| |
CORRESPONDENCE HISTORY
Introduction
In its workplan for the year 2001 the
Friends of the Jock River (FJR) included an item to pursue membership on the
Richmond Conservation Area Management Committee (RCAMC). At that time, we
had already organized a Bioblitz Day at the Richmond Conservation Area
(RCA), in August of 2000, which had contributed a great deal to the existing
knowledge of the flora and fauna of the area. In addition, we had undertaken
a significant tree planting project for the RCA during the preceding spring
and planned to continue with another such project in the spring of 2001.
Moreover, we had acquired a great amount of expertise on the RCA with our
new secretary, Eric Snyder, who was instrumental in founding the RCA,
writing the RCA Management Plan (RCAMP) and lobbying for its implementation.
Because of this experience with the area, we were convinced that we alone
occupied a position from which to effectively protect the RCA, which has
been under attack since 1998. Furthermore, given that the RCA is a large
natural area, situated within the boundaries of the Village of Richmond, to
be managed primarily for birding and other kinds of nature appreciation, we
believed that it could benefit the Jock River Watershed in at least two
ways. First, through its protection, a large area of the Jock River flood
plain, and riparian habitat along the Jock River and Marlborough Creek,
could be preserved in a natural condition. Second, if properly managed, the
RCA could become an important means of promoting the natural values of the
entire Jock River Watershed. Hence, we decided to ask to have a
representative appointed to the RCAMC. At this time, although the City of
Ottawa has agreed to allow us a position on the RCAMC, we have not yet had a
representative appointed. Nevertheless we have taken the lead in protecting
this important area.
Official Opening and Management Plan
The RCA used to be the most visited
birding destination within the Region of Ottawa-Carleton. This was largely
because the Richmond Lagoons provided productive mudflat habitat for many
uncommon species of migrating shorebirds. However, it was also because of
the many old field species which breed on the abandoned pastures and hay
fields surrounding the Lagoons, the riparian species found around the Jock
River and Marlborough Creek, and also the marsh and pond species within the
Lagoons. Although shorebird use has diminished over the last eight years,
most of the other species can still be found in the area. Consequently, the
RCA remains Richmond's most significant resource for birding, naturalization
projects and environmental education. The list of bird species for the area
continues to grow, and so far almost 200 different species of birds have
been reported at the RCA.
The RCA was officially opened in June
1993 as part of Richmond’s 175th anniversary. Goulbourn councillors, area
birders, naturalists, environmentalists, staff of the Wild Bird Care Centre,
birding columnist, Elizabeth LeGeyt, and Goulbourn’s Environmental Advisory
Committee (GEAC) were all in attendance. The land was blessed by Mi’ kmaq
elder, Noel Knockwood, and Anglican Church Primate, Archbishop Michael
Peers. Since its opening, the RCA has been recognized in the Federation of
Ontario Naturalists' A Nature Guide to Ontario and Guide to
Municipal Environmental Advisory Committees. It has also been recognized
in Clive E. Goodwin's A Bird-Finding Guide to Ontario.
In August 1995 the first draft of the
RCAMP was completed by the RCA Subcommittee of GEAC, chaired by Eric Snyder.
The plan was distributed to Goulbourn's council and potential partners
including the Regional Municipality of Ottawa-Carleton (RMOC), the Rideau
Valley Conservation Authority, Ducks Unlimited Canada, the Ottawa Field
Naturalists’ Club and the Rideau Trail Association. The goals of the RCAMP
are to re-establish the RCA as an exceptional birding destination within
Ottawa-Carleton, to preserve the natural values of the RCA lands, to
undertake projects which will improve and diversify wildlife habitats, to
provide an opportunity for environmental education programs, and to provide
passive recreational opportunities for Richmond and surrounding areas. On 19
August 1997, after review by all potential partners, the final draft of the
RCAMP was adopted by Goulbourn's council. The resolution to adopt the plan
stated that the council would establish "good conservation practices for the
development and management of [the RCA] as a wildlife habitat with outdoor
passive recreation and educational uses which promote the appreciation of
that habitat, but in no way adversely affects that habitat".
Conservation or Sewage Storage?
However, unknown to GEAC, although it
had adopted this resolution, Goulbourn’s council had other plans for the
RCA. At GEAC’s 5 August 1997 meeting, Councillor Steven Lewis had asked if
the RCAMP would allow the use of the Lagoons during emergency hundred year
floods. He was told that this would not be a problem. At the 19 August
council meeting at which the RCAMP was adopted, the question was again
raised: Could the Lagoons still be used for the storage of sewage in an
emergency? Council was told that nothing in the plan absolutely precludes
it. Nothing further was said on the matter. GEAC was not told that
the Richmond Lagoons had already been identified as an inexpensive way to
solve continued problems with the Richmond sanitary sewer. On a number of
occasions significant wet weather conditions had led to infiltration of
surface and groundwater into the Richmond sewer system, which had exceeded
the capacity of the Richmond pumping station. It was known that since 1993,
when detailed data collection at the pumping station began, there had been
three sewage bypasses to the Jock River. The last had occurred on 7 April
1997, only five months before the RCAMP was adopted. Although there was not
sufficient data to provide a statistically significant estimate, this
suggested that the Lagoons might have to be used not every hundred years,
but every two or three years. Moreover, RMOC also wanted to use them to deal
with breaks in the forcemain and maintenance, which would further increase
the frequency of use. With the support of Goulbourn’s mayor, RMOC began a
Class Environmental Assessment (EA) in January 1998 to justify these uses of
the Lagoons. The product of this assessment was to be the Richmond Pumping
Station Forcemain Study (RPSFS). The request for proposals was sent out on 3
December 1997. Connelly McManus Engineering (CME) was hired, and began
drafting the RPSFS in January 1998.
Although it had been working for
Goulbourn on the RCAMP for over four years, GEAC only learned of the RPSFS
in March 1998 from the local papers. Inclusion of GEAC within the Class EA
process did not greatly improve as the study progressed. The first draft of
the RPSFS was received by the Goulbourn Clerk’s Office on 8 June with a
covering letter from RMOC inviting comments on the draft for a meeting on 17
June. GEAC was neither informed that the draft was available nor told of the
meeting. The minutes of the meeting later revealed that crucial questions
concerning impacts on the RCA had not been pursued by Goulbourn staff. It
was only on 9 July that GEAC received notice that the study was available.
By late August members managed to procure a copy from the Goulbourn Clerk’s
Office. GEAC began its own analysis of impacts on the RCA. At the same time
it sent a letter to the mayor of Goulbourn Township, Janet Stavinga,
detailing its exclusion from the process and asking for more transparency.
The letter was ignored. However, GEAC completed its analysis and sent it to
CME on 3 February 1999. Its primary concerns were with RMOC’s reluctance to
regulate water within the Lagoons as required to maintain wetland habitats,
restrictions on habitat enhancement possibilities within the Lagoons,
restrictions on public access to the Lagoons for wildlife viewing,
restrictions on access by RCA managers for habitat maintenance, obtrusive
signs and floatables (e.g. contraceptives and sanitary products), which
would remain in the Lagoons after a bypass of sewage. Having finally heard
from GEAC, RMOC staff seemed for the first time to realize that there might
be some problems with what was being proposed in the RPSFS.
On 30 March 1999, a meeting occurred
between Goulbourn, the RMOC and the Ministry of Environment (MOE).
Goulbourn’s solicitor put forward a proposal. It had apparently been
determined that only one of the three Richmond Lagoon cells could be used
for sewage storage, Cell C. The soils underlying the other two cells, A and
B, were deemed to be too permeable for their use as sewage lagoons. The
solicitor suggested that arrangements be made for Cell C to be jointly used
by both the RMOC and Goulbourn. The RMOC would own the berms and basin of
the cell, and any infrastructure associated with its use as a sewage works,
but Goulbourn would own the land on which the cell was located. Therefore a
joint use agreement (JUA) would have to be worked out to determine what
rights and responsibilities both parties would have, given that the RMOC
would be able to operate its sewage works on Goulbourn’s land.
