Major sewage forcemain break
occurs in Richmond

June 19, 2002

              This is break...  "Number 5"               

"No clearer evidence is needed, to demonstrate that a Munster-Richmond forcemain
would convey unnecessarily high risks to the ---140-plus--- private, shallow wells
along the 11-kilometre pipeline route, and to the Richmond Fen."

The city has confirmed that a major sewer forcemain break occurred at about 2:30 pm Wednesday afternoon, June 19th, 2002. The rupture occurred in the newly installed “twin crossing pipes”, buried in the north shoulder of the Jock River.

City crews were seen arriving at the scene at about 7:30 pm, at which point about five hours of pumping volumes had been flowing into the Jock River. How many thousands of litres of sewage spilled to the Jock River has yet to be calculated.

     
 

Burst section of pipe at Y-connector location.

 

Closer view of fifth rupture to occur in the Richmond-GlenCairn forcemain

Evidence of erosion around these cracks in the pipeline, indicated that the forcemain had
been leaking sewage "over the span of several weeks or months" before its total failure.
(Quote from Environmental Hydraulics Group Inc, for David McManus Engineering Ltd.)

 
   

In the case of a similar high-pressure forcemain coming from Munster, the occurrence of slow leakage would represent a "worst case scenario". All residents with shallow wells would be at risk from life-threatening E-coli infection, through their own drinking water ...long before any alarms would sound. Residents deserve better than to be treated no differently than "test canaries in a coal mine".

                  THIS REPRESENTS A COMPLETELY UNNECESSARY
                                AND UNACCEPTABLE LEVEL OF RISK.

DON'T LET IGNORANT POLITICIANS AND BUREAUCRATS DO THIS TO YOU!

 

 

June 19 2002  forcemain break continued...

 
   

   

Flow was later diverted to Lagoon Cell “C”, and Sewer-Matic pump trucks commenced “cosmetic” mop-up procedures. The last pump truck was seen leaving the scene at about 5:45pm on Thursday, the 20th.

At about 6:30 pm on the 20th repairs were completed, and the excavation was refilled. Workers on the site were asked the cause of the break, and they stated that the cause was under investigation. It seemed strange that the said investigation would have to do without the hard evidence of the broken pipe, because it was left in the excavation, and was buried under the excavation re-fill material.

       

Photo at left, shows the 4-metre deep pit being filled up, after the twin pipelines were repaired.

Crescent on left side, shows the last visible portion of the broken pipe sections, that were buried during the refilling of the excavation.

This begs the question:
1.) Was the break due to a manufacturing flaw? (If YES, then: Why bury the evidence?)
2.) If not, then: Is human error, once again, the problem?


 

 

  To view other photos:  CLICK HERE


This episode only feeds the controversy surrounding Public concerns regarding the city’s profound lack of wisdom in proposing a pipeline to carry Munster’s Sewage to Richmond.

If a brand new section of pipeline ---just a few dozen metres in length--- ruptures TWICE, in its
first seven months, imagine the risk created by a 1700-metre pipeline span through the Fen!
  
Richmond Fen

No clearer evidence is needed, to demonstrate that a Munster-Richmond forcemain would convey unnecessarily high risks to the ---140-plus--- private, shallow wells along the eleven-kilometre pipeline route, and to the Richmond Fen.

How far is the city intending to stray away from Best Management Practices, its fiduciary duty to ratepayers and the sound environmental science and engineering ...which it has been entrusted to fulfill?

How long does the city intend to obsessively promote ---for all the wrong reasons--- such unwarranted risks to the environment, and public health and safety, (as those generated by a Munster-Richmond pipeline)?
One Insider's Observation

The city's irresponsibility becomes especially evident, in view of the pipeline's $23 million life-cycle price tag. When you consider that a perfectly risk-free local system, without a pipeline, and without solids-retention lagoons, can be utilized ---which has a life-cycle cost of $5.9 million ...where's the city's accountability? Where's its logic?   So far, ratepayers have not received the slightest semblance of a public accounting, or rationale.
Example of the ONSITE TREATMENT SYSTEM

In the wake of preceding pipeline disasters, such as the 50-million dollars wasted on the Ottawa South Collector, for which there has never been a public forensic accounting, the whole city’s Wastewater Infrastructure Operations Department "has waving red flags all over it",  calling out, the urgent need for a highest level forensic investigation.

Such wanton disregard for the public interest, environmental stewardship, and trust with the public purse, presently appears to border on the criminal.

Residents should demand an immediate halt to the city’s reckless course of action, and insist on the more prudent, onsite treatment plant for Munster …or otherwise, demand that a public judicial (forensic) inquiry be launched, forthwith.


   

Public Kept in Dark About Solids-Retention  |  Two Lagoon Spills in Four Months   |  One Insider's Observation  | Correspondence History

    BACK  |  CLOSE WINDOW 
 

___________________________________________________________________________

OttawaSewergateFiasco.com