Subject:
TRAIL ROAD LEACHATE MANAGEMENT

Letters of Concern and Written Presentations
to Planning and Environment Committee, to Council
and Letters to the Editor

 

     


One observer’s perspective
of the (2004) Trail Road EA Process (especially as it relates
to the functioning of the Public Liaison Committee –PLC).

 
 

Councillors:

As an outside observer at the PLC meetings, all I had to do is observe.

First of all, I was struck by the professionalism demonstrated by all of the public members of the PLC. Any objective EA process could not have dreamed of having a more balanced, talented and forthright collection of engineering, statistical and environmental expertise, combined with intelligent inquiry, objectivity and plain common-sense. The public members of the PLC were hard-working and considerate of all view points.

I was thoroughly shocked, however, by the disgraceful manner in which the public members of the PLC were treated, by the "evaluation team". They were deprived of requested information (and still are); they were given misinformation by city staff, in particular; they were demeaned and put down on occasion, along with the public itself.

For example, a multi-page document was circulated by the city's consulting engineers, Conestoga-Rovers and Associates (CRA), to PLC members, to supposedly demonstrate complexity of on-site treatment technology. One public PLC member asked why an equivalent document wasn’t produced showing the technical complexities of leachate transmission over forcemains (dealing with sepsis control, risk management, and many other factors). The CRA engineer replied:

"We did not produce the same level of information for pipelines or trucking, because I assumed most of the members of the PLC understood what a pipeline, and what a tank truck, looks like and how it operates."

At the April 14, 2004, Open House, the public was presented with "Comment Sheets" which led off with, "We are interested in your opinion on the relative importance of various Primary Criteria and Sub Criteria"...

An enlightened public expressed --in the most unambiguous terms-- its preference for the on-site technology, shown in the following official numbers for each of the options:

                                                  YES                              NO                           NO PREFERENCE

Pipeline:

11 %

82 %

7 %

Trucking:

11 %

80 %

9 %

On-Site Treatment:

78 %

17 %

5 %

(As quoted from the PLC management team assessment of public comments), the main reasons stated by the public, for their support of an on-site solution, included:

· the ability to more easily "isolate" any problems that might occur;

· that it involved "more modern technology";

· there would be "less impact on (ground)water levels";

· there would be "less exposure to the environment";

· any "leaks would be quicker to catch, and easier to resolve";

· the technology is "more cost effective";

· it is the most "environmentally safe" system;

· use of such technology will become a "necessity in the future", so we might as well
  do it now; and;

· "willing to pay whatever it takes to best-protect public health".

 

When presenting the public comments to the PLC, the evaluation team characterized the public as "uninformed" and "unrepresentative of the population, in terms of numbers of Open House attendees, relative to the population as a whole", even though it was one of the better-attended open houses in recent memory.

The evaluation team ignored multiple requests for a risk assessment of the pipeline and other options, saying, "We wouldn’t know how to do one."

It appears strange to this observer that the consulting firm of (CRA) was reluctant to talk about details of a London, Ontario, on-site leachate treatment plant, that CRA, itself, had built. Was the performance of that plant so bad ---or so good--- that no one wanted to discuss it.

Also, why did the evaluation team not discuss the North Toronto (Britannia) on-site leachate treatment plant, and the Edmonton on-site leachate treatment plant, both of which are huge successes?

The PLC meetings were abruptly cancelled before any meaningful discussion of the available treatment technologies had taken place, yet the evaluation team unilaterally chose to use the activated sludge (AS) treatment model, (like the ROPEC plant), to compare with the pipeline option. The AS system happens to be one of the highest cost options in both capital, and O&M, thus making the on-site option show in less than optimum light. (Reference: A Report to US Congress, as early as the mid ‘70s required that any government-funded treatment plant proposals must be accompanied by comparables of Rotating Biological Contactor -RBC-treatment plant bids, before ANY consideration of funding of activated sludge plant bids, simply because of the significant capital and O&M savings with the RBC treatment system, relative to the AS systems.)

