region
Conservation Authority is expected to approve five permits to
remove the underground water, as recommended by its staff.
And the provincial environment ministry is
also likely to announce its approval by the end of the month.
The federal Department of Fisheries and
Oceans, however, is still studying the issue. York Region is
seeking federal authorization although it isn't required. The
department could lay charges after construction starts, with fines
of up to $300,000 a day, if fish habitats are disturbed.
It has already laid charges against the
region in connection with the first phase of the sewer project.
Those charges are still outstanding.
Meanwhile, water is being pumped out of the
ground to ensure Phase II can go ahead if it's approved. Plans
include a main pipe, 2.7 metres in diameter, up Leslie St. to
communities north of Newmarket.
It would twin a system, built in the late
1970s under Yonge St., that is almost filled to capacity with
sewage. Several housing developments face delays because the
existing pipes can't handle their wastes.
Brian Denny, chief administration officer for
the Toronto & Region Conservation Authority, and Anne Neary,
manager of technical support for the ministry's central region,
acknowledge problems with the project's first phase, which
included a branch line along 16th Ave. in Markham from the 9th
Line to west of Markham Rd., and another short section along the
9th Line, finished this spring.
The sewer system mainly uses gravity to
propel wastewater down toward Lake Ontario. The main or "trunk"
pipes must be buried up to 50 metres deep in the ground to create
enough slope for smaller feeder lines.
At that depth, the pipes are in an aquifer, a
layer of sand and gravel saturated with water water that must be
removed before the pipe can be built.
An environmental assessment which a 2002
York Region report describes as only "cursory" was conducted
before Phase I. But once work started, it became clear the amount
of water to be pumped out was far greater than estimated, Denny
says.
Some streams went dry. Others, with torrents
of water discharged into them, flowed much higher and faster than
normal, causing erosion and damaging rare fish. The underground
water, at a constant 10C, is colder than surface water in summer
and warmer in winter, which may harm fish, and contains iron,
phosphorous and other substances that poison fish.
On top of that, at least
100 wells went dry as the water table dropped from five to 50
metres over 65 square kilometres.
Charges against York Region were laid under
the federal Fisheries Act in connection with construction along
the 9th Line; the fisheries department is considering more charges
because of impacts along 16th Ave.
But officials with the conservation authority
say they're satisfied with the corrective measures for Phase II
which continues west along 16th Ave. to Warden Ave proposed by
York Region after months of discussions and negotiations. "We
think we've got a pretty good solution ... that we're prepared to
recommend," Denny said.
The provincial environment ministry says it
has all the information it needs for a decision. "Because of our
experience with Phase I, we went back to York Region and said we
wanted very detailed assessments of impacts or potential impacts,"
for Phase II, Neary said.
The new plan spreads discharges among more
streams. The water will be given time to warm up in summer or cool
in winter before it's dumped. If necessary, it will be heated in
summer, Denny said.
As well, the region must monitor the impact
of the project for several years after it's built.
The extra cost is at least $8 million and
could go much higher.
But opponents say the measures are
inadequate, untested, and haven't undergone an environmental
assessment.
"While the proposed mitigation plan is
ingenious and intriguing from an engineering point of view, (we
are) unaware of any similar undertaking being tried elsewhere, let
alone achieving success," Ron Christie, chair of the Rouge Park
Alliance and a former assistant deputy minister with the
provincial Ministry of Natural Resources, stated in a letter to
the federal fisheries minister.
The Fisheries Act prosecution couldn't stop
the project, but it could force a costly and time-consuming
reconsideration of the mitigation measures, said lawyer Donnelly.
If the environment ministry approves dewatering for the pipe, the
group will seek an injunction under the province's Environmental
Bill of Rights, he said.
Great Lakes United, a joint American-Canadian
environmental lobby group based in Buffalo, other environment
groups and a local member of Parliament, Tom Wappell, have
demanded a full environmental assessment of the project.
Opponents believe York should look after its
own sewage. Further, because the proposed pipe is so deep in the
ground, the pressure outside the pipe would be greater than
inside. That means as leaks inevitably develop, underground water
would flow into the pipe and be carried with the sewage to Lake
Ontario. Such "infiltrated" water would make up as much as 20 per
cent of the flow, according to engineering reports prepared by the
region. That would have a significant impact on the underground
water supply, say the groups.
Opponents recommend smaller,
pressurized pipes close to the surface that don't interfere with
underground water and can be easily repaired. They also suggest
smaller, local treatment plants and marshes that naturally cleanse
sewage.
Toronto Star |