Council Resolutions and the Joint Use Agreement
The JUA now became the main focus of
GEAC’s efforts. On 14 April RMOC staff submitted a preliminary set of
conditions for an agreement. Acceptance of the conditions would mean the end
of the RCA. GEAC submitted a revised set of conditions just prior to a 7 May
meeting between the RMOC and Goulbourn. However, for the subsequent three or
four months, further revisions were to take place under the Municipal Class
EA process.
By the end of May, the RMOC had
completed the final draft of the RPSFS. A Regional staff report on the study
had been written for the RMOC’s Planning and Environment Committee, and it
included conditions under which GEAC was purported to find the preferred
alternative of the study acceptable. These conditions had to be brought
before Goulbourn Council to be accepted or rejected. Thus Goulbourn’s clerk
had to write a report on the RPSFS and make a recommendation as to whether
the conditions were adequate. The report went before Council on 1 June. The
wording of the recommendations was vague, not dealing with the specific
details necessary to ensure that RCAMP objectives could be satisfied. It
contained a number of glaring omissions and inexplicably framed the
conditions as requests for RMOC to consider. GEAC had to send
a letter to Goulbourn Council the day before the report came forward
requesting that the omissions be dealt with and wording strengthened. Under
pressure from GEAC at the meeting, the mayor agreed to add only one further
condition. The RMOC’s activities had led to Ducks Unlimited Canada backing
out of the project, and Ducks Unlimited had previously agreed to manage
water for the RCA. Hence Goulbourn Council agreed that it would only accept
the recommendations of the RPSFS if the RMOC would agree to manage water for
the RCA.
Thus, somewhat strengthened, although
still rather vague conditions went to the Planning and Environment Committee
on 8 June. At this time, however, RMOC staff suggested further revisions
that again weakened the conditions. The committee accepted these revisions.
However, through lobbying RMOC councillors, GEAC had the final decision on
the conditions deferred. The conditions went back to the Planning and
Environment Committee on 13 July, but this time, the committee was persuaded
to accept revisions supporting the RCA. Most of the revisions went through.
However, although this provided some
assurance that the RCA was not to become no more than a sewage works, the
future of the area was still in question. The adopted conditions were still
rather vague. Whether there was really a possibility for shared use of the
RCA would be decided in the process of drafting the JUA. There the details
would have to be worked out. Hence, the next step was to finalize the JUA.
Throughout GEAC’s lobbying of RMOC, Eric Snyder had been continually
updating and revising the conditions that GEAC had proposed for the JUA in
May. So he had wording for the JUA ready in July. On 11 August a meeting
occurred between Mayor Stavinga, Goulbourn’s clerk and various GEAC members.
At this meeting it was agreed that Goulbourn’s clerk would take Eric’s
wording and put it in the form of an agreement.
Municipal Restructuring and Amalgamation
However, nothing was done for months.
Municipal restructuring was announced. The outcome could leave Goulbourn in
a weakened negotiating position, for if Goulbourn was to be amalgamated by
the year 2001, the RMOC would have no incentive to draft an agreement. GEAC
repeatedly asked staff to get on with it. Its concerns were dismissed. On 26
October, GEAC made a presentation to Goulbourn Council, updating it on GEAC
projects and activities. It again explained the importance of completing the
JUA before the decision on restructuring. Still it was not until late
December that GEAC received a draft from the clerk. The decision on
municipal restructuring had been made and Goulbourn had lost any negotiating
advantages that it had.
The draft was disappointing to say the
least. Eric’s wording had not been used. Indeed even the conditions adopted
respectively by the Goulbourn and RMOC councils under the Class EA process
were not reflected in the agreement. GEAC voiced its frustration to
Goulbourn Council. The mayor’s first response was denial. However, after
passages of the draft were read to her, she had to change her strategy. She
agreed to a meeting on the problem but refused to agree on a date for it.
She held off the meeting for about three months. Eric used this time to
complete his own draft JUA and have it adopted by GEAC. Then through
discussion with RMOC’s legal staff he learned that Goulbourn’s clerk had
approached RMOC to have it complete the agreement. Apparently this was
preferable to having further attention focussed on his own efforts. GEAC
members were outraged. Eric informed RMOC’s lawyer that GEAC had already
drafted an agreement. She contacted Goulbourn. It was 14 February 2000. GEAC
was to make a presentation to Goulbourn Council the following day, and it
would be an embarrassment for the mayor to have this brought out in public.
So she changed her strategy again. She was unusually accommodating. She set
a date to meet on the agreement. Goulbourn’s lawyer would be there together
with all necessary staff and councillors.
The meeting took place on 23 February
2000. The mayor made a number of commitments to ensure that the future of
the RCA would be assured in the new City of Ottawa. To begin, GEAC’s draft
JUA was accepted. It would be sent to RMOC before the end of February. Even
if signed by both parties, it would not be binding on the new City of Ottawa
after the year 2000, but it would provide a historical record of the intent
of the two preceding governments. It would show that both intended to
support the use of the RCA lands in accordance with the objectives of the
RCAMP. Mayor Stavinga promised to ensure that an agreement was signed before
the transition. She also promised to bring the RCA to the attention of the
transition board. Moreover, she said that she would try to determine if RVCA
could be made a party to the JUA, so it would retain validity after the
transition. She did none of this. Moreover, having been compromised by
Eric’s communications with the RMOC’s legal staff, she insisted that GEAC
members have no further contact with that staff. When Eric continued to
contact the RMOC’s operations staff, who were responsible for implementing
the RPSFS, she had him removed from GEAC.
RMOC only responded to GEAC’s draft on
7 July 2000. Rather than provide comments, it produced a completely
different draft. The two drafts were radically divergent as to which would
be the primary use of the land, conservation or sewage storage. Indeed,
RMOC’s draft was clearly written with the intention of removing Cell C from
the conservation area, and allowing for the same to occur with the other
cells in the future. Furthermore, the draft revealed that the RMOC was
unwilling to manage water levels either in Cell C, or the other two cells,
as was required to establish a mudflats for migrating shorebirds. Moreover,
RMOC staff did not want to allow RCA managers to be able to access Cell C,
and seemed unwilling to restrict public access to the cell in a way that
would be compatible with the objectives of the RCAMP. On 26 October,
Goulbourn’s clerk met with RMOC staff to discuss these matters. RMOC staff
elaborated on some of the points in their draft. It was agreed that
Goulbourn’s clerk would send them a number of recommendations within the
week. Negotiations were to get underway in the last two months before
restucturing. However, the clerk never sent any recommendations.
Consequently, no progress was made and no JUA was signed.
The only exception to this
shortsightedness on the part of Goulbourn Council was its appointment of the
RCAMC prior to restructuring, in August 2000. Since, unlike the RCA
Subcommittee of GEAC, the RCAMC included members independent of Goulbourn
Township, it would not entirely disappear along with GEAC after municipal
restructuring. Unfortunately, our secretary, Eric Snyder, was not appointed
to the RCAMC. Consequently, during the following eighteen months, the most
effective advocacy for the protection of the RCA would come through the
Friends of the Jock River.
Request for Membership on the RCAMC
After municipal restructuring, we
decided that we could deal most effectively with outstanding problems
regarding sewage storage at the RCA if recognized as a member of the RCAMC,
which would have a mandate to manage the RCA for the City of Ottawa. Thus
when a proposal to extend the term of the existing members of the RCAMC came
forward in March 2001, we sent a letter to the City’s Corporate Services and
Economic Development Committee, and subsequently to Council, requesting that
the City appoint a representative of the Friends of the Jock River on the
RCAMC. Our letter received no response from City Council. Unfortunately, our
interest in membership did not receive any acknowledgement from the RCAMC
either, at least not until after the appointments of its members were
extended. We realized that we would have to lobby more persistently for a
position on the RCAMC. Fortunately, the Richmond Village Association was
also becoming concerned with the lack of progress implementing the RCAMP.