Because of the premature termination of the PLC, the public members have not had any opportunity to question the evaluation team on dubious decisions it had unilaterally taken. This is NOT transparency, folks! (Isn’t transparency what a PLC is supposed to achieve?)

To sum up, the evaluation team is proposing to use a forcemain to transport --toxic leachate—under pressure, right across the city, without any risk assessment, and to pay an on-going fine for non-compliance in toxic exceedences of its own Sewer Use By-Law.

That does not make any sense, at all, when a safe on-site treatment option exists, that is fully self-contained and costs less to build and operate.

Reference Source (in more detail): http://www.ottawasewergatefiasco.com/TR-PLC-record.htm

Richard Bendall
Munster area resident, and Ottawa ratepayer



From: Brian Finch, President of
The Friends of the Jock River

 
 

The Friends of the Jock River
A non-profit, charitable environmental organization
managed and supported by volunteers in the Jock River watershed
www.geocities.com/jockriver

Brian Finch
President,
The Friends of the Jock River,
Box 674
Richmond, ON
K0A 2Z0

Councillors
City of Ottawa

                                                                                                          November 20, 2004

Dear Councillors:

Re:  Trail road Landfill Leachate and Nepean Landfill Contaminated Groundwater

I was a member of the Public Liaison Committee (PLC) for the recently completed Environmental Assessment of the methods to treat leachate from the Trail Road Dump Site and contaminated groundwater from the old Nepean Dump Site.  Based on my membership on this committee and my other experiences on environmental issues, I am able to comment intelligently on the topic.  The following also represents the position of the Friends of the Jock River in support of on-site treatment and in opposition to the pipeline option,

Cost:

The 60 lifecycle cost of pipe is stated to be $17,100,000 and for on-site $21,800,000, but the figures must be questioned.  The figure for on-site has been inflated. 

1.  The groundwater from the old Nepean Dump Site is contaminated with volatile organic compounds (VOCs), specifically, chlorinated hydrocarbons.  In an on-site plant, the VOCs would be removed in a separate, purpose-built facility and the treated water discharged back to ground.  The contaminated water is of finite amount and scope, and would be exhausted in a period of 10-20 years, as is typical in the treatment of closed dumpsite contaminants.  Consequently, some of the capital cost of the treatment facility would be recoverable and, of course, operating and other related costs would go to zero.  The pipeline option would similarly exhaust the contaminated groundwater but the capital would be unrecoverable.  The 60 year lifecycle of the on-site option would be reduced by more than the pipe option.

2.  Based on the projected annual operating costs of on-site, an expert in leachate treatment has indicated to me that the electricity (hydro) cost of $112,200 shows the pricing has been based on an activated sludge process, one of the most energy intensive techniques in current use today.  By comparison, a technology based on rotating biological contactors would consume a quarter the amount of electricity per year for a saving of just under $5M for 60 years.  The difference on this single factor obliterates the lifecycle cost advantage of pipeline.

3.  Two local (Ottawa) companies have designed and installed high tech leachate treatment plants in Canada.  Neither of these companies was asked to comment on capital, operating or lifecycle costs of their systems.  Both have indicated lower capital, operating and lifecycle costs than those indicated in the staff report.

4.  Even if the different lifecycle costs are to be taken at face value, the $4.7M difference over 60 years is $78K per year and $215 per day.   The difference is minor.

5.  It is also of note that the Official Plan requires the City to use other measures besides monetary costs, notably environmental and public safety.  These other “costs” must be taken into consideration.  I would like to point out that the rationale for advancing the O-train was based on environmental and public health considerations, not the simple $ cost.

Environmental and Public Health:

1.  An on-site purpose-built leachate treatment facility would treat the leachate effluent to swimming pool quality, a better quality than the water in the Jock.  Further, the contaminated ground water would be treated in a separate purpose-built facility.  By comparison, ROPEC is a secondary sewage treatment plant that discharges water that is worse than the water in the Ottawa River and relies on dilution for acceptable discharge levels.  ROPEC is designed to treat only human sewage.

