|
(Highlighting added)
EXCERPTS |
McManus Engineering found evidence of slow forcemain leaking
"over the span of several weeks or months".
|
hydraulic transient analysis
OF THE
richmond pump station and forcemain
AND
break investigation
–
jock river crossing
IN THE
city of ottawa, ontario, canada
Prepared for
David McManus
Engineering
Limited
Nepean,
Ontario,
Canada
Prepared by
Environmental Hydraulics Group Inc.
18 Crown Steel Drive, Unit 113
Markham, Ontario, L3R 9X8
ehg(g),ehg-inc. com
www.ehg-inc.com


David McManus
Engineering Ltd
The records above indicate a number of points
1. There was no appreciable "spike" in pressure recorded at the
pumping station prior to either failure. This indicates that
failure was not the result of a sudden
increase or decrease of pressure at the pumping station. The delay
in the failure time for the two "Y"s may be attributable to a
deterioration in the
condition of the pipe material through fatigue. Alternatively the
failure may
have been caused by a local catastrophic increase in pressure
created by a
transient surge wave, possibly exacerbated by trapped air.
Incorrect operating
of the air release valves may have contributed to this possible
failure scenario.
2. The pressures in the system are broadly in line with the
pressures indicated in
the 1998 forcemain study and within the
limits of the design criteria.
3. The soft start motor installed on the 75 HP pump has
appreciably reduced the pressure envelope under which the
forcemain operates. This can be expected
to significantly reduce surge pressures and
contribute to the extended life of
the forcemain.
4. The pumps have been operating on 12 minute cycles; i.e.
5 per hour. This short pump shut down/start up time may be
insufficient to allow transient
surge waves to dampen and dissipate
completely. The initial transient analysis
undertaken by Proctor and Redfem recommended
a minimum of 10 minutes
before pump start up follows shutdown.
4.0 Conclusions
The pressure/flow data
from Richmond Pumping Station indicate that the forcemain system
has been operating well within the design parameters of the
polyethylene and PVC pipes
including the PVC "Y"' s.
The_reaspns for the failure of the "Y"' s are therefore not
clear at this stage. A number of
theories have been
postulated:-
1. The PVC Y fittings were either
defective or damaged on installation.
2.
The thrust blocks used to support the fittings were incorrectly
sized or
in the wrong location.
3. Air is being introduced into
the system at the location of the crossing
and is not able to escape, exacerbating the pressure surges during
pump shut down and start up.
I
4. The change in geometry of the forcemain has introduced
more fittings
where air may be drawn into the system
5.
The operation of the pumps without a
"soft starter" increased the
severity of the transient waves and contributed to a fatigue failure.
Several methods of repairing the system
have been proposed including replacing
the PVC "Y"'s with a higher strength
material such as cast iron, hyprescon or higher
specification PVC. It is our
opinion that to design a repair is premature until more work
has been done to identify precisely why failure occurred in the "Y'"s.
Richmond Pumping
Station Upgrading
Project
Report on Failure of PVC "Y"s
David
McManus Engineering
Ltd.
for
the City of Ottawa Ontario, Canada
Hydraulic Transient Analysis of
the
Richmond Sewage Pump-Station and Forcemain
-
Including Break Investigation at Jock River
Crossing
number is in
line
with Trow's estimate, based on a simpler formula, of
approximately 10,000 Ibs
(based on 80
psig steady pressure).
Since
transient
pressure cycles
were
to be expected
in this system,
the
basis for
designing the thrust block
must consider
hydraulic transient pressures (which requires a
hydraulic
transient
analysis as
presented
in
Section
4 and
which not all designers
do
in standard
practice)
and,
ideally,
transient forces
(which most
designers seldom consider). EHG's experience
in
other
jurisdictions is
that smaller
diameter forcemains are often split to two inside a MH structure
prior
to a
crossing,
which
provides
the
required rigidity and anchorage
but
is not as
feasible
for
larger
forcemains
such as the
subject system. In other cases,
a
vault is
provided for the split
and
an air
release
valve and MH is provided
at the change
in profile-just prior
to
going
under the
river.
The
transient
thrusts
applied in the longitudinal direction (x on the
figures)
immediately decrease
(along with system
pressure)
after a power failure but then increase and reach maximum
values
which
far exceed 10,000 Ibs
and which, in
the two 200 HP pump case, change direction
very
rapidly several times (x
switches from
positive to negative
on
the bottom
graph).
EHG
understands
that
a "filter
cloth"
of some kind was installed between the concrete thrust block
and
the
PVC Y-
fitting.
Further,
the
thrust block
did not enclose the fitting but only
provided
contact
for
about half
of its
circumference.
Finally, it
does
not
appear that
thrust
block
restraint
was,
provided to prevent
longitudinal
motion
of the
pipe.
In wet soil
conditions
and
with repeated
pressure (expansion-contraction) and thrust (longitudinal
motion) cycling,
it is
possible
the
pipe could
have
moved
a few mm
back
and forth
over
time.
This
remains
true
even
if one allows
for some restraint by friction at the compression gaskets
and
due
to surrounding soils. Indeed, IPEX
correspondence
(after the break) indicates the
spigot was
found
pushed
all
the way
into
contact
with the PVC
bell, not separated by some
clearance as
installation standards followed by CAGE
construction
require. Since the lateral branch
can not
move in a longitudinal direction as
readily as the
straight-through branch of the
Y, this
motion
provides a
mechanism for
crack
initiation and growth and, ultimately, liquid
leaks
and
the
uncontrolled release of
air.
EHG and
DMEL
staff visited with
CAGE
'Construction and
inspected one of
the
broken Y-
fittings kept in their construction yard.
Small hairline
cracks
were observed
and
photographed
along the dividing point on the outside of the pipe
fitting
(Figure 4, top).
A photograph showing
what appears to be external erosion of the PVC plastic pipe wall
(due
to a
leak) was also
examined.
It
was apparent that pressurized liquid and sand/silt
escaping
the
system through
a crack eroded the plastic material in a fan shape, likely
over the span of several
weeks or months
(Figure
4, bottom). With time, the crack likely grew bigger gradually
and
the
PVC material eroded by
the leak weakened the Y- fitting (as the pipe wall became
thinner).
This
evidence confirms
that a crack
occurred
on
the
downstream
Y- fitting.
|
Environmental Hydraulics Group Inc.
16
August 2003 |
|