Table 23:  Life cycle cost comparison – onsite vs pipeline

Item

Onsite Plant

Pipeline

Ratio  Pipe/Onsite

Material & installation

3,245,519

14,614,957

4.5

Refurbishment

1,233,292

6,082,332

4.9

Annual O, M & R

94,735

338,758

3.6

Life Cycle Cost

5,905,139

22,958,140

3.9

Uniform annual cost

243,294

945,884

3.9

 

Source:  Independent Citizen's Review of the Munster Sewage Project (November, 2002):