2.  On-site treatment will prevent the discharge of a significantly greater proportion of the leachate pollutants into the environment than would ROPEC.  To consider just one of the main pollutants, phosphorous (P), ROPEC would discharge 30 times more P to the environment than would an on-site facility treating the same amount of leachate. The other leachate components that are partially/poorly treated or untreated by ROPEC (such as many heavy metals) would end up in the sludge, which is then distributed on fields, or would be discharged to the Ottawa River and then be available to downstream communities (e.g., Montreal) that use the Ottawa River water for drinking water.

3.  The water discharged to the Jock River would benefit the river.  On-site treatment would retain the water in the watershed and augment the river flow in drought years.  The pipeline option would steal 7 L/sec. (22M L/year) of water from the watershed.

4.   A disturbing fact about pipes is that they break, even so-called reliable pipes!  No engineer will guarantee that the pipe will not break.  Consider the Richmond - Glen-Cairn forcemain sewer pipe, which has ruptured 6 times in the 20 years of its existence.  (While the leachate pipe would be of different material than the above sewer pipe, the risk of rupture will remain.)

5.  Forcemain leachate pipes of the proposed length are considered by engineers to be problematic because of the need for venting of poisonous and corrosive H2S gas, and the requirement to control the biologically active leachate.  Also, the intermittent (stop-start) operation (e,g., every 5-10 minutes depending on load) creates significant transient hydraulic fluctuations, which are difficult to control and are often the cause of ruptures.

6.  The City's electronic monitoring system (SCADA) would shut off the pipe in the event of a rupture but it is unable to detect slow leaks.  (For example, engineering consultant investigating the fifth breakage of the Richmond - Glen Cairn forcemain sewer said that the pipe leaked for “weeks, possibly months” before it failed completely.)  In the event of a rupture within the on-site facility, all of the effluent would be contained on-site and would not pose a risk to the environment or the public.

7.  Leakage of leachate from a pipeline has the potential to contaminate shallow and deep aquifers.  Some of the many Nepean residents on or near the proposed pipe route depend on wells for their water.  

Environmental Assessment Process:

1.  The City’s consultant recommended a pipeline option because it came out numerically higher than the on-site option (9.34 vs 8.99) but the representation of figures with this accuracy (3 figures of accuracy) is logically and scientifically inappropriate.  Considering the statistical aspect of the public consultation process and the subjective nature of many of the evaluated criteria, the final numerical values are identical.  Both are 9 out of 10!

City staff knows on-site can meet MOE’s Policy 2 requirements as it conducted a $500,000 study several years ago of 7 different on-site options and proved that at least 5 of the 7 would meet MOE requirements.  The Friends of the Jock River is similarly satisfied that the technology of on-site treatment of leachate is mature and that the facility can be operated to a high standard

The Friends of the Jock River asks that you reject the staff recommendation of pipeline and recommend on-site treatment.

Sincerely

Brian Finch
President

Friends of the Jock River



From: Keith Preston, Stonebridge Resident,
Public Member of the Trail Road - PLC

 
 

(To Councillors):

My name is Keith Preston, a resident of Stonebridge in Barrhaven for the past three years.  I am a retired research chemist with some 40 years experience in the science of physical measurements and I am a member of the Public Liaison Committee for the Environmental Assessment that is the basis for the staff recommendation under discussion today.

I wish to focus Committee’s attention on a serious issue that, in my mind, has not been satisfactorily resolved in the current EA process, nor is it addressed in the staff recommendation for pipeline.  Yet the issue to which I refer, namely the VOC plume at the Nepean Landfill site, is sufficiently serious that it stalled the EA/PLC process for four months while City staff made additional measurements and consulted with Ontario MOE over management of this new contamination source and its incorporation within the EA.