This organization proved to be a strong source of support for our later
lobbying efforts.
During the spring of 2001, as we were
planning another tree planting project on RCA land, we received a letter
from the RCAMC informing us that our membership on it was desired. However,
no definite time lines were provided in which that objective was to be
achieved. We began making inquiries with City of Ottawa staff. The initial
results of those inquiries were not encouraging. Staff would be writing
revised terms of reference for the RCAMC. Then the RCAMC would be revising
the RCAMP. Both the terms of reference and revised plan would then have to
be approved by City Council. Once Council did so, the City would then
proceed with recruitment for the public positions on the RCAMC, and only
then would we be asked to submit a nominee as our representative on the
RCAMC. When a Selection Panel had made a recommendation on the public
membership, and various organizations had provided the names of their
nominees, a report would go forward to Committee and Council recommending
membership. Once approved by Council, the new RCAMC would then replace the
former committee.
We had two main objections to this
approach. First, we projected that if we could not have a representative
appointed until the existing RCAMC completed revisions to the management
plan, we would be waiting a long time. We could see no reason for the delay.
Second, given the experience we had with the RCA, we believed that we could
make a significant contribution in revising the RCAMP. Hence we wrote to
city staff as follows:
The Friends of the Jock River respectfully submits the
following comments . . . dealing with membership on the Richmond
Conservation Area Management Committee.
The Friends of the Jock River would strongly prefer to
have . . . [the terms of reference] approved by council prior to further
work on the management plan. We have recently been given an opportunity to
submit comments on proposed revisions to the plan. However, we would like to
be allowed full participation in discussions of the management plan
subcommittee of the RCAMC, and the opportunity to participate directly in
drafting the revisions. Furthermore, we want to be able to vote on proposed
revisions if necessary. Hence, [we ask] . . .
[1. T]o what City of Ottawa policies can you refer to
justify proceeding in the manner indicated above?
[2]. Do any of these policies provide a definitive
reason why membership cannot be dealt with prior to revising the plan?
[3]. If you answer [2] in the negative, at whose
discretion is it decided whether or not membership will be dealt with in
this way?
The response that we received from the city was not
altogether convincing, resulting in another letter and more questions from
us. City staff answered the above questions as follows:
Council has tasked the existing team with the mandate
to revise the plan and membership and come back . . . . In addition, Council
has already passed a motion approving that the existing membership of the
team stay in place until such time as additional review is conducted. The
additional review entails the membership and management plan.
We responded:
We have been unable to find any passage in the Report
on External Boards, Commissions and Authorities that specifies that the task
of the current membership of the RCAMC is to revise both the plan and
membership, and only then report back to city council. The report does
indeed recommend the extension of the former Goulbourn council appointments
to the RCAMC to allow it to continue acting to fulfill its mandate of
managing the RCA until such time as additional review can be conducted. But
we can find nothing in the report, or the motion passed by City of Ottawa
council, which suggests that this additional review entails that both
membership and management plan must be dealt with together. If there is
something that we have overlooked, we apologize for our lack of perspicacity
and invite you to point it out to us.
Following this letter, City staff agreed to write the
terms of reference and begin the process of establishing the new RCAMC
without further delay. Once we had this agreed to, the terms of reference
were soon drafted by staff.
We made a significant contribution to revising the
draft, particularly with respect to the mandate and responsibilities of the
RCAMC. Some of our contribution is excerpted from a letter to the City of
Ottawa in the following:
Mandate
The draft states: "The mandate of the Richmond
Conservation Area Management Committee is to manage the area with a goal of
preserving and enhancing a variety of wildlife habitats in order to
encourage biodiversity. It will, in addition, offer passive recreational and
educational opportunities, in accord with the conservation objectives of the
Richmond Conservation Area for the City of Ottawa, residents and visitors to
the area."
Although wording very similar to the preceding is used
in the 1997 RCA Management Plan, we find it somewhat inadequate in the
present context. (i) First, since the Terms of Reference of the RCAMC are no
longer included in the RCA Management Plan, the former should state that the
committee has a mandate to develop policy for the conservation area as will
be presented in the latter. (ii) Second, since the above referenced "goal of
preserving and enhancing a variety of wildlife habitats in order to
encourage biodiversity" is no longer elaborated upon by means of a detailed
site management plan, as it is in the 1997 RCA Management Plan, we believe
that the goal should be restated more precisely here. (iii) Moreover, given
the relatively recent changes in the status of Cell C with respect to its
use as a sewage works, we believe it desirable to refer to this in the
mandate. Accordingly, we recommend something like the following:
"The mandate of the Richmond Conservation Area
Management Committee is:
(1) To develop (a) the management policy for the
Richmond Conservation Area, and (b) an implementation strategy for that
policy, both of which are to be included in the Richmond Conservation Area
Management Plan;
(2) To manage the Richmond Conservation Area for (a)
the preservation and enhancement of those types of biotic communities, or
habitats, currently established within its boundaries, (b) the
re-establishment of habitat types which historically supported biota valued
by birders and naturalists, and (c) the establishment of additional habitat
types which will increase desirable biotic diversity;
(3) To manage the conservation area for the purpose of
providing passive recreational and educational opportunities, which are
compatible with the above stated habitat management objectives (1)-(2);
(4) To advise the Council of the City of Ottawa on
implementation of the preferred alternative identified in the 1999 Richmond
Pumping Station and Forcemain Study so as to ensure that the use of Richmond
Lagoon Cell C as a sewage works will not prevent the management of the
Richmond Conservation Area, including Cell C, for the above stated purposes
(1)-(3)."
Responsibilities
The draft states: "The Richmond Conservation Area
Management Committee shall be responsible for:
Preserving the natural values of the Richmond
Conservation Area through active or passive management;
Providing opportunities for environmental education
programs, field interpretation, on site demonstration projects and
volunteers involvement;
Providing a range of passive recreation opportunities
in the area;
Undertaking projects in the Richmond Conservation Area
to improve and diversify the wildlife habitats and encourage an appropriate
bio-diversity;
Providing a "prime" birding area where diverse species
of birds are accessible to the interested public; and
Providing on going management of the Richmond
Conservation Area such that it is of environmental, social and economic
value to the community."
The above list of responsibilities is taken from
Section 1.5 of the 1997 RCA Management Plan; however, the ordering of the
responsibilities has been changed, as has some of the wording. We propose
that the responsibilities be listed, where possible, in order of importance.
We also propose the inclusion of additional responsibilities and suggest
some of our own changes to the wording. We recommend:
"The Richmond Conservation Area Management Committee
shall be responsible for:
1. Revising the Richmond Conservation Area Management
Plan, as is required in the pursuit of its mandate;
2. Preserving the natural environmental values of the
Richmond Conservation Area, including the Jock River and Marlborough Creek,
through both active and passive management;
3. Re-establishing the Richmond Lagoons as an
exceptional birding area in the City of Ottawa, as is to be reflected in the
use of the area by the birding public;
4. Undertaking projects to improve and diversify the
representation of appropriate eastern Ontario biotic communities within the
Richmond Conservation Area;
5. Providing opportunities for environmental education
programs, field interpretation, on site demonstration projects and volunteer
involvement;
6. Providing opportunities for unsupervised, passive
recreation;
7. Advising City Council on the operation of Cell C to
mitigate the impacts of its use as a sewage works on the preceding;
8. Providing continued management of the Richmond
Conservation Area such that it is of environmental, social and economic
value to the community."
Many of these revisions were used in the final terms
of reference for the RCAMC.
