| |
A few of the Conclusions and Comments
to the Third Munster Wastewater Evaluation
contributed by Expert Witnesses, Proponents Public,
"Interested Parties", Informed
Observers
November - 2002
This page contains links to a few of the
informed comments and concerns submitted to the "2002 Evaluation Group", regarding Munster's
wastewater treatment evaluation chaos,
to provide input to the (2002), third re-evaluation, ordered by the Ontario Municipal Board.
Here is a sampling of the inputs:
- Engineers' Statement of Agreements and Disagreements (OMB
Order No. 1012 Issued July 12/2000):
This
important document was supplied to the "Third Evaluation Group"
because it represents the point where the OMB left off. Note
that the Appellant's Expert Engineering Witness for the onsite
treatment plant was able to directly answer every issue. After
all, that is what is expected of a "Requests for Proposals"
(RFP) bidder, who invests in a legitimate, qualified, bid submission. It is
readily apparent, by reading this document, that the Engineering
Witnesses for the RMOC (City), often failed to give full
rationales for their disagreements; they just chose to
"disagree".
This was especially noticeable, when the engineers were ordered
by the Chair of the OMB Hearing, to re-calculate the cost of rock removal, based on
new rock borehole evidence which was presented at the Hearing.
(The attached document [see: Sec. 4.1.8, and Sec. 4.1.11] will
show how the City's consultants appeared uncooperative in
dealing with the task). Furthermore, when asked to respond, with answers to
issues that should have been resolved going into the "Design
Build" RFP bid process, (vitally important issues such as
overall costing, land use planning considerations, pipeline risks to the environment, extent of lagoon use, forcemain
breakage risk protection for shallow wells, and many others),
the City's consulting engineers appeared evasive and inconclusive.
As a result, every difficult issue, with regard to the pipeline, remains
unanswered, and would still have to be resolved at the design or
construction stage, including even the pipeline sizing, the
route through Richmond and, of course, its full cost. This was
not what Munster and Richmond residents wanted or were led to
believe would happen, nor did it conform to the spirit or the
function of a properly conducted RFP
process. (In regard to the RFP process, litigation is still
pending, over the City and its Consultant allegedly acting in
bad faith by soliciting and accepting non-compliant pipeline RFP
bids, by rigging a pipeline selection through unwarranted
manipulation of the compliant RFP bids, and by carrying out a flawed and overly
subjective ranking of the evaluation criteria - as noted in the
Evidence, and Decision of the OMB Hearing.)
CLICK HERE
- The Friends of the Jock River:
This is a volunteer
organization. Their primary mission is the wellbeing of the Jock
River watershed. For this organization to come out so strongly in favour
of an on-site treatment plant for Munster, and opposed to a
pipeline, speaks volumes about which alternative is better for
the aquatic habitat and surrounding environment. As taxpayers, the group is also concerned about the
apparent waste of taxpayers' money. The following excerpt from their Spring 2002,
Newsletter was also sent to the evaluation group:
CLICK HERE
- Jeffrey White, P.Eng., President of Watertek Corp:
A proponent
of the "Snowfluent" bid, Mr. White was an expert witness at
the OMB Hearing. He demonstrated superior expertise in pipeline
technology, and
raised many questions regarding the pipeline's inappropriate application for
Munster, which could not be answered by the city's engineering
consultants. Following, is
the summation of his observations regarding the city's
performance in this whole process:
CLICK HERE
- Independent Citizen's
Review of the Munster Sewage Project (November,
2002):
To
view 107-page Adobe File:
CLICK HERE
(Others to follow) |
|