Let me first explain what VOCs are:  In this particular instance the Volatile Organic Compounds are chlorinated organics, a notorious class of chemicals that invariably cause environmental and health problems, examples of which are DDT and PCBs.  In this particular case we are dealing with a much simpler compound, a very common degreasing and cleaning agent, trichlorethylene, that is nonetheless a carcinogen, that is, a cancer‑causing substance.  The levels of this poison in the Nepean Landfill groundwater are such that it is suspected that drums full of the material, dumped at the old landfill site years ago, are now rusting through.

Such poisons have no place in a pipeline that is to cross the city, exposing all and sundry to a potential health threat.  MOE inform me that the acceptable limits for VOCs in city sewers have recently become much more stringent, and there is little doubt in my mind that these offensive materials must be contained and extracted on-site.  Indeed, City staff acknowledged that the VOC contaminated groundwater would have to be treated on-site at PLC meeting 3a, and in the subsequent meeting 3b, the consultants CRA indicated, and I quote from item 2.0 of the minutes, “the contaminated groundwater plume can be hydraulically controlled through extraction wells and treated through an on-site system.  M. Benson indicated that City is currently preparing a letter to the MOE that outlines the rationale for this approach and seeks MOE concurrence.”

The Problem Definition section of the present report to this PEC clearly acknowledges compliance of City staff with the MOE directive of July 16 2004 to address the VOC contamination under the current Class EA process.  Yet the pipeline management method recommended in this report fails to address this very serious VOC issue.  Indeed, in a City report of November 9, it is clear that staff do not yet have a solution in place.  I quote from that report: “At the same time the ESR is filed we will also request a 24-30 month extension to our current MOE order (deadline April 30 2005) to have a management solution in place for the contaminated groundwater (VOC) at the Nepean Landfill site.”

Of course pipeline does not solve the VOC problem.  As I have said repeatedly, and I say it again, it does not solve anything, it simply defers the problem, transfers it to another neighbourhood and in so doing incurs additional problems.  If City’s intent, as it would appear to be, is to treat the VOCs on site, as they surely will have to, then the cost of that treatment must be added to the pipeline estimate for fair comparison with the twin on‑site plants.  In distinct contrast, the on-site plant for contaminated groundwater will naturally manage the VOC problem with little incremental cost, a cost that has perhaps already been incorporated into the estimate.

In view of what I have revealed and said, I would urge this committee and all Councillors to adopt the only sensible and environmentally acceptable solution to this problem: reject the staff recommendation for pipeline and vote for the on-site alternative that scored equally in the EA evaluation.

Keith F. Preston, MA, PhD
Ottawa, November 23rd, 2004



From: Bruce Webster, Vice President
 of the Richmond Village Association

 
 

Mr. Chair;
Councillors of the committee:

I am speaking to you today about a subject which has become repetitive but needs to be put under your scrutiny and consideration once again.

It is the matter of how the city staff deal with waste in liquid form.  The city has a good system for dealing with biological wastes, but it is being stressed and utilized to dispose of materials for which it was not designed nor is the ROPEC plant capable of treating these leachate, contaminated groundwater and volatile organic compounds.  In fact, the Ministry of the Environment and the city's own sewage use plan prohibits the transportation of volatile organic compounds by sewage works.  The city is prepared to PAY a fine or Penalty in order to be allowed to break this and other "laws".  Such is the insistent desire of the city engineers to have a pipeline.

I wish to draw to your attention the guest column written by Jeff White for the Ottawa Citizen, on Wednesday, November 10th, and would ask that this article be written into the minutes as printed, in its entirety.  Some points which deserve highlighting are those of  

1)      Cost.   The city and consultants for Trail Road are employing figures which their own experiences contradict.  Pipeline costs are estimated to be $3.8 million PLUS unforeseen/unusual costs (blasting, unstable soils pumping equipment)

2)      The real cost of the Munster/Richmond pipeline is now approaching $17 Million for 11 KM.  Trail Road is approximately 6 KM so the math says a closer "estimate" for the Trail Road project by pipe is $8 Million.  I have a document which mentions an accepted bid for a section of the pipe alone in Richmond to be almost one million for slightly over one KM, constructed in previously disturbed soils, of a known content.  So that in itself should question the 3.8 "estimate" for Trail Road.