A Conservation Area made Sewage Works
During the time that we were involved
in lobbying for membership on the RCAMC, and working on its terms of
reference, the city’s operations staff were occupied with implementing the
RPSFS. In the course of negotiations over the RPSFS and JUA, RMOC operations
staff had made commitments to consult with the RCAMC during implemetation of
the study recommendations. However, these commitments were not taken very
seriously by the operations staff in the new City of Ottawa. City staff
attended one meeting of the RCAMC on 15 May 2001. Rather than offer to
include the RCAMC in the implementation process for the RPSFS, and solicit
advice on mitigating impacts on the RCA, they proposed that the
implementation be phased. Staff argued that, contrary to what had been
observed for years at the RCA, two of the lagoon cells, Cells A and B, could
not hold water. Thus it was proposed that these cells be tested for
permeability before any mitigation work be undertaken. Hence, first the work
for the sewage facilities would be done, then, once permeability testing was
complete, that for mitigation on the RCA might be undertaken. Unfortunately,
Janet Stavinga, now City of Ottawa Council representative on the RCAMC, and
the RCAMC chair, accepted the phasing proposal.
What resulted from this was a
disaster. Having permission to proceed with constructing a sewage works in
the conservation area, and unconstrained by any kind of joint use agreement,
staff showed no respect for the area. The RCAMC seemed to be unaware of what
was happening. However, the FJR documented the abuses of the RCA and made
complaints to the RCAMC, the City of Ottawa and the MOE. The RCAMC reacted
with questions of its own for city staff, but even having received
inadequate answers, the chair and council representative then became
resistant to pursuing the matter further. Indeed, when Eric Snyder reported
at the 4 December 2001 meeting of the RCAMC that Ottawa staff had caused a
sewage spill at the RCA, the chair responded, "This isn’t on the agenda".
However, MOE has initiated an investigation into the situation, which is
ongoing. We are still awaiting the results. The following two letters
explain the basis of our complaints and the abuses that have occurred.
Letter 1
November 16, 2001
Mr. Stephen Forestell,
Project Manager,
Richmond Pumping Station Upgrade,
City of Ottawa,
110 Laurier Ave. West,
Ottawa, ON
K2P 2L7
Mr. Forestell,
Re: The Richmond Conservation Area, the Richmond Pumping
Station and Forcemain Study and Amendment to Certificate of Approval Number
3-0834-83-006
We have a number of concerns regarding (i) the above
referenced certificate of approval, as amended on 24 August 2001, and (ii)
the ongoing work for which approval was given, the final plans and
specifications for which were submitted in support of the application for
the amendment. We are concerned that neither the amended certificate of
approval nor the final plans and specifications, prepared by David McManus
Engineering Ltd., take into account certain commitments, which were made to
mitigate impacts on the Richmond Conservation Area (RCA) resulting from the
use of Cell C of the Richmond Lagoons as a sewage works. Our concerns are as
follows:
1. Status of Cells A and B
The amendment to Certificate of Approval number
3-0834-83-006 should reflect the fact that Cells A and B of the Richmond
Lagoons will no longer be maintained or used as part of the Richmond pumping
station and forcemain facilities. The May 1999 Richmond Pumping Station
Forcemain Study (RPSFS) states:
The geotechnical investigation report, attached as
Appendix ‘J’, concluded that Cells A and B should not be utilized as
temporary storage facilities for sewage from the pumping station because the
underlying soils are too permeable. However, Cell C could be used as an
emergency lagoon for temporary storage of sewage. (RPSFS, p. 9, §3.13; cf p.
ii, §3.3; p. 33, §9.0)
Similarly, the June 1999 Richmond Pumping Station
Forcemain Study Environmental Screening Report (ESR), prepared by the
Regional Municipality of Ottawa-Carleton Engineering Services Branch,
states, "It was found that, under existing conditions, only one of three
lagoon cells (Cell C) has the integrity to hold sewage . . ." (ESR, p. 10,
§4.3). Accordingly the recommendations of the RPSFS include the following
statement:
Cells A and B, in their current conditions, are not
recommended as temporary storage facilities and, therefore, the existing 200
mm diameter forcemain, which terminates at Cell A, should be extended to
Cell C, for the bypass of sewage from the pumping station to Cell C of the
lagoons. (RPSFS p. 33, §9.0; cf. p. iii, §7.1; p. 33, rec. ii; p.34, rec.
xi)
And the recommendations of the ESR include the statement:
The existing 200 mm forcemain linking the pumping station
to Cell A should be extended to Cell B and C to permit the discharge of
sewage into Cell C and water into Cells B and C. (ESR p. 15, §6, rec. 1)
However, the amended Certificate of Approval number
3-0834-83-006 does not reflect the above. On the contrary, Condition No. 2
of the certificate, which states, "Where there is a conflict between a
provision of any submitted document referred to in this Certificate and the
Conditions of this Certificate, the Conditions in this Certificate shall
take precedence," implies that Cells A and B will continue to be regarded as
part of Richmond’s sewage facilities. This contradicts assurances given to
stakeholders, during the drafting of the RPSFS, that only Cell C would be
considered a sewage works if the recommendations of the study were to be
adopted.
We therefore conclude that, if Condition No. 2 is to
remain a part of Certificate of Approval number 3-0834-83-006, the
certificate should be amended to state that only Cell C is to be maintained
and used as part of the Richmond pumping station and forcemain facilities.
Do you agree, and if so, will you undertake to have the necessary amendment
made?
2. The 200 mm Diameter Forcemain Connection to Cell A
We would like assurances that the remaining 200 mm
diameter forcemain connection to Cell A has been tested and found to be
operational. The RPSFS states:
The chamber, between Cells A and B, operated as a
distribution control box and would have been designed to distribute flow to
either Cell A or Cell B. . . . Upstream of this control box, the piping
system was arranged so that with the use of gate valves, the flow could be
directed to Cell A, bypassing the control box. (RPSFS p. 10, §3.2.1)
The final plans and specifications, prepared by David
McManus Engineering Ltd., indicate that the manhole and appurtenances, which
were used for the regulation of flows through the downstream connection to
Cell A, are to be removed, and have been removed if the plans have been
followed. This leaves only the upstream connection. According to the RPSFS,
in 1999, "[t]he existing 200 mm diameter forcemain from the pumping station
to the lagoons was tested and found to be operational" (RPSFS p. 19, §6.3).
Is it the case that both connections to Cell A were tested and found to be
operational during the study?
3. The 200 mm Diameter Forcemain Connection to Cell B
The minutes of the 15 May 2001 Richmond Conservation Area
Management Committee (RCAMC) meeting indicate that you were in attendance to
explain how the implementation of the RPSFS was to be phased. According to
the minutes, Phase 1 is supposed to involve "most of the works needed to
deal with sewage" while Phase 2 is to "deal with the conservation needs"
that must be satisfied to implement the RCA Management Plan. The minutes
indicate that both the RCAMC chair and the City of Ottawa Council member on
the RCAMC supported this approach to phasing the project. Given the
conclusions of the geotechnical investigation report for the RPSFS, why has
the 200 mm diameter forcemain extension to Cell B been completed during
Phase 1? Does the staff of the City of Ottawa Operating Division have any
intention of using Cell B for storage of sewage at any time?
4. Mitigation of Impacts on Cell B
Resolution No. 99-110, passed by Goulbourn Council on 1
June 1999, concerns the conditions under which the council was willing to
accept the "proposed solution" of the RPSFS. The resolution states:
Be it resolved that the Council of the Corporation of the
Township of Goulbourn hereby supports the use of Cell C of the Richmond
Conservation Area (RCA) for sewage purposes, subject to a Joint-Use
Agreement, satisfactory to the Council of the Township of Goulbourn, which
shall minimize negative impacts on the RCA and shall not dramatically
interfere with the operation of the area for its originally intended purpose
as a conservation area.
Amongst the conditions listed in the resolution as
necessary for a joint use agreement is the following: "The design and
placement of additional works will be conducted in cooperation with the
Township so as to mitigate any damage and disruption caused by the
construction".
The 13 July 1999 Report on the RPSFS, for the Regional
Municipality of Ottawa-Carleton Planning and Environment Committee, from the
Engineering Division of the Environment and Transportation Department,
contains the recommendation that the Planning and Environment Committee
confirm staff’s response to Goulbourn Township’s conditions for a joint use
agreement. Staff endorsed the above condition. The Planning and Environment
Committee, and subsequently Regional Council, also did so.
The condition was intended to ensure that managers of the
RCA, either the Richmond Conservation Area Subcommittee (RCAS) of the
Goulbourn Environmental Advisory Committee, or its successor, the RCAMC,
would be consulted during the implementation of the RPSFS.
However, the RCAMC was not consulted on mitigation
requirements for the construction that has recently been undertaken at the
RCA. As a result, destruction of vegetation communities has occurred that
need not have occurred. (An area used by breeding Empidonax traillii
is of particular concern. No protective fencing was erected between this
area and the adjacent construction site on the berm of Cell B, and this has
resulted in the unnecessary destruction of part of the stand of Salix
shrubs where the species breeds.) Moreover, the conditions concerning
seeding and mulching, in the City of Ottawa Notice of Tenders, Richmond
Pumping Station and System Upgrades (Contract No. ETL01-2095) threaten to
make matters worse. If the conditions are followed then the impacted
vegetation communities will be replaced by non-indigenous plant communities
as a result of seeding and mulching efforts by the contractor. Can certain
conditions specified in the City of Ottawa Notice of Tenders, Richmond
Pumping Station and System Upgrades (Contract No. ETL01-2095) be altered to
prevent further damage to the RCA?
5. Mitigation of Impacts on Cell C
5.1 Screening of Floatables
The final plans submitted with the application for the
amendment to Certificate of Approval number 3-0834-83-006 should have
included designs for the screening of sewage bypassed to Cell C, and both
inlet structures for Cell C should have appurtenances, which function to
screen "floatables" from the sewage bypassed to the cell. Amongst the
conditions given in Goulbourn Township resolution 99-110, was the following:
"That steps will be taken to minimize the risk of undue contamination of the
lagoons by [means of] the Region . . . considering screening the sewage flow
into the lagoons . . .’. Staff endorsed this condition. The Planning and
Environment Committee, and subsequently Regional Council, strengthened it to
state: "The Region will undertake to research and determine the requirements
of screening of sewage discharges into the lagoons with a view to
implementation".
However, the final plans and specifications, submitted
with Certificate of Approval number 3-0834-83-006, include no designs for
appurtenances that would function to screen sewage discharges into Cell C.
Accordingly, no such appurtenances have been constructed during the
extension of either the 200 or the 500 mm diameter forcemain to the cell.
As a result, following testing of the 200 mm diameter
forcemain extension, used tampons and condoms were found littered about the
inlet structure. We expect the same result when the 500 mm diameter
forcemain extension is used, however, in that case, such "floatables" will
be distributed throughout Cell C.
An inquiry from RCAMC member, Mr. Peter Blancher,
concerning the situation described above led to the following staff response
on 14 November 2001 from Ms. Susan Murphy:
Based on information provided by our Consultant and
discussions with City's Operating Division with respect to screening of
overflows to the lagoon, it has been decided not to provide any permanent
screening facility for such overflows. The MOE does not require screening
for lagoons that are being used infrequently such as in the case of
Richmond. From an operating perspective our staff have indicated their
agreement with this approach. To install a mechanical system for something
that might only be used every few years is not an effective or efficient
approach. In fact, such a system could be detrimental in that it provides
another opportunity for a failure (plugging of the line, mechanical failure)
that could result in a bypass to the Jock River. The Operating Division has
indicated that their approach will be to closely monitor the facility during
use and to have staff conduct a clean up (raking, etc.) at the conclusion of
the event. Operations staff has indicated a desire to experiment with some
sort of "basket" arrangement once the contractor has completed their work
and turned the facility over to the City.
This raises the following questions:
(i) Who made the decision not to screen overflows? Since
it is the Council of the City of Ottawa, not the MOE, that has the authority
to decide what mitigation measures will be implemented for Cell C, insofar
as it is still part of the RCA, and not just a sewage works, was the council
consulted regarding the decision on screening? Why was the RCAMC, which has
been given the responsibility of managing the RCA by the Council of the City
of Ottawa, not consulted?
(ii) What designs for screening were assessed by the
staff of the city’s Operating Division in determining that screening is not
an effective or efficient approach? In undertaking this assessment, what
information on the performance of such designs, and the frequency of
mechanical failure or plugging, was reviewed by the city’s staff? Assuming
that such information has been reviewed, and given that two bypass pipes to
Cell C have been constructed, what is the risk, expressed as a conditional
probability, that both would fail during a bypass of a few hours?
What is the risk of such a failure during a bypass of two, three or five
days? On the assumption that Certificate of Approval number 3-0834-83-006
will not be further revised, so that Cells A and B remain part of Richmond’s
sewage facilities, if all four existing inlet structures for the Richmond
Lagoons were redesigned to provide for screening of sewage, what is the risk
of a complete system failure and bypass to the Jock River resulting from
that screening?
(iii) Why are experimental mitigation proposals, such as
the above referenced "basket arrangement", being tested after a bypass of
sewage to Cell C rather than before? Cannot staff undertake tests in other
lagoon facilities before using Cell C, and should this not have been done as
part of the detailed design stage of the implementation of the RPSFS?
Indeed, what research on, and evaluation of, the post-bypass clean up
approach was done during the detailed design stage for the RPSFS? What cost
assessments were done and what assessments of potential impacts on the
wetland habitat in Cell C?
(iv) How does staff propose that "floatables" be raked
from dense beds of Typha species?
(v) How is the "basket arrangement" supposed to function?
5.2 Draining of Sewage
A number of sources document the commitment to drain Cell
C after its use for sewage storage. Indeed the proposed solution to overcome
the Richmond Pumping Station overflow problem by bypassing sewage to Cell C
is repeatedly characterized in both the RPSFS and the ESR as temporary
sewage storage (e.g. ESR p. 3, §3; cf p. 15, rec. 6 and RPSFS pp. 19-20,
§6.3, p. 24, §6.4.1). This is also emphasized in the handout provided at the
public open house for the RPSFS, which states that storage will be
"temporary . . . over a short period of time (from a few hours to a few
days)" (ESR appendix D). The point was repeated at a meeting between
Regional staff and RCA managers on 7 May 1999, the minutes of which state:
Regional staff assured all that Cell C is for infrequent
and temporary storage only. The cell will only be used for the reasons
outlined in the study and the contents of the cell will be drawn back as
soon as is practical following an incident. (RPSFS appendix G)
Goulbourn Council Resolution 99-110 gives as a condition
for an agreement on the joint use of Cell C: "That Cell C will be emptied as
soon as is practicable immediately after any use for overflow". The 13 July
1999 Regional staff response to this condition, which was subsequently
confirmed by both the Planning and Environment Committee and Regional
Council, endorses it. The Request for Proposals for the implementation of
the recommendations of the RPSFS includes in the description of the scope of
the work to be undertaken: "Permit use of the Richmond lagoon Cell C as an
emergency bypass facility and allow for drainage back to the pumping station
following an event" (RFP No. 0200-91842-P08, p. 7).
However, the final plans and specifications, submitted
with Certificate of Approval number 3-0834-83-006, do not provide for the
draining of Cell C. Cell C was to have been drained by means of the 200 mm
diameter forcemain extension into its basin (RPSFS pp. 19-20, §6.3). But the
inlet structure represented in the final plans, which has now been
constructed on site, is not designed to permit the draining of Cell C to
less than 450 mm depth above the concrete pad on which the structure is
situated. Furthermore, since the structure is placed at that end of Cell C,
which is of highest elevation, sewage will remain in the cell at an average
depth greater than 450 mm. No efforts have been made to regrade the basin
given that it is now supposed to drain at the end opposite from that which
it previously drained.
Ms. Murphy’s correspondence of 14 November 2001 indicates
that following the bypass to Cell C, which is expected from 20 to 22
November, the sewage released into Cell C will be pumped out. This raises
the following questions:
(i) Is this how the staff of the city’s Operating
Division proposes to empty Cell C following all future bypass events?