3)      The city and CRA, as consulting engineers, KNOW how much a similar processing plant, onsite in London Ontario, cost.  The figure is at $3 Million...less than the "estimate" for pipe.  This London facility has been said to be too small to handle the flow rates at Trail Road, but it is not the flow rates but the volume which dictates size.  The operators control how much is processed at a given time and for either pipe or onsite.  A certain storage capacity is necessary and is already in place by virtue of the site itself.  Therefore, you do not need a facility twice as large for twice the volume and the possibility of size increase is not directly proportionate in cost.  That is to say twice in size does not equal twice the cost.  A side note:  flow rates are typically reduced during winter and the holding capacity is therefore vastly increased while the pipeline would possibly not have enough volume to function, thus causing sludging and a high eminence cost. 

4)      RISK:  The pipeline is considered to be of what risk?  No "risk analysis" was done for this project and so the risk of pipeline is indeterminate.  The risk of onsite is known  - if the facility has a breakdown it stops or is stopped by operator control.  The result?  A back up in volumes retained onsite.  Power interruption back up standby power is part of an onsite package, and unlike ROPEC, maintains full compliance to MoE standards under these conditions. Should a pipeline crack, it is debatable whether SCADA, the alarm system for the city sewers, will respond.  I cite the McManus report of 2003 Richmond...break investigation of Dec. 2001 and June 2002 wherein the conclusions were "that these breaks existed for weeks or months before being detected" (McManus section 5.6 ) by a catastrophic rupture.  A similar rupture occurred on Oct. 26 2004 and was discovered after raw sewage had been flowing into a class 2 river for some time.

In Summary:  The best and only acceptable solution as demanded by public survey, conducted by the EA process for Trail Road PLC is ONSITE.  This head in the sand attitude, by the city and consultants, must be overcome and Ottawa, as the Capital of Canada, should look to take the lead in embracing new innovative technology.  Let us be true "Silicon Valley North" not just an empty phrase.

Thank you for your interest in this project and for permitting me the time to present my views.

Bruce Webster
Vice President
Richmond Village Association

November 2004



Leachate and Contaminated Groundwater Pipeline
Proposed for the Stonebridge Subdivision, South Nepean


Mayor Bob Chiarelli and Council                                                  Monday, November 22, 2004
City of Ottawa
110 Laurier Avenue West
Ottawa, Ontario
K1P 1J1

Fax : 580-2509

Dear Mayor Chiarelli and Members of Council:   

RE:  Leachate and Contaminated Groundwater Pipeline Proposed for the Stonebridge Subdivision, South Nepean 

Planning and Environment Committee has before it, at its meeting tomorrow, a proposal that staff finalize and implement an Environmental Assessment Study that recommends transport by pipeline of the Leachate
and contaminated groundwater from the Trail Road Landfill and Nepean Landfill, respectively, over a distance
of 40 kilometres from the landfill to the Robert O. Pickering facility for treatment. The pipeline route recommended by the consultants involves the construction of a plastic pipe along a line that hugs the west and north boundaries of the Stonebridge subdivision, on the northerly line of which is the Jock River and the neighbourhood of Heart’s Desire. The pipe so proposed is a forcemain, which forces the untreated contents
under pressure along the length of the network until they reach a new gravity sewer (the South Nepean
Collector). Pressurization requires venting, and so it is proposed to release the fumes of untreated leachated sewage over the residential areas, at interval locations. 

   In your review of the consultants’ report and attendant recommendation from staff, we encourage you
to consider the following: 

v           The Environmental Study Report favors pipeline transport of the Leachate and contaminated groundwater by only a small margin over the alternative of treating these substances on-site. Indeed, the margin of difference is so small that it is dismissable by normal statistical standards.

 

v           Argument can be made that, not only do the 2 alternatives of pipeline and on-site treatment stand as equally favored by the Study when corrected for statistical error, but moreover, that on-site treatment is actually the preferred alternative. This argument is supported by adjusting for the unfortunate mistake in the analysis, that being, the mistake of ascribing fully equal effects on health and safety to both the pipeline and the on-site treatment options. (Efforts by the Public Liasion Committee to have the consultants correct this, and other errors, in their analysis have been so far unsuccessful).

v           Volatile Organic Compounds (VOCs), in this specific instance Chlorinated Compounds, examples of which are cancer-producing PCB’s and Drycleaning Solvents, were discovered one year ago in groundwater monitoring wells downgradient of the Nepean Landfill site. VOC’s, by Ministry of Environment regulation, necessitate treatment on-site. While the Ministry has directed that this issue be resolved within the framework on the current Environmental study and have set a date of December 31, 2004 for proposals for resolution, the recommendations you have before you from staff are inexplicably muted on this matter.

v                 Initial reading of the staff report, suggests that the costs of the on-site treatment option are double that of the pipeline alternative. We draw your attention, however, to page 5 of the staff report, and specifically to the section entitled EVALUATION RESULTS. There, you will note, under “Second Place Alternative”, that not one, but two, on-site treatment facilities are specified as necessary. Derivatively, the second facility is for the mandatory treatment on-site of the VOC’s discussed above (described in the staff report as “on-site contaminated groundwater extraction and treatment facility”). This second facility cost is, surely however, constant for both options, i.e. it is unlawful to pipe untreated VOC’s. Costing for the pipeline option has to, therefore, be corrected upwards for this apparent oversight, arguably then neutralizing the cost difference staff have cited between the two options.       

        We submit that the recommendation to approve and implement the current Environmental Study report depends too heavily on data that has been manipulated to support a case for pipeline construction, and invites decisions by Council based on analyses that are neither comprehensive nor transparent for the treatment of
the Volatile Organic Compounds now evident in the contamination produced by the Nepean Landfill.

        As you aware, hundreds of homeowners purchased property in the new subdivision of Stonebridge
without the benefit of disclosure in respect to the planned Leachate pipeline.While the process that produces
the current study no doubt intends to amend that history, it patently fails to meet that test.

Sincerely yours,

Patrice Meloshe and Elmer Tumak
Stonebridge
e-mail: patrice@rogers.com



Subject:

Treatment of Leachate and Contaminated Groundwater from the Trail Road/Nepean Landfill Sites

 
From: "Wendy Duross" <wduross@rogers.com>
Date: Mon, 22 Nov 2004 17:03:02 -0500
 
As a resident of the community of Stonebridge, I wish to express my deep concern over the fact that city staff are going to recommend to City Council that they vote for a pipeline versus on site treatment.
 
I attended the recent Open House and after hearing all the facts and figures on cost versus risk, I fail to understand why Council would not vote for on-site treatment as the safest, most environmentally conscious method.  You can't put a price on public health and safety, or the environment.  One break such as the one that occurred in late October in Richmond would leak toxic waste into the ground surrounding a community of over three hundred homes, putting everyone at risk.
 
I do hope that after hearing once again the concerns of various individuals attending and speaking out at the Planning & Environment Committee meeting tomorrow, that you will think strongly of voting for on-site treatment.
 
Sincerely,
 
Wendy Duross
 (Stonebridge)


 
Subject:

Michael Phelans Comments for the presentation to Planning&Enviromental Committee

From: "michael phelan" <golflinks9@rogers.com>
Date: Tue, 23 Nov 2004 13:30:58 -0500
To: <Lorenzina.Ferrari@ottawa>, "Anne Stubbs" <Anne@neutronics.ca>
 
Ms. Ferrari, thank you for allowing me to email my comments I would have presented to the Committee today. They are as follows.
 
Thank you Mr. Chairman and members of the committee for allowing me to speak.

My name is Michael Phelan.  I am a resident of Stonebridge and the President of the Stonebridge Community Association.

Let me say that I have heard the presentation from city engineers and consultants .
I wish to say I am not an engineer or a chemist or an expert on the treatment of contaminated water.
I did work for 40 years for a major Canadian financial institution and will briefly comment on my views on the mathematics of the presentation in a few moments.

When we moved to Stonebridge 3 years ago, there were about 12 houses, it has grown to over 600 and plans call for the expansion to 2500 in the future. As a matter of interest I am led to believe that the proposed pipeline route on Cambrian drive will be developed by a major Toronto developer within the next year.
The proposed pipeline of 40 KM. to the ROPEC treatment facility where there is no treatment of the inorganic compounds of Lechate it is merely treated and poured into the Ottawa river.

The experts tell us disposing of Lechate via pipeline is safe,but there have been many instances over the years where experts have told us something was safe only to find out in later years that it poses a serious health risk.
Ruptures do happen, as on the very day of the final public meeting Oct.26th. a major pipeline break occurred in Richmond. Over the last decade there have been thousand of pipeline ruptures in Ontario many as a result of human error.

The weightings and cost comparisons of onsite vs. pipeline are almost equal but in my forty years as a banker it was not unusual to see marketing plans/budgets presented by those supporting a project to look very favorable leaning to the preferred choice by the presenter. Then when the actual costs were tabulated there were significant cost overruns.

When Councillor Hume mentioned this morning that the preferred choice was heavily made on the basis of the lowest cost, I couldn't help remember when Astronaut John Glen returned from one of his missions in space a reporter asked him what he was thinking when he was inside the spaceship. He replied that when he was looking at all the instruments in the spaceship cabin he thought "Oh my God all these parts were bought from the lowest bidder."

Mr. Chairman, Ladies and Gentlemen,
 we would be most grateful if you would vote in favor of onsite treatment.
Thank you
Michael Phelan
(Stonebridge)  
   

 
Subject:

FW: TRAIL ROAD LEACHATE PIPELINE PETITION

 
 
-----Original Message-----
From: IMRAN MIRZA [mailto:imirza2480@rogers.com]
Sent: November 17, 2004 12:45 AM
To: bob.chiarelli@ottawa.ca
Cc: Wendy Duross; oped@ott.sunpub.com; letters@thecitizen.canwest.com
Subject: TRAIL ROAD LEACHATE PIPELINE PETITION
Dear Mayor Chiarelli:
 

On Tuesday, November 23rd Ottawa's Planning and Environment Committee will decide whether to support a pipeline or on-site treatment to manage Trail Road's leachate and Nepean Landfill's contaminated groundwater. After six long years, city staff are still recommending a pipeline as the solution. 

Because I believe that a pipeline could have significant negative effects on our health, safety, social well-being, property values and the environment,

I SUPPORT ON SITE TREATMENT AT TRAIL ROAD AND NEPEAN LANDFILL WITH DISCHARGE AFTER ON SITE TREATMENT INTO THE JOCK RIVER

Yes: X
No: 

Name:Imran & Shahana Mirza
 Nepean


Mayor Chiarelli, we are very upset at the city staff decision to make this recommendation without any consideration of what the residents of this community wish, and without any safety consideration for this rapidly growing community.   As we registered our concerns about the safety of the pipeline at the Public Open House on October 26th, it would appear that City officials were aware of yet another serious break in the Richmond forcemain.  Please see the attached photo below for your information.

The community that suffered as a result of carelessness on part of officials in Walkerton Ontario is a case in point that is a tragic lesson learned, and therefore we cannot take safety lightly.  There has been numerous incidents involving bursting of pipelines, and your staff proposed leachate pipeline is no exception.  Frankly I am completely at a loss as to why our elected and hired city staff members would put our families - men, women and children at risk by running this contaminant carrying pipeline through a populated area in Stonebridge.  When this same event was proposed to happen several years ago in the Barrhaven area, the community managed to stop the pipeline.  I wonder if it  had anything to do with the fact that it was going through very closely by a prominent lawyer's house, or was it that there were more voters in the area than there are in Stonebridge? If the city backed off on that decision, why are we now being subjected to this same shameful act of putting our children and community at risk ?  

Please don't tell us or allow your staff to tell you  that you have done all the studies and this is completely safe - this is the same type of argument that we used to get in the old days when tobacco companies denied smoking had any connection to causing cancer in people.  With every project involving life and death, risks have to be evaluated, the probability of that risk occurring has to be determined and the IMPACT has to be assessed.  Even if the staff tell you that for some reason the risk is low that the Pipeline will not break and contaminate our drinking water, etc, please consider the fact that should this so called "low" risk event occur, the impact is irreversible - when community members, adults and children alike die, neighborhoods are contaminated, and our biggest investments in our personal life our legacy in our children and community is destroyed because some bureaucrat(s) decided that this was a cheaper solution.  God Forbid, but should something bad happen in this community like it did in Walkerton, which city official will be blamed for the tragedy? What good will it do after the fact? Was the tragedy in Walkerton not enough?  Where does your responsibility end?  What excuses will the staff come up with then?  And frankly, I don't want that situation to occur, and therefore, I am urging you take direct action in preventing this from happening. 

All of our Stonebridge petitions are being sent to Ms. Jan Harder's office for consolidation, and I thought it was important that you were absolutely aware of the desperate situation in our community, and our expectation that at least our Mayor will intervene on our behalf to put things right.  We hope you can help.

We remain yours truly,

Imran & Shahana Mirza
Stonebridge residents who will be directly impacted by this pipeline.

CC: To Editors of Ottawa Citizen and Ottawa Sun.

[Photo at left shows a section of Richmond's sewage pressure-forcemain which had massively ruptured on the afternoon of the very same day (October 26, 2004) that city officials told an evening Open House gathering of Stonebridge and Barrhaven residents that they were not aware of any forcemain breaks in the city, that had occurred spontaneously without construction equipment intervention being the sole causative factor ...a huge lie.

Not only was this the SIXTH spontaneous rupture, just on the Richmond forcemain alone, but the longitudinal split suggested that, (as in the previous such incident), there may have been gradually increasing leakage into the groundwater for a period of weeks to months before the massive rupture caused the SCADA alarms to go off.  -OSF]

 


 

RE: Treatment of the leachate and contaminated groundwater from the Trail Road/Nepean landfill site.


Ladies and Gentlemen:

This is to recommend to you, in the strongest terms possible, that you collectively vote in favour of the ON-SITE TREATMENT of leachate and contaminated ground water from the Trail Road/Nepean landfill site at your council meeting on November 24.  Prior to this vote, I am sure that you will have thoroughly briefed yourselves on the issues surrounding this decision and will vote accordingly.  Having studied, as you have, the pros and cons associated with the alternatives, they need not be repeated here.  My specific request to you is that you respond to the wishes of your constituents.  Those who have taken the initiative to study the matter and have had the opportunity to express their opinion, are overwhelmingly in favour of the on-site treatment solution.  All things in balance, to vote otherwise would be inexplicably going against the considered opinions and wishes of voters and taxpayers.

Kind regards,
 
Lewis Cardin
Nepean, Ontario


PowerPoint presentation prepared by the public members of the Public Liaison Committee (PLC), showing the valid reasons for their support of the on-site solution:  CLICK HERE



Please check back soon, as more documents are added...

 

___________________________________________________________________________

HOME | CLOSE PAGE | SITE MAP
 

OttawaSewergateFiasco.com