(ii) Does staff also propose to use pumping, rather than
draining by gravity, in fulfilling its commitment to gradually reduce water
depths in Cell C, once or twice every year, for the purpose of managing the
wetland habitat in Cell C for migrating shorebirds?
(iii) If the answer to the above two
questions is affirmative, on what basis has staff concluded that pumping is
preferable to draining by gravity? Please answer this question taking into
consideration disruption to RCA operations and the respective costs of the
two alternatives. (The ESR indicates that, using a portable pump, each
pumping operation will cost $8,000 (ESR p. 16 and appendix B)). Again, if
the answer to the above two questions is affirmative, was the Council of the
City of Ottawa consulted on the decision in question? Why was the RCAMC not
consulted?
5.3 Restricting Public Access
We question why there have been no efforts to develop
protocols, in consultation with the RCAMC, concerning restrictions on public
access to Cell C during a sewage bypass. In particular, we observe that the
final plans submitted with the application for the amendment to Certificate
of Approval number 3-0834-83-006 include no designs for fencing around Cell
C. During completion of the RPSFS, Regional staff were insistent that Cell C
would have to be fenced once it was capable of being used for sewage
bypasses. Accordingly, the ESR states, "Cell C should be fenced in order to
protect the community from potential safety hazards" (ESR p. 15, rec. 12).
Indeed this document includes designs for ten fencing alternatives (ESR
appendix E). Furthermore, the 13 July 1999 report to Regional Planning and
Environment Committee recommends "construct fencing around the Richmond
Lagoon Cell C to address safety concerns", and this recommendation was
endorsed by both the Planning and Environment Committee and Regional
Council.
During completion of the ESR, and subsequent adoption of
conditions for a joint use agreement, the RCAS opposed fencing Cell C. Given
that the designs submitted with Certificate of Approval number 3-0834-83-006
include nothing on fencing, can the current RCA management organization, the
RCAMC, be assured that Cell C will not be fenced, and nor will any
combination of some or all of Cells A, B and C? If that is the case, will
the RCAMC be consulted on the development of protocols for restricting
public access during bypasses of sewage to Cell C?
6. Mitigation of Impacts on the Richmond Conservation
Area
6.1 Mitigation during Construction
6.11 Public Accessibility
Access to the RCA by heavy equipment, during
construction, should have been restricted to a single entrance along
Eagleson Road, either the Rideau Trail entrance or the existing parking lot.
However, both entrances along Eagleson Road have been used, resulting in
unnecessary impacts on the RCA. Both entrances now present RCA visitors with
exceedingly muddy trails, deeply rutted by large tire tracks. Why was the
RCAMC not consulted on protocols for minimizing this kind of impact during
construction? Will the entranceways be repaired once construction is
complete?
6.12 Public Safety
Deep pits have been left open and unattended, without
safety fencing, during the construction of both the 200 and 500 mm diameter
forcemain extensions. Why?
6.13 Worker Defecation
Although a portable toilet has been provided at the
existing parking lot, construction work at Cell C is a considerable distance
away. Workers have been using the trails surrounding Cell C. What
inspections by City of Ottawa staff will be undertaken to ensure that this
does not continue?
6.2 Mitigation after Construction
To mitigate impacts on the RCA resulting from the use of
Cell C as a sewage works, commitments were made to modify the Richmond
pumping station and forcemain to allow river water to be pumped into the
lagoon cells for habitat management purposes. Accordingly, the RPSFS states:
Modifications should be implemented at the pumping
station to supply water from the Jock River to the 200 mm diameter forcemain
to the lagoons . . . . These modifications should be co-ordinated with the
RCAS, as the facilities may occasionally be required to regulate water
levels in the lagoons. (RPSFS p. 34, rec. vi, cf p. iv, §7.5)
And it further states: "The piping system at the outlet
of the existing 200 mm diameter forcemain should be re-instated and modified
so that water can be directed to Cell A and Cell B" (RPSFS p. 34, rec. xi).
The ESR elaborates on these proposed mitigation efforts.
Table 4.2 of the ESR lists as concerns or potential impacts, resulting from
the bypassing of sewage to Cell C, the following: (i) "Cell C could be used
to store sewage over extended periods", (ii) "Proposed solution will
constrain future flexibility in regulating water levels in the lagoons" and
(iii) "Proposed solution may not be compatible with the Richmond
Conservation Area Management Plan". The response to or mitigating measure
for these potential impacts are given respectively as follows:
(i) Sewage will be drained back to the pumping station
following completion of a contingency event. Under a worst case scenario,
storage would be required for a period of about five days. It is estimated
that temporary storage would be required once every two or three years.
(ii) Proposed modifications to the Richmond Pumping
Station would permit water to be pumped from the Jock River to the Lagoons.
(iii) - Proposed solution would
require that objectives for Cell B and Cell C be exchanged, but overall
objectives for RCA can be maintained,
- Proposed modifications to pumping
station provides solution to fundamental RCA problem of how to regulate
water levels in the lagoons . . .
- Cell C use can be integrated into
RCA Management Plan but its primary use would be as a sewage works. (ESR
pp.12-3, table 4.2)
In view of the above, Goulbourn Council Resolution No.
99-110 states:
The Region shall provide for the purchase, installation
and operation of a system of pipes and pumps necessary to realise the
purposes of the RCA Management Plan. Schedules for pumping of water to the
three lagoons shall be coordinated between the Region and the Township in
accordance with the MOE guidelines.
The Regional Municipality of Ottawa-Carleton’s Planning
and Environment Committee, and subsequently, Regional Council endorsed this
condition, given an estimated cost of $40,000 for the purchase and
installation of pumps and pipes. We emphasize that the above commitments
were made at a time when geotechnical studies concerning the permeability of
soils underlying Cells A and B were already completed and the results
distributed to all concerned.
However, the 15 May 2001 minutes of the RCAMC record that
you recommended that the above mitigation efforts be delayed until the
permeability of Cells A and B could be further investigated. The proposed
delay has, for the most part, occurred. Further investigation into the
ability of Cells A and B to hold water has also occurred. Data collected
over the spring, summer and fall of 2001 reveal that despite drought
conditions, Cell B held water for 120 days. Analysis of this data (by Mr.
Blancher) indicates that loss of water can be entirely attributed to
evaporation and transpiration. However, at the 16 October meeting of the
RCAMC, you were again in attendance and advised that the $40, 000 purchase
of pumps and pipes still not be undertaken until it can be demonstrated in a
manner which is "scientifically irreproachable" that Cell B is sufficiently
impermeable to hold water for the purposes of the RCAMC. Thus the mitigation
efforts have again been delayed.
The following considerations lead us to question whether
this delay is justified:
(i) If the soils underlying Cell C are impermeable, that
would seem to give sufficient grounds for fulfilling of the commitment to
modify the pumping station; for the modifications were also supposed to
allow river water to be pumped to Cell C for habitat management purposes (ESR
p. 15, §6, rec. 1). In fact, the modifications were intended to allow water
to be pumped into Cell C for its management as a mudflat to attract
migrating shorebirds. Since Cell C is believed by City of Ottawa Operating
Division staff to have the ability to hold water, it should still be useable
by the RCAMC in management efforts to attract shorebirds during the spring
migration, if not the summer/fall migration also. Accordingly, the
modifications to the pumping station should not be made contingent on the
integrity of Cells A and B. Indeed the only mitigation effort, which could
justifiably have been made contingent on the permeability of either Cell A
or B, is the 200 mm diameter forcemain extension to Cell B, and that is the
only mitigation effort that has been done. Why has the extension to Cell B
been completed, given that staff maintains that Cell B will not hold water?
Why have the modifications to the Richmond Pumping Station that would permit
water to be pumped from the Jock River to the Richmond Lagoons not been
done, given that staff believes Cell C can hold water?
(ii) The commitment to modify the Richmond Pumping
Station in a manner that would permit water to be pumped from the Jock River
to the Richmond Lagoons was made to stakeholders, with Regional Council and
staff knowing that the question of both Cell A’s and Cell B’s ability to
hold water remained unanswered. The commitment was not conditional on this
question having been answered in accordance with the most rigorous standards
of evidence. There is now strong evidence, even if not the strongest
possible, for the assertion that Cell B holds water. Since the assertion
that Cell C is sufficiently impermeable to hold sewage is based on data from
four auger holes which are assumed to be representative of an area of
approximately 37, 500 m2,, we question why the most rigorous
scientific standards must be satisfied to justify an expenditure of $40, 000
to pump water into Cell B, while much less rigorous standards have been
applied in justifying an expenditure of $485, 000 to pump sewage into Cell
C. Why is the staff of the City of Ottawa’s Operating Division not applying
standards of evaluation commensurate with the costs and risks of the
proposed undertaking, as would seem to be only reasonable?
7. Consultation with Stakeholders and
the Joint Use Agreement
The supporting documentation submitted
with the application for amended Certificate of Approval number
3-0834-83-006 should have included a joint use agreement. This agreement was
to have been drafted in consultation with the managers of the RCA, either
the RCAS or its successor, the RCAMC. It was to have dealt with, inter
alia, operating procedures for the use of Cell C and detailed design
specifications for the infrastructure that would facilitate its use. It was
to have been completed as part of the detailed design stage of the RPSFS
process (ESR p. 15, rec. 13). Consultation during this stage of the process
was supposed to have involved the presentation of design alternatives for
RCA managers to assess (e.g. ESR p. 3, §3).
This is made quite clear in the RPSFS and the ESR. The
RPSFS states: "Any detailed design and operational criteria related to the
use of the lagoons should be established in consultation with the RCAS" (RPSFS
p. 34, rec. xiv; cf p. iv, §7.13). The ESR states: "The detailed design of
any works in the lagoon area should be carried out in consultation with the
Township and the RCAS" (ESR p. 15, rec. 4). It further states:
A shared use agreement for the lagoon
lands is currently being negotiated between the Region and the Township.
This agreement will respect the main recommendations of the RPSFM study, but
will provide additional detail on:
an operations protocol to minimize
impacts on the Conservation Area,
the cost-sharing of various measures
and
on the ownership and operation of
infrastructure (ESR p. 7, §4, cf p.15. rec. 5)
It says in addition: "The Township has indicated it is in
agreement with the major study recommendations subject to the
successful negotiation of a shared use agreement for the lagoon area" (ESR
p. 11, §4.4). Goulbourn Council Resolution No. 99-110 does indeed say this,
the relevant quotation having been given above. Furthermore, the 13 July
1999 Report to Planning and Environment Committee recommends that "the
Region and Township enter into a joint use agreement for the Richmond Lagoon
area". This recommendation was endorsed by Regional Council on 14 July 1999.
Admittedly, the joint use agreement was at first
conceived as a legal contract between the Regional Municipality of
Ottawa-Carleton and Goulbourn Township. Such a contract is no longer
necessary, or possible, given their amalgamation. However, the agreement has
since been conceived differently, as a detailed statement of understanding
for the operation of the lagoon lands, to be endorsed by the operations
staff at the City of Ottawa and the RCA managers. This is evidenced, for
example, by a letter from the Goulbourn ward councillor, dated 20 March
2001, well after amalgamation, which states that the agreement is still
being drafted and will contain the necessary references to the role of the
RCAMC. Accordingly, it has been the understanding of stakeholders concerned
with the RCA that, despite amalgamation, efforts were still being made to
complete the joint use agreement.
However, neither design alternatives nor proposed
operations protocols were ever presented to the RCAS or RCAMC during the
design stage of the RPSFS’s implementation, and the application for amended
Certificate of Approval number 3-0834-83-006 includes no joint use agreement
with the information submitted in support of the application. Will a joint
use agreement be completed to deal with questions concerning operations
protocols for the lagoons?
Conclusion
We observe that the application for the amendment to
Certificate of Approval number 3-0834-83-006, which you submitted to MOE,
indicates that the works for which the amendment has been made have
fulfilled all requirements of the Environmental Assessment Act through
completion of a Class A assessment. Given your considerable
involvement with the RPSFS, since 1999, and your position as project manager
for its implementation, you must be aware that the RPSFS was in fact done in
accordance with the requirements of a Class B assessment. In
fulfilling the requirements, there were significant commitments made to
stakeholders, most of which we have pointed out above. In view of these
commitments, your proposal to phase the implementation of the RPSFS
recommendations, as explained at the RCAMC meeting of 15 May 2001, makes no
sense. It is not possible to phase the project, so that the work necessary
for sewage storage is completed, and subsequently that necessary for
conservation is done. For the work necessary for sewage storage was supposed
to include mitigation measures for conservation. Indeed, in implementing the
RPSFS recommendations concerning sewage storage, the city’s consultant was
supposed to ensure that its detailed design proposals would satisfy the
requirements of the RCA Management Plan (RFP No. 0200-91842-P08, p. 8). This
has not been done. If you disagree, please explain why you disagree by
answering the questions, which we have posed above. For the time being, we
would ask that no further discharges of sewage on to RCA lands be allowed
until our concerns have been dealt with.
Sincerely,
Eric Snyder
for the Friends of the Jock River
Letter 2
December 11, 2001
Mr. Stephen Forestell,
Project Manager,
Richmond Pumping Station Upgrade,
City of Ottawa,
110 Laurier Ave. West,
Ottawa, ON
K2P 2L7
Mr. Forestell,
Re: The Richmond Conservation Area, the Richmond Pumping
Station and Forcemain Study and Amendment to Certificate of Approval Number
3-0834-83-006
We are writing in pursuit of the inquiries initially made
in our correspondence of November 16, a copy of which is attached. We have
as yet received no response, nor even an acknowledgement from you. We
understand that you have discussed some of our concerns in conversation with
Councillor Stavinga. We are also aware that you have provided a report to
the RCAMC in which you give written comments relating to a number of our
concerns. Nonetheless, we do not believe that you have answered most of our
questions. Therefore we are again asking those questions for which answers
have not yet been given.
However, before doing so, we would like to inquire about
an additional problem that has recently arisen. For some days this month
untreated sewage has been allowed to spill from Cell C into Cell B. As you
know, the RPSFS makes it clear that Cell B does not meet MOE standards and
should not be used for temporary sewage storage. Somehow no one thought to
obstruct the pipe between Cells C and B during the bypass of sewage to Cell
C. This is surprising since the ESR recommends removal of this pipe
altogether so as to prevent Cell B’s contamination. It is all the more
surprising, given that you inspected the Richmond Lagoon site on November 23
and, as project manager, must have known that this pipe was a concern. We
therefore ask: First of all, how has this been allowed to happen, and
secondly, what has been done by way of clean-up to ensure that the MOE will
under no circumstances view the contents of Cell B as sewage?
Our previously asked questions:
1. Status of Cells A and B
Will you undertake to ensure that Certificate of Approval
number 3-0834-83-006 shall be amended to state that only Cell C is to be
maintained and used as part of the Richmond pumping station and forcemain
facilities?
2. The 200 mm Diameter Forcemain Connection to Cell A
Is it the case that both the upstream and downstream
connection to Cell A were tested and found to be operational during the
Richmond Pumping Station Forcemain Study?
3. The 200 mm Diameter Forcemain Connection to Cell B
Why has the 200 mm diameter forcemain extension to Cell B
been completed during Phase 1? Does the staff of the City of Ottawa
Operating Division have any intention of using Cell B for storage of sewage
at any time?
4. Mitigation of Impacts on Cell B
Can you confirm in writing that, notwithstanding what is
specified in the City of Ottawa Notice of Tenders, Richmond Pumping Station
and System Upgrades (Contract No. ETL01-2095), no non-indigenous plant
species will be introduced to the RCA as a result of seeding and mulching
efforts by the City’s contractor?
5. Mitigation of Impacts on Cell C
5.1 Screening of Floatables
(i) Who made the decision not to screen overflows? Was
the Council of the City of Ottawa consulted regarding the decision on
screening? Why was the RCAMC not consulted?
(ii) What designs for screening were assessed by the
staff of the city’s Operating Division in determining that screening is not
an effective or efficient approach? In undertaking this assessment, what
information on the performance of such designs, and the frequency of
mechanical failure or plugging, was reviewed by the city’s staff? Assuming
that such information has been reviewed, and given that two bypass pipes to
Cell C have been constructed, what is the risk that both would fail
during a bypass of a few hours? What is the risk of such a failure during a
bypass of two, three or five days? On the assumption that Certificate of
Approval number 3-0834-83-006 will not be further revised, so that Cells A
and B remain part of Richmond’s sewage facilities, if all four existing
inlet structures for the Richmond Lagoons were redesigned to provide for
screening of sewage, what is the risk of a complete system failure and
bypass to the Jock River resulting from that screening?
(iii) Concerning the so-called basket arrangement
recently used during a bypass of sewage through the 200 mm diameter
forcemain inlet structure for Cell C (and apparently not as effective as
might be desired): Why did not staff undertake tests of this arrangement in
other lagoon facilities, before using Cell C, as part of the detailed design
stage of the implementation of the RPSFS? Since, in deeper water than that
currently in Cell C, floatables discharged within the recently used baskets
will presumably float, and therefore may not remain in the baskets, will
further tests be undertaken in deeper water conditions before significantly
larger quantities of sewage are released into Cell C? What alternatives to
the basket arrangement will be tested?
(iv) What research on, and evaluation of, the post-bypass
clean up approach was done during the detailed design stage for the RPSFS?
What cost assessments were done and what assessments of potential impacts on
the wetland habitat in Cell C? How does staff propose that "floatables" be
raked from dense beds of Typha species?
5.2 Draining of Sewage
In your report to the RCAMC you state the following
concerning the draining of Cell C:
The outlet structure for Cell C has been designed to
drain by gravity (siphon) back to the pumping station. This will drain the
lagoon down to 450 mm above the bottom of the lagoon. The reason for the 450
mm dimension is due to debris that sits on the bottom of the lagoon. It is
not unusual for there to be 200-300 mm of this debris. In order to ensure
that there is no plugging of the line, sufficient space has to be maintained
from the inlet to the bottom of the lagoon. There has been an allowance for
further lowering of the water in the lagoon. The outlet structure has a
plate that can be removed to allow water to be pumped back to the pumping
station through the use of a portable submersible pump. (File No.
19-97-0013-V)
We repeat our previous questions, revised accordingly:
(i) Will the staff of the city’s Operating Division empty
Cell C using a portable pump following all future bypass events? If so, to
what depth can Cell C be emptied after any such event? Since the above
referenced debris is a constituent of the sewage, and as such is supposed to
be emptied from Cell C along with the drainable constituents, can we be
assured that pumping will remove the debris?
(ii) Does staff also propose to use pumping, rather than
draining by gravity, in fulfilling its commitment to gradually reduce water
depths in Cell C, once or twice every year, for the purpose of managing the
wetland habitat in Cell C for migrating shorebirds?
(iii) If the answer to the above two questions is
affirmative, on what basis has staff concluded that pumping is preferable to
draining by gravity? Please answer this question taking into consideration
disruption to RCA operations, the respective costs of the two alternatives
and other options for preventing plugging of the forcemain. Again, if the
answer to the above two questions is affirmative, was the Council of the
City of Ottawa consulted on the decision in question? Why was the RCAMC not
consulted?
5.3 Restricting Public Access
Can the RCAMC be assured that Cell C will not be fenced,
and nor will any combination of some or all of Cells A, B and C at any
future time? If that is the case, will the RCAMC be consulted on the
development of protocols for restricting public access during bypasses of
sewage to Cell C? (We observe that for at least a month, a City of Ottawa
sign stating "Do not enter, waste water present" has been erected at the
Eagleson Road entrance to the RCA, which unnecessarily restricts access to
the entire Richmond Lagoon area, rather than just Cell C.)
6. Mitigation of Impacts on the Richmond Conservation
Area
6.1 Mitigation during Construction
6.11 Public Accessibility
Why was the RCAMC not consulted on protocols for
minimizing impacts during construction, such as those on the two Eagleson
Road entranceways and those on the berm of Cell B? Will the entranceways be
repaired once construction is complete? If so, when will repairs be
undertaken, and will the RCAMC be consulted on both the entranceway repairs
and mitigation for the Cell B berm?
6.2 Mitigation after Construction
In your report to the RCAMC you state:
We are proposing to submit a report to the Environmental
Services Committee on December 11, 2001 that will provide an update on the
status of the project and seek approval to undertake permeability testing of
the lagoons. Pumping Station modifications will be reviewed once testing (if
approved) of the lagoons is completed and a workplan has been identified.
(File No. 19-97-0013-V)
We therefore repeat the following questions:
(i) If the soils underlying Cell C are impermeable, that
would seem to give sufficient grounds for fulfilling of the commitment to
modify the pumping station; for the modifications were also supposed to
allow river water to be pumped to Cell C for habitat management purposes (ESR
p. 15, §6, rec. 1). In fact, the modifications were intended to allow water
to be pumped into Cell C for its management as a mudflat to attract
migrating shorebirds. Since Cell C is believed by City of Ottawa Operating
Division staff to have the ability to hold water, it should still be useable
by the RCAMC in management efforts to attract shorebirds during the spring
migration, if not the summer/fall migration also. Accordingly, the
modifications to the pumping station should not be made contingent on the
integrity of Cells A and B. Indeed the only mitigation effort, which could
justifiably have been made contingent on the permeability of either Cell A
or B, is the 200 mm diameter forcemain extension to Cell B, and that is the
only mitigation effort that has been done. Why has the extension to Cell B
been completed, given that staff maintains that Cell B will not hold water?
Why have the modifications to the Richmond Pumping Station that would permit
water to be pumped from the Jock River to the Richmond Lagoons not been
done, given that staff believes Cell C can hold water?
(ii) The commitment to modify the Richmond Pumping
Station in a manner that would permit water to be pumped from the Jock River
to the Richmond Lagoons was made to stakeholders, with Regional Council and
staff knowing that the question of both Cell A’s and Cell B’s ability to
hold water remained unanswered. The commitment was not conditional on this
question having been answered in accordance with the most rigorous standards
of evidence. There is now strong evidence, even if not the strongest
possible, for the assertion that Cell B holds water. Since the assertion
that Cell C is sufficiently impermeable to hold sewage is based on data from
four auger holes which are assumed to be representative of an area of
approximately 37, 500 m2,, we question why the most rigorous
scientific standards must be satisfied to justify an expenditure of $40, 000
to pump water into Cell B, while much less rigorous standards have been
applied in justifying an expenditure of $485, 000 to pump sewage into Cell
C. Why is the staff of the City of Ottawa’s Operating Division not applying
standards of evaluation commensurate with the costs and risks of the
proposed undertaking, as would seem to be only reasonable?
7. Consultation with Stakeholders and the Joint Use
Agreement
In your report to the RCAMC you state that, as a result
of amalgamation, a joint use agreement is no longer required. The events of
the last several weeks prove that a joint use agreement is required. Will a
joint use agreement be completed to deal with questions concerning
operations protocols for the lagoons?
Conclusion
In your report to the RCAMC you state, "If there are any
questions or concerns about what we are doing, please feel free to contact
us and we will do our best to answer your questions". We trust that the
Friends of the Jock River, which the Council of the City of Ottawa has
recently given a position on the RCAMC, will receive answers to its
questions.
Sincerely,
Eric Snyder
HOME |
BACK